The scope of this cable works was as follows, it was drilled two shafts, NO. 1 shaft (${\phi}6.8m{\times}31m$), NO.2 shaft (${\phi}6.8m{\times}33m$), ) and it was connected two shaft in Tunneling. The first, it was needed to investigate the surey of influenced of vibration and noise by blastig to near by housing structure. 2nd, it was essential to decide the boundary line of influenced for agriculture water and portable water, by draw down of underground water. Blasting works has been done successfully without any problem, but by draw down of underground water, with in 250m level from #1 shaft, agriculture well drilled 8 place and portable water well drilled 7 place for near by farmers.