• Title/Summary/Keyword: Offshore wind power plant

Search Result 31, Processing Time 0.03 seconds

Fault Response of a DFIG-based Offshore Wind Power Plant Taking into Account the Wake Effect

  • Kim, Jinho;Lee, Jinsik;Suh, Yongsug;Lee, Byongjun;Kang, Yong Cheol
    • Journal of Electrical Engineering and Technology
    • /
    • v.9 no.3
    • /
    • pp.827-834
    • /
    • 2014
  • In order to meet the low voltage ride-through requirement in a grid code, a wind power plant (WPP) has to stay connected to a grid, supporting the voltage recovery for a grid fault. To do this, a plant-level controller as well as a wind generator (WG) controller is essential. The dynamic response of a WPP should be analyzed in order to design a plant-level controller. The dynamic response of a WPP for a grid fault is the collective response of all WGs, which depends on the wind speed approaching the WG. Thus, the dynamic response of a WPP should be analyzed by taking the wake effect into consideration, because different wind speeds at WGs will result in different responses of the WPP. This paper analyzes the response of a doubly fed induction generator (DFIG)-based offshore WPP with a grid fault taking into account the wake effect. To obtain the approaching wind speed of a WG in a WPP, we considered the cumulative impact of multiple shadowing and the effect of the wind direction. The voltage, reactive power, and active power at the point of common coupling of a 100 MW DFIG-based offshore WPP were analyzed during and after a grid fault under various wind and fault conditions using an EMTP-RV simulator. The results clearly demonstrate that not considering the wake effect leads to significantly different results, particularly for the reactive power and active power, which could potentially lead to incorrect conclusions and / or control schemes for a WPP.

The Case Study on the Niche Experimentation in Offshore Wind Renewable Energy Transition (해상풍력 기술의 사회-기술시스템 전환과정에 관한 탐색적 사례연구)

  • Kim, Bonggyun;Kim, Dukyoung;Kim, Kyungnam;Kim, Donghwan
    • Journal of Korea Technology Innovation Society
    • /
    • v.17 no.2
    • /
    • pp.355-379
    • /
    • 2014
  • For the transition to the low carbon society, it is inevitable but difficult journey that the new energy technology spread co-exists with formal social system. The objective of offshore wind power plant that has been implemented by the government is to connect large capacity new renewable energy to the central electric power system. Therefore, for the successful introduction of offshore wind power system, the transition of the formal social technology system should be companied. This study analysis the energy system transition about niche strategy adjustment using Multiple Level Perspectives & Strategic Niche Management. It also multi level analyzes and structuralizes the process that new technology, as a research result, evolves through connecting and communicating with formal regime and landscape. Also, adjusting Strategic Niche Management, it diagnoses the obstructive factors in the initial stage of niche experiment and found the major reasons why offshore wind power test plant had been delayed. Through this study, it reaches to the practical implication that offshore niche technology could grow stably in the energy system and various policies.

A study on Design of Generation Capacity for Offshore Wind Power Plant : The Case of Chonnam Province in Korea (해상풍력 발전용량 설계에 관한 연구 : 전남사례를 중심으로)

  • Jeong, Moon-Seon;Moon, Chae-Joo;Chang, Young-Hak;Lee, Soo-Hyoung;Lee, Sook-Hee
    • The Journal of the Korea institute of electronic communication sciences
    • /
    • v.13 no.3
    • /
    • pp.547-554
    • /
    • 2018
  • Wind energy is widely recognized as one of the cheapest forms of clean and renewable energy. In fact, in several countries, wind energy has achieved cost parity with fossil fuel-based sources of electricity generation for new electricity generation plants. Offshore wind energy development promises to be a significant domestic renewable energy source for the target of korea government 3020 plan. A pivotal activity during the development phase of a wind project is wind resource assessment. Several approaches can be categorized as three basic scales or stages of wind resource assessment: preliminary area identification, area wind resource evaluation, and micrositing. This study is to estimate the wind power capacity of chonnam province offshore area using three basic stages based on the six meteorological mast data. WindPRO was used, one of a well-known wind energy prediction programs and based on more than 25 years of experiences in development of software tools for wind energy project development. The design results of offshore wind power generation capacity is calculated as total 2.52GW with six wind farms in chonnam offshore area.

