Investigation of three-dimensional deformation mechanisms of box culvert due to adjacent deep basement excavation in clays

  • Bu, Fanmin;Yu, Wenrui;Chen, Li;Wu, Erlu
    • Geomechanics and Engineering
    • /
    • v.30 no.6
    • /
    • pp.565-577
    • /
    • 2022
  • In this study, a series of three-dimensional numerical parametric study was conducted to investigate deformation mechanisms of an existing box culvert due to an adjacent multi-propped basement excavation in clays. Field measurements from an excavation case history are first used to calibrate a baseline Hardening Soil Small Strain (HS-small) model, which is subsequently adopted for parametric study. Results indicate that the basement-box culvert interaction along the basement centerline can be considered as a plane strain condition when the length of excavation (L) reaches 14 He (i.e., final excavation depth). If a plane strain condition (i.e., L/He=12.0) is assumed for analyzing the basement-box culvert interaction of a short excavation (i.e., L/He=2.0), the maximum settlement and horizontal movement of the box culvert are overestimated significantly by up to 15.7 and 5.1 times, respectively. It is also found that the deformation of box culvert can be greatly affected by the basement excavation if the distance between the box culvert and retaining wall is less than 1.5 He. The induced deformation in the box culvert can be dramatically reduced by improving the ground inside the excavation or implementing other precautionary measures. For example, by adding jet grouting columns within the basement and installing an isolation wall behind the retaining structures, the maximum settlements of box culvert are shown to reduce by 37.2% and 13.4%, respectively.

Characteristics of Vacuum Consolidation by Comparing with Surcharge Loading Consolidation (성토재하공법과 비교한 진공압밀공법의 압밀특성 분석)

  • Sim, Dong-Hyun;Lee, Jae-Hwan;Jeong, Sang-Seom
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.30 no.5C
    • /
    • pp.201-208
    • /
    • 2010
  • In this study, the ground settlement was investigated by using monitoring data of the test sites where vacuum consolidation method and surcharge method were applied for improving deep soft soil. The monitoring data are chosen in ${\bigcirc}{\bigcirc}$ area port construction site reclaimed with very soft dredged clay. These data are analyzed to compare the consolidation characteristics between the different loading methods for soil improvement. Through analysis of the loading time, it is shown that the ground settlement reaches its allowable value under vacuum consolidation loading by about 45% faster than that of the surcharge loading consolidation. This could be explained that vacuum consolidation method makes the isotropic consolidation condition so that the time for reaching a certain final preloading without soil failure can be shortened.

Case Study of Comparative Analysis between Static and Dynamic Loading Test of PHC Pile (굴착 후 타입된 PHC 말뚝의 재하시험 결과 비교분석 사례 연구)

  • Kim, Jaehong;Yea, Geuguwen
    • Journal of the Korean GEO-environmental Society
    • /
    • v.14 no.11
    • /
    • pp.13-23
    • /
    • 2013
  • In the west coastal soft ground, the static and dynamic loading tests for PHC piles which were executed using light driving without injecting cement milk were carried out and the correlation was analyzed. Initial dynamic loading test used hydraulic hammer(ram weight 70kN) and final average penetration effect presented 3.0 to 8.0mm at 0.8m drop. Then final allowable bearing capacity using CAPWAP presented 776.4 to 1,053.6kN a pile. The static loading tests which were performed at the other piles loaded 200% of the design load dividing by eight phases. As the result, total settlement was 15.97 to 16.38mm and residual settlement was 4.48 to 5.38mm, but both yielding and ultimate load can't be estimated. Therefore, allowable bearing capacity was determined larger than 1,200kN a pile regarding maximum test load as yielding load. Thus, it showed that allowable bearing capacity of the dynamic loading test was larger than static loading test in 1.54 to 1.14 times.

