International conference on construction engineering and project management
/
2011.02a
/
pp.168-175
/
2011
Construction accidents are major problem in Turkish Construction industry and especially fatally rates are very high. Current legislative system on occupational safety in Turkey enforces employers to implement safety measures as well as safety management systems. However level of consciousness in the industry is unsatisfactory and safety are perceived as extra cost and unnecessary expenditure. Moreover, especially in small residential building constructions which have a big share in the industry and unfortunately safety measures to mitigate or abate construction risks do not exist. The study focuses on small residential building construction sites and in the scope of this study, thirty building projects are examined. For each building project, project cost including labour and material costs, service and consultancy costs for mechanical, electrical systems as well as architectural and structural services, costs for supervision and finally general expenditures for construction site facilities were calculated. On the other hand, occupational safety costs for personal protective equipment, collective protective measures, consultancy and training were determined. Work breakdown structures were established and for each work item firstly occupational risks were evaluated and furthermore according to risk scores safety measures to be implemented were defined and related costs were calculated. The study gave results for total safety cost on average, in terms of percentage of total project cost (3.73% of total project cost), safety cost per man-hour (0.40 USD) and safety cost in terms of unit construction area (11.60 USD per square meter). Since safety management is a part of whole project management process, study gives suggestions and techniques to calculate safety costs and implement safety measures as a part of project management service for professionals. Authors believe that suggested approach may easily developed by the usage of more data to establish a model for estimation not only for building construction sites but also for all construction projects.
Journal of the Korea Institute of Building Construction
/
v.14
no.5
/
pp.415-422
/
2014
There is growing difference between a planned value and an actual cost for increasing as an risk of construction cost. A construction cost index is an alternative to redeem a problem, but it is still very difficult to reduce an actual differential as a price fluctuation. Furthermore an existing theory of a construction cost index is overly complex, and is unsuitable for using in working-level. This study suggests an optimum correction rate in respect of a total construction cost. It is analyzing the actual cost of 53 public buildings that the Public Procurement Service ordered. The objects are main processes that include architectural works, mechanical works, electrical works, telecommunication works, and service facilities. It is compared a total construction cost based on absolute error rate using the median from frequentist principle. For this, it is selected the suitable regression model and set a correction rate.
Korean Journal of Air-Conditioning and Refrigeration Engineering
/
v.26
no.3
/
pp.115-121
/
2014
HVAC&R system costs can often be one of the most expensive components, representing approximately 15% of the total construction cost for office buildings. Despite their significant importance, there is a lack of a consistent and homogeneous framework to approximate the estimate research. This research deals with the prediction methodology of HVAC&R system cost with the aim of establishing a common idea for the analysis of the construction cost estimate. Our approach deals with the concept of an HVAC&R set that is composed of subsystems. The matrix combination analysis is examined, and total 960 HVAC&R system cost estimation can be implemented to large scale office buildings.
Proceedings of the Korean Institute of Building Construction Conference
/
2014.05a
/
pp.44-45
/
2014
Recently the Korean government also has strictly restricted a law such as GBCC(Green Building Certification Criteria)and RPS(Renewable Portfolio Standard) on the construction. Especially the government announced a obligation of renewable energy consumption over 12% for all the public buildings of total area over 1,000㎡ since 2014. Regarding to the policy, this study presented the economics of energy analysis of the public office buildings that supplies 12% renewable energy output in the early stage of construction project. This paper calculated on CO2 emission by the geothermal, solar heat, and solar photovoltaic system and estimated the saving cost. Reduced cost through the energy saving are predicted to influence on the total construction cost. As a result air pollution and energy saving cost are expected that renewable energy system would be saving total initial cost of construction on planning phase.
Korean Journal of Construction Engineering and Management
/
v.4
no.4
s.16
/
pp.106-113
/
2003
The purpose of this thesis is to provide an appropriate trade-off information for the conflicting interests caused by the various factors between building owner and contractor during selecting the contractor and performing the construction work, in which the construction was contracted by open bidding from the government or private organizations. In order to propose the legitimate evidence, the differences between the domestic contract sheet of drawing change and the process of drawing change and those of the foreign countries were compared and analysed The number of construction ordered in Youngdong area in 2001 whose construction expenses are more than 100,000,000 won is 218 items and 147,005,000,000 won in total cost Among them, the number of 218 items whose total cost amounts to 16,705,000,000 (11.36$\%$) is in case of increase of construction expenses due to the drawing changes, and the number of 48 items whose tool cost amounts to 2,009,000,000 won (1.37$\%$) is the case of decrease. In conclusions, the contractor could have more benefits than the building owner in case they submit the detailed estimate sheet without eliminating the increasing expenses of construction. It is shown that the building owner's loss is increasing whenever the labor cost is higher material cost Therefore, this thesis proposes a proper standards for the harmonious compromise between the contractor and the building owner for the problems caused by the drawing changes when the contract agreement is occurred.