Optimization of Grid Network for Offshore Wind Power Plant (해상풍력발전단지의 전력망 구성의 최적화에 관한 연구)

  • Moon, Won-Sik;Jo, Ara;Kim, Jae-Chul;Bae, In-Soo;Yoon, Gi-Gab;Park, Sang-Ho;Choy, Young-Do
    • Proceedings of the KIEE Conference
    • /
    • 2015.07a
    • /
    • pp.1094-1095
    • /
    • 2015
  • The costs of installation, loss, and energy not supplied energy for submarine cable of offshore wind power plant (OWPP) are very high because the level of technology is still in the early stage as well as because of the marine environments. Therefore, reducing the total costs of a grid network for OWPPs is very important for financial feasibility. In particular, it is needed to minimize the project cost for optimizing the grid design and offshore substation location of a OWPP. The suggested method can reduce the total system cost and make it lower compared with existing methods.

  • PDF

Validation study of the NCAR reanalysis data for a offshore wind energy prediction (해상풍력자원 예측을 위한 NCAR데이터 적용 타당성 연구)

  • Kim, Byeong-Min;Woo, Jae-Kyoon;Kim, Hyeon-Gi;Paek, In-Su;Yoo, Neung-Soo
    • Journal of the Korean Solar Energy Society
    • /
    • v.32 no.1
    • /
    • pp.1-7
    • /
    • 2012
  • Predictions of wind speed for six different near-shore sites were made using the NCAR (National Center for Atmospheric Research) wind data. The distances between the NCAR sites and prediction sites were varied between 40km and 150km. A well-known wind energy prediction program, WindPRO, was used. The prediction results were compared with the measured data from the AWS(Automated Weather Stations). Although the NCAR wind data were located far away from the AWS sites, the prediction errors were within 9% for all the cases. In terms of sector-wise wind energy distributions, the predictions were fairly close to the measurements, and the error in predicting main wind direction was less than $30^{\circ}$. This proves that the NCAR wind data are very useful in roughly estimating wind energy in offshore or near-shore sites where offshore wind farm might be constructed in Korea.

Analysis of fault current in offshore wind farm ccording to the grid connection method (해상풍력 발전단지의 전력망 연계방식에 따른 고장전류 분석)

  • Ahn, Jin-Hong;Kim, Eel-Hwan
    • Journal of IKEEE
    • /
    • v.24 no.3
    • /
    • pp.691-698
    • /
    • 2020
  • The installation cost or the magnitude of the fault current varies depending on the grid connection method of the offshore wind farm. Therefore, there is a need for an efficient power grid connection method considering the capacity and location of the complex. In particular, most power cables in offshore wind farms use 3-core considering cost and efficiency. In the event of a failure such as a short circuit, the entire cable must be replaced, which can lead to significant losses in terms of cost, considering repair costs and turbine downtime. Therefore, in this paper, a radial, ring, and molding method is introduced into a 100 MW wind farm to be installed at Jeju offshore, and a three-phase short circuit failure is performed using a PSCAD/EMTDC program to perform computer analysis. I would like to propose a suitable power grid connection method.

Assessment of Offshore Wind Power Potential for Turbine Installation in Coastal Areas of Korea (터빈설치를 위한 한국 연안 해상풍력발전 부존량 평가)

  • Kang, Keum Seok;Oh, Nam Sun;Ko, Dong Hui;Jeong, Shin Taek;Hwang, Jae Dong
    • Journal of Korean Society of Coastal and Ocean Engineers
    • /
    • v.30 no.4
    • /
    • pp.191-199
    • /
    • 2018
  • In this paper, wind data at 20 locations are collected and analyzed in order to review optimal candidate site for offshore wind farm around Korean marginal seas. Observed wind data is fitted to Rayleigh and Weibull distribution and annual energy production is estimated according to wind frequency. As the model of wind turbine generator, seven kinds of output of 1.5~5 MW were selected and their performance curves were used. As a result, Repower-5 MW turbines showed high energy production at wind speeds of 7.15 m/s or higher, but G128-4.5 MW turbines were found to be favorable at lower wind speeds. In the case of Marado, Geojedo and Pohang, where the rate of occurrence of wind speeds over 10 m/s was high, the capacity factor of REpower's 5 MW offshore wind turbine was 56.49%, 50.92% and 50.08%, respectively.

