A Case Study on Minimizing Contract Amount Adjustments due to Design Changes in Defense and Military Facility Projects

국방·군사시설 사업의 설계변경 계약금액조정 최소화를 위한 사례연구

  • Cho, Sung-joon (Department of Military Science, Cheongju University) ;
  • Lee, Kyoung-han (Southern Gyeonggi Province for the Defense Installations Agency) ;
  • Lee, Myung-sik (Department of Architectural Engineering, Dongguk University) ;
  • Park, Bong-gyu (Department of Military Science, Cheongju University)
  • 조성준 (청주대학교 군사학과) ;
  • 이경한 (국방시설본부) ;
  • 이명식 (동국대학교 건축공학과) ;
  • 박봉규 (청주대학교 군사학과)
  • Received : 2024.01.15
  • Accepted : 2024.04.17
  • Published : 2024.07.31

Abstract

In defense and military facility projects, adjustments to contract amounts due to design changes directly or indirectly affect factors such as increased construction costs and extended construction periods. Moreover, they can lead to differences of opinion and conflicts between the military and contracting parties. This case study analyzed the integrated management of defense and military facility projects by the Gyeonggi Southern Facilities Division, which oversees projects in Seoul and the southern Gyeonggi Province region for the Army, Navy, Marine Corps, and Air Force. Out of 388 completed projects, 103 cases with design changes were selected for analysis, aiming to ensure the reliability of data regarding the proportion of design changes in project completion. The study classified samples by the causes of design changes specified in the Ministry of Planning and Finance's contract regulations, assigning rankings based on the occurrence rates of each cause. Furthermore, it analyzed detailed factors for each cause of design change and derived implications to propose improvement measures. Considering the limited access to military primary data, this case study is expected to contribute to minimizing design changes in defense and military facility projects. Additionally, it is anticipated to be practically useful for subsequent research on contract amount adjustments resulting from design changes.

국방 및 군사시설 프로젝트에서는 설계변경으로 인한 계약금액 조정은 공사 비용의 증가와 공사 기간의 연장 등에 직접 또는 간접적인 영향을 미친다. 또한, 이는 군과 계약 당사자 간 의견 차이와 갈등으로 이어지기도 한다. 본 사례연구는 서울과 경기도 남부지역에서 육군, 해군, 해병대, 공군의 국방 및 군사시설 사업을 통합 관리하는 경기남부시설단 추진사업을 분석한 것이다. 본 사례연구는 공사가 완료된 388건의 프로젝트 중 설계변경이 이루어진 103건을 표본으로 분석하였다. 이를 통해 프로젝트의 완결에서 발생하는 설계변경 비율 등에 대한 신뢰성을 확보하고자 하였다. 본 사례연구는 기획재정부 계약예규 공사계약 일반조건에서 규정하는 설계변경 발생 원인별로 표본을 분류하고, 각각의 원인별로 발생률에 따른 순위를 부여하였다. 또한, 각각의 설계변경 발생 원인별 세부 요인을 분석하고 시사점을 도출하여 설계변경 발생 원인에 대한 개선 방안을 제시하였다. 이러한, 사례연구는 군의 원천자료 접근에 제한성이 있는 특수성을 고려해 볼 때, 국방 및 군사시설 사업에서 설계변경을 최소화되도록 하는데 기여 할 것을 기대한다. 아울러, 설계변경에 따른 계약금액 조정 등에 관한 후속 연구 등에 실증적으로 유용할 것이다.

Keywords

Acknowledgement

본 사례연구에 함께 참여해 준 이경한 박사(국방시설본부 경기남부시설단장)과 연구논문을 세심하게 지도 해주신 동국대학교 이명식 교수님, 청주대학교 박봉규 교수님께 감사의 마음을 다시 한번 전해 올립니다.