The International Arbitration System for the Settlement of Investor-State Disputes in the FTA (FTA(자유무역협정)에서 투자자 대 국가간 분쟁해결을 위한 국제중재제도)

  • Lee, Kang-Bin
    • THE INTERNATIONAL COMMERCE & LAW REVIEW
    • /
    • v.38
    • /
    • pp.181-226
    • /
    • 2008
  • The purpose of this paper is to describe the settling procedures of the investor-state disputes in the FTA Investment Chapter, and to research on the international arbitration system for the settlement of the investor-state disputes under the ICSID Convention and UNCITRAL Arbitration Rules. The UNCTAD reports that the cumulative number of arbitration cases for the investor-state dispute settlement is 290 cases by March 2008. 182 cases of them have been brought before the ICSID, and 80 cases of them have been submitted under the UNCITRAL Arbitration Rules. The ICSID reports that the cumulative 263 cases of investor-state dispute settlement have been brought before the ICSID by March 2008. 136 cases of them have been concluded, but 127 cases of them have been pending up to now. The Chapter 11 Section B of the Korea-U.S. FTA provides for the Investor_State Dispute Settlement. Under the provisions of Section B, the claimant may submit to arbitration a claim that the respondent has breached and obligation under Section A, an investment authorization or an investment agreement and that the claimant has incurred loss or damage by reason of that breach. Provided that six months have elapsed since the events giving rise to the claim, a claimant may submit a claim referred to under the ICSID Convention and the ICSID Rules of Procedure for Arbitration Proceedings; under the ICSID Additional Facility Rules; or under the UNCITRAL Arbitration Rules. The ICSID Convention provides for the jurisdiction of the ICSID(Chapter 2), arbitration(Chapter 3), and replacement and disqualification of arbitrators(Chapter 5) as follows. The jurisdiction of the ICSID shall extend to any legal dispute arising directly out of an investment, between a Contracting State and a national of another Contracting State, which the parties to the dispute consent in writing to submit to the ICSID. Any Contracting State or any national of a Contracting State wishing to institute arbitration proceedings shall address a request to that effect in writing to the Secretary General who shall send a copy of the request to the other party. The tribunal shall consist of a sole arbitrator or any uneven number of arbitrators appointed as the parties shall agree. The tribunal shall be the judge of its own competence. The tribunal shall decide a dispute in accordance with such rules of law as may be agreed by the parties. Any arbitration proceeding shall be conducted in accordance with the provisions of the Convention Section 3 and in accordance with the Arbitration Rules in effect on the date on which the parties consented to arbitration. The award of the tribunal shall be in writing and shall be signed by members of the tribunal who voted for it. The award shall deal with every question submitted to the tribunal, and shall state the reason upon which it is based. Either party may request annulment of the award by an application in writing addressed to the Secretary General on one or more of the grounds under Article 52 of the ICSID Convention. The award shall be binding on the parties and shall not be subject to any appeal or to any other remedy except those provided for in this Convention. Each Contracting State shall recognize an award rendered pursuant to this convention as binding and enforce the pecuniary obligations imposed by that award within its territories as if it were a final judgment of a court in that State. In conclusion, there may be some issues on the international arbitration for the settlement of the investor-state disputes: for example, abuse of litigation, lack of an appeals process, and problem of transparency. Therefore, there have been active discussions to address such issues by the ICSID and UNCITRAL up to now.

  • PDF

Patterns of Subsistence Production in the Early Bronze Age in the Seoul/Gyeonggi Region (서울·경기지역 청동기시대 전기 생계자원(生計資源) 생산방식)

  • LEE Minyoung
    • Korean Journal of Heritage: History & Science
    • /
    • v.56 no.3
    • /
    • pp.22-44
    • /
    • 2023
  • The subsistence economics of the early Bronze Age has focused on explaining the intensity of agricultural practices without sufficiently taking into account the diversity of production methods that may arise from cultural types or environmental factors. The problem appears to stem from paying insufficient attention to the question whether we should understand the transition from the Neolithic Age to the Bronze Age as continuous or discrete. This has hitherto blocked an avenue to investigate the gradual changes in subsistence resource production methods. Taking as its premise that changes in the production methods of subsistence resources in the Bronze Age have been continuous and gradual, this paper seeks to restore the production patterns of subsistence resources according to the variety of factors that may have influenced the early Bronze Age production method. With diverse cultural patterns and ecological spaces of the early Bronze Age being confirmed, the work of restoring the production methods of subsistence resources in a specific period is difficult to achieve with one or two stand-alone analyses. A more appropriate method would involve separating a number of different aspects related to the production of subsistence resources, analyzing and interpreting each, and in the final stage, synthesizing the analyses. The specific research method employed in this paper checked for compositional differences in stone production tools, functionally categorized according to a variety of factors that have a close relationship with the production of subsistence resources: cultural-environmental factors and cultural patterns, geographical and topographical factors, soil productivity, and size of settlement. The results of the analysis are as follows: for the early Bronze Age production pattern of subsistence resources in the Seoul and Gyeonggi regions, while no substantive differences were observed with respect to cultural type, geographical and topographical location, the results show statistically significant differences in the composition of production tools according to settlement size and soil productivity. Also, with an increasing ratio of settlement size and total production soil, increases in hunting and armoring tools, woodworking tools, and harvesting tools were observed; on the other hand, when it came to the ratio of fishing tools, the opposite relationship was observed. While a correlation between settlement size or crop cultivation productivity and dependence on hunting or farming was expected, the results of the regression analysis show that settlement size and soil productivity ratios do not have mutually significant relationships. The results thus illustrate that patterns of production differ according to a variety of factors, and no single factor is decisive in the adoption of subsistence resource production methods by a specific settlement. Therefore, the paper emphasizes the need to investigate the production patterns of subsistence resources according to the variety of cultural and environmental factors that make up settlements in early Bronze Age society.