The Analysis of Active Power Control Requirements in the Selected Grid Codes for Wind Farm

  • Kim, Mi-Young;Song, Yong-Un
    • Journal of Electrical Engineering and Technology
    • /
    • v.10 no.4
    • /
    • pp.1408-1414
    • /
    • 2015
  • The renewable energies such as photovoltaic power, wind power and biomass have grown to a greater extent as decarbonization techniques. The renewable energies are interconnected to power systems (or electrical grids) in order to increase benefits from economies of scale, and the extra attention is focused on the Grid Code. A grid code defines technical parameters that power plants must meet to ensure functions of power systems, and the grid code determined by considering power system characteristics is various across the country. Some TSO (Transmission System Operator) and ISO (Independent System Operator) have issued grid code for wind power and the special requirements for offshore wind farm. The main purpose of the above grid code is that wind farm in power systems has to act as the existing power plants. Therefore wind farm developer and wind turbine manufacturer have great difficulty in grasping and meeting grid code requirements. This paper presents the basic understanding for grid codes of developed countries in the wind power and trends of those technical requirements. Moreover, in grid code viewpoint, the active power control of wind power is also discussed in details.

A New Structure of Communication System for Monitoring and Control of Heterogeneous Wind Tubines (이종 풍력 터빈의 감시 제어를 위한 통신 시스템 구조)

  • Kim, Tae-Hyoung;Hwang, Tae-Ho;Ham, Kyung-Sun
    • Journal of The Institute of Information and Telecommunication Facilities Engineering
    • /
    • v.10 no.1
    • /
    • pp.40-45
    • /
    • 2011
  • As increasing the importance of renewable energy recently, the scale of a wind power plant is increasing to the number of GW scale and specially, it is trend to move from onshore to offshore to use the higher quantity and quality of wind. Consequently to meet the trend, it is largely considered the importance of communication protocol to control and monitor remotely. But, because the communication protocol between the control center and a wind turbine has been independently developed by each wind turbine vendor, it is absence of the compatibility and extensibility when the heterogeneous wind turbines are installed in the wind farm. The IEC 61400-25 is the specifying standard for these problems in Europe. In this paper, we will show the state of these problems and present a new structure of communication based on the IEC 61400-25 to get the compatibility and extensibility between a control center and wind turbines.

  • PDF

An Experimental Study on Dynamic Performance of Large Floating Wave-Offshore Hybrid Power Generation Platform in Extreme Conditions (대형 부유식 파력-해상풍력 복합발전 구조물의 극한환경 운동 성능에 대한 실험적 연구)

  • Kim, Kyong Hwan;Hong, Jang Pyo;Park, Sewan;Lee, Kangsu;Hong, Keyyong
    • Journal of the Korean Society for Marine Environment & Energy
    • /
    • v.19 no.1
    • /
    • pp.7-17
    • /
    • 2016
  • The present study experimentally considers dynamic performance of large floating wave-offshore hybrid power generation platform in extreme conditions. In order to evaluate the motion performance of the large floating hybrid power generation platform, 1/50 scaled model was manufactured. A mooring line was also manufactured, and free-decay and static pull-out tests were carried out to check the mooring model. A mooring line table was introduced to satisfy the water depth, and environmental conditions were checked. Motion responses in regular waves were measured and complicated environmental conditions including wave, wind, and current were applied to see the dynamic performance in extreme/survival conditions. Maximum motion and acceleration were judged following the design criteria, and maximum offset and mooring tension were also checked based on the rule. The characteristics of hybrid power generation platform are discussed based on these data.