Korean Journal of Construction Engineering and Management
/
v.12
no.2
/
pp.81-88
/
2011
Providers haven't recently had a flexible construction cost estimation system to meet various needs of consumers about public housing. So the subject of this study is to estimate construction cost reasonably in early project stage of public housing and then develop reliable means which is able to support construction cost management and establish a adequate funding investment plan as a provider. In this study, Regression analysis was performed by the case on 20 public apartment complex which were designed from the first half of 2007 to the first half of 2008. A total construction cost of construction, civil engineering, machinery, elevator, land scape, electricity and communication work was used as one sample for increasing explanation and representativeness of the case. In addition, The total construction cost which is devided into design, contract and completion cost was variously analysed for increasing relevance of model and actual utilization. The result of estimation model based on a total construction cost set up completion and design cost showed that error rate is within 2%, which is a excellent result. The estimation model of the construction cost developed by this study is expected to estimate approximate construction cost which is adjacent real construction cost in early stage of the project by using some data.
Proceedings of the Korean Institute Of Construction Engineering and Management
/
autumn
/
pp.383-386
/
2001
The ability to make good cost overruns predictions is a very important aspect of in major construction project. The probabilistic cost models can provide more reliable than traditional cost models which have been used in korea to prepare Bill of Quantities, if the actual cost data are sufficient enough to analyze the trends of the variables. The paper considers non-deterministic methods in a cost estimate. The method(referred to as the 'Monte Carlo simulation' method) interprets cost data indirectly, to generate a probability distribution for total costs from the deficient elemental experience cost distribution. The objectives of this research is to develop a method to forecast the probabilistic total construction cost and the elemental work cost
Proceedings of the Korean Institute of Building Construction Conference
/
2015.05a
/
pp.7-8
/
2015
Formwork accounts for 10% of the total construction cost and 30~40% of the framework cost, which is a fairly large part. Various system forms were developed for improved economic feasibility and constructability of formwork and for reduced construction duration. In general, the price of system forms per unit area is higher than that of the conventional method, yet the total construction cost can be reduced through higher reusability and constructability. However, if the reusability of forms is excessively increased to cut down the material cost, it may increase the construction duration, which will result in cost increase. On the other hand, if the reusability is decreased for reduction of construction duration, it may lead to cost increase caused by excessive input of materials. To solve such a problem, an algorithm for simplified reuse planning that meets the requirements of construction duration, cost, quality and safety is required. In this regard, the study intends to perform a fundamental research for development of reuse planning automation algorithms on system forms that are used on girders and beams.
Korean Journal of Construction Engineering and Management
/
v.14
no.3
/
pp.12-21
/
2013
Total Project Cost Management System(TPCMS) was introduced with the purpose of increasing the efficiency of cost control for public construction project in 1994. In this paper, general perception of participants of the public construction project on the TPCMS was examined, and the problems in implementing the TPCMS was figured out through expert interviews and survey. Then better ways to implement the system were drawn based on the problems. To effectively manage the cost of public construction project, basically project cost should be estimated accurately in planning stage and managed based on it to have a project complete within the budget. In addition, the cost need to be managed in more systematic ways in terms of data collection and analysis, and the autonomy in managing the project cost given to the project owner needs to be expanded. Most of all, proper budget should be provided to prevent a project from delay through setting the priority of projects and proper budget allocation based on the priority.
Korean Journal of Construction Engineering and Management
/
v.4
no.4
s.16
/
pp.192-200
/
2003
The object of this research is to develop a computerized algorithm of cost estimation method to forecast the total construction cost in the bidding stage by the historical and elemental work cost data. Traditional cost models to prepare Bill of Quantities in the korea construction industry since 1970 are not helpful to forecast the project total cost in the bidding stage because the BOQ is always constant data according to the design factors of a particular project. On the contrary, statistical models can provide cost quicker and more reliable than traditional ones if the collected cost data are sufficient enough to analyze the trends of the variables. The estimation system considers non-deterministic methods which referred to as the 'Monte Carlo simulation. The method interprets cost data to generate a probabilistic distribution for total costs from the deficient elemental experience cost distribution.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.