Study on the effect of tail void grouting on the short- and long-term surface settlement in the shield TBM Tunneling using numerical analysis (쉴드TBM터널에서 뒤채움 주입이 지반의 단기·장기 침하에 미치는 영향에 대한 수치해석적 연구)

  • Oh, Ju-Young;Park, Hyunku;Kim, Dohyoung;Chang, Seokbue;Lee, Seungbok;Choi, Hangseok
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.19 no.2
    • /
    • pp.265-281
    • /
    • 2017
  • For shallow tunnel constructions, settlement of the ground surface is a main issue. Recent technical developments in shield TBM tunneling technique have enabled a decrease in such settlements based on tunneling with ground deformation controls. For this objective, the tail void grouting is a common practice. Generally surface settlements in a soil of low permeability occur during a tunnel construction but also during a long period after completion of the tunnel. The long-term settlements occur mainly due to consolidation around the tunnel. The consolidation process is caused and determined by the tail void grouting which leads to an excess pore water pressure in the vicinity of the tunnel. Because of this, the grouting pressure has a strong effect on the long-term settlements in the shield tunneling. In order to investigate this effect, a series of coupled hydro-mechanical 3D finite element simulations have been performed. The results show that an increase in grouting pressure reduces the short-term settlements, but in many cases, it doesn't lead to a reduction of the final settlements after the completion of consolidation. Thereby, the existence of a critical grouting pressure is identified, at which the minimal settlements are expected.

Case Study on Treaty-Based Investor-State Arbitration and Environmental Litigations with Specific Reference to Chevron/Ecuador Litigation (환경 소송과 국제투자중재 - 쉐브론 사건을 중심으로)

  • Kang, Pyoung-Keun
    • Journal of Arbitration Studies
    • /
    • v.25 no.4
    • /
    • pp.3-23
    • /
    • 2015
  • The Chevron saga including Chevron/TexPet v. Ecuador, PCA Case No. 34877(hereinafter referred to as "Chevron I") and Chevron/TexPet v. Ecuador, PCA Case No. 2009-23(hereinafter referred to as "Chevron II") started out of domestic litigations between TexPet and Ecuador in the early 1990s. In Chevron I, the Tribunal decided that Article 2(7) of the U.S.-Ecuador BIT on effective means of provision was breached because of undue delays in the seven legal proceedings TexPet had brought against Ecuador in respect to contractual obligations. In Chevron II, it was contended that through the actions and inactions of the judiciary and the executive, Ecuador breached her several obligations under the BIT. Ecuador objected to the jurisdiction of the Tribunal because TexPet's investment was terminated in 1992, and because Chevron is not a party to the 1995 Settlement Agreement and 1998 Final Release. In its Interim Award on Jurisdiction and Admissibility, the Tribunal applied a prima facie standard to the facts alleged by the Claimants but denied by the Respondent, and decided that questions in respect of the Respondent's jurisdictional objections should be joined to the merits under Article 21(4) of the UNCITRAL Arbitration Rules. In the merits phase of Chevron II, the Tribunal divided the merits of the Parties' dispute into two parts, entitled "Track 1" and "Track 2". In its Partial Award on Track 1, the Tribunal decided that Chevron is a "Releasee" under the 1995 Settlement Agreement. In a decision on "Track 1B", the Tribunal decided that the Lago Agrio complaint cannot be read as pleading "exclusively" or "only" diffuse claims, and that, to this extent, the Claimants' reliance on the 1995 Settlement Agreement as a complete bar to the Lago Agrio complaint must fail, as a matter of Ecuadorian law. The Tribunal maintained the position that the Parties' disputes on both merit and jurisdiction should be reserved for Track 2. It remains to be seen how the Tribunal addresses the Claimants' allegations of multiple denials of justice under international law against the judgments of the Respondent's Courts, together with the Respondent's jurisdictional objections in Track 2 of the arbitration.