References

  1. Armed Forces Printing Window (2014). "Dictionary of Military Facilities Terminology." Standard Design Drawing, p. 438.
  2. Cho, Y.J. (2020). "Effective Handling of Construction Disputes for Strengthening the International Competitiveness of the Construction Industry." Korean Journal of Construction Engineering and Management, KICEM, 21(4), pp. 3-11.
  3. Defense Installations Agency (2022). "Minutes of the Project Promotion Meeting." 6th in 2022 , Number of military facility construction projects in Seoul and southern Gyeonggi Province.
  4. Defense Installations Agency (2023). "Rules of Defense Installations Agency." Referring to Article 25 of the Construction Project Management Regulations .
  5. Im, C.S., and Lee, G.C. (2004). "The Influence of Construction Cost by the Variation of Design." Journal of Architectural Institute of Korea . AIK, 20(11), pp. 107-114.
  6. Jung, W.S., and Lee, M.J. (2016). "A Study on Change Order Factor Analysis for Military Facility Projects." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 127-134.
  7. Kim, S.W., Nam, H.W., Lee, J.S., Shin, C.H., and Chun, J.Y. (2009). "Case Survey and Analysis for Proper Design Changes Management." Proceedings of the Annual Conference of the Architectural Institute of Korea , Kangwon University, Seoul (Korea): Architectural Institute of Korea, pp. 605-608.
  8. Kim, S.H. (2011). "The Rationalization of Contract Sum Adjustment through Case Study of Price Fluctuation Adjustment Based on Index Adjustment Method." Korean Journal of Construction Engineering and Management. KICEM, 12(4), pp. 70-78.
  9. Kim, I.H. (1994). "A Study on the Methodology of Rational Planning and Decision of Military Facility Construction Cost." Journal of Architectural Institute of Korea . AIK, 10(6), pp. 13-20.
  10. Kim, C. (2019). "Consideration on Adjustment of Contract Amount Due to Design Change of Public Construction Works, Focusing on the Act on Contracts with Local Governments as Parties." Wonkwang University, (forLight Law, Volume 35, No. 3), pp. 215-237.
  11. Korea Commercial Arbitration Board (2019). A Book of Precedents: Classification of Arbitration Cases by Factors, p. 8.
  12. Lee, H.S., Jung, M.G., Park, M.S., and Son, B.S. (2010). "Cost Estimation for Public Facilities at Early Stage Using Functional Area Cost: Focusing on Army Barracks." Korean Journal of Construction Engineering and Management. KICEM, 11(6), pp. 3-13.
  13. Lee, K.H., and Lee, M.S. (2005). "Improvement of Contract Amount Adjustment in the Public Construction Sector: Focused on the Cases of Korea Army Central Contract." Dongguk University, Seoul (Korea), pp. 52-68.
  14. Lee, K.H., and Choi, J.S. (2013). "Causes of Change Orders in the Military Facility Construction Projects and Suggestions for Improvement." Journal of The Korean Institute of Building Construction, KIC, 13(3), pp. 263-271.
  15. Ministry of Strategy and Finance (2021). "Contractual Regulations 581." Referring to Articles 2 and 19 of the General Conditions of the Construction Contract (Partial Revision 2021).
  16. Park, G.S., Jin, S.H., and Kim, Y.S. (2000). "A Study on the Development of Change Order Management System for SOC (Social Overhead Capital) Projects." Journal of Architectural Institute of Korea . AIK, 20(1), pp. 427-430.
  17. Park, W.H., and Paek, J.H. (2009). "A Study on Design Additional Fee Estimation by Change Order." Proceedings of the Annual Conference of the Korean Institute of Building Construction. 9(1), pp. 155-158.
  18. Park, J.W., Son, B.S., and Lee, H.S. (2005). "A Budget Estimation Model for Military Facility Construction Using Cost Index." Journal of the Architectural Institute of Korea . AIK, 21(2). pp. 111-121.
  19. Park, I.S., Kim, H.R., Lee, H.J., Kim, D.H., Min, Y.G., and Cho, H.H. (2021). "Analysis of Causes and Impact of Change Orders in U.S. Military Construction Projects." Journal of The Korean Institute of Building Construction, KIC, 21(3), pp. 213-219.
  20. Public Procurement Service (2021). Press Release on the Unstable Supply and Demand of Reinforced Steel, Public Procurement Service.