Estimation of volume Ratio according to Step up Filling Method for a Dredged Clay (단계투기법에 의한 준설점토의 체적비 산정)

  • Lee, Song;Kang, Myoung-Chan
    • Journal of the Korean Geotechnical Society
    • /
    • v.16 no.1
    • /
    • pp.167-178
    • /
    • 2000
  • An experimental study on step up filling method is carried out to reinforce the Yano method which is widely used to estimate volume ratio and self-weight consolidation settlement in reclamation area. This method considers actual reclamation construction in which dredged clay is continuously filled and rising of deposit height is presented as a result of volume decrease by height rising and self-weight consolidation. It measured the relationship between filling velocity and deposit rising velocity; calculated the total filling height which is needed to achieve the planned final deposit height, and its solid height and the time which is taken to finish the planned final deposit height; and on the basis of these calculated parameters, predicted the self-weight consolidation and volume change ratio in reclamation construction. Yano method is also used to predict the same conditions. 29.8% in self-weight consolidation, 31.1% in volume ratio, 40% in void ratio and water content is underestimated in Yano method compared to step up filling method.

  • PDF

Layer Interface Analysis of Multi-Layered Soils by Numerical Methods (수치해석에 의한 다층토 압밀의 경계요소면 해석)

  • 김팔규;류권일;구기욱;남상규
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1999.03a
    • /
    • pp.349-356
    • /
    • 1999
  • In general, the term soft ground includes clayey soils, which have large compressibility and small shear resistance due to the external load. All process of consolidation in compressible soils can be explained in terms of a transfer of load from an incompressible pore-water to a compressible soil structure. Therefore, one of the most important subjects about the characteristics of the time-dependent consolidation of the clay foundation by the change of load may be the presumption of the final settlement caused by consolidation and the degree of consolidation according to the time. The problems of discontinuous layer interface are very important in the algorithm and programming for the analysis of multi-layered soils using a numerical analysis, finite difference method. Better results can be obtained by the Process for discontinuous layer interface, since it can help consolidation analysis to model the actual ground. The purpose of this paper Provides an efficient computer algorithm based on numerical analysis using finite difference method(F.D.M.) which account for multi-layered soils to determine the degree of consolidation and excess pore pressures relative to time and positions more realistically.

  • PDF

A Study on the Efficiency of Trade Arbitration by the New Arbitration Law of Korea (무역중재의 특성과 개정중재법의 효율성에 관한 고찰)

  • Chung, Ki-Ihn
    • Journal of Arbitration Studies
    • /
    • v.16 no.1
    • /
    • pp.3-44
    • /
    • 2006
  • Arbitration, which involves a final determination of disputes, has elements of the judicial process. Although an alternative to formal court litigation, it does not replace it in all aspect, but rather coexists with court procedure as an adjunct and part of administering justice. As the international trade has the basic problems of business managed between the parties of other countries having different laws, customs, cultures, currencies and religions. It has been known that these defects caused the commercial disputes and suspended economic fluence in world economic development through the foreign business. The United Nations launched 'the United Nations Convention on the Enforcement and Recognition of the Foreign Arbitral Awards' in 1958 to give effect to the international commercial arbitration. However, the convention has the limitation in excluding the legal obstacles originated from domestic arbitration systems of every states. As the result, the UN succeeded in making world wide arbitration law named 'The UN Model Law on International Commercial Arbitration' in 1983 and recommended all member countries to accept it to revise their domestic arbitration laws thereafter. Korea revised national arbitration law accepting 100% of the model law in 2000. In this respect korea became to have the international dispute settlement system. Korea will be able to settle more business disputes arisen from the international trade and enjoy the world credibility through the new arbitration system.

  • PDF