• Title/Summary/Keyword: rock blast

Search Result 194, Processing Time 0.021 seconds

A Case Study of Electronic-blasting, Railroad Tunnel to Pass under Existing Highway (기존 고속도로 하부 통과를 위한 철도터널 전자발파 시공사례)

  • Kim, Gab-Soo;Son, Young-Bok;Kim, Jae-Hoon
    • Explosives and Blasting
    • /
    • v.32 no.2
    • /
    • pp.16-24
    • /
    • 2014
  • In this "Wonju~Jaecheon double-lanes railroad" project, a highway is located at about 13meter above a tunnel. Initially, rock-splitting method was used for the tunnel excavation in order to minimize the possible damage on the highway. The method, however, takes a long time for the tunnel excavation and that may cause other problems like large displacement of tunnel and subsidence of highway ground before the tunnel can be stabilized by supporters. Therefore, the application of electronic blasting method(eDdevII) was recommended to control the blast vibration below 1.0cm/sec as well as to prevent the subsidence of highway ground. The analysis of the influence of tunnel excavation on the highway showed that electric blasting method is permissible for the safe management of the highway. Based on that, the tunnel construction under a highway could be carried out quickly and safely without any damages on the highway.

Comparative Study on the Characteristics of Ground Vibrations Produced from Borehole Blast Tests Using Electronic and Electric Detonators (전자뇌관과 전기뇌관을 사용한 시추공 발파시험에서의 지반진동 특성에 관한 비교 연구)

  • Choi, Hyung-Bin;Won, Yeon-Ho
    • Explosives and Blasting
    • /
    • v.28 no.2
    • /
    • pp.37-49
    • /
    • 2010
  • Ground vibration caused by blasting in the urban area close to structures can give some indirect damage to human body and may lead to structural damage to buildings. At the stage of design or when complaints were filed by residents, the test blasting in borehole, which is most practical for expressing simple vibration wave form quantitatively, is usually chosen for assessing the degree of damage to structures. In this paper, some lessons gained from the application of electronic detonator triggering system in borehole test blasting are presented. The difference in delay time of detonator when borehole is blasted by electronic detonator and electric detonator are discussed. The peak particle velocities measured at the structure embedded in the similar rock layer to main line of tunnel at test site and measured at the road surface just above the tunnel having different overburden layers were analysed to draw their relationship. By comparing the results with those appearing in some published literatures, the usefulness of the borehole test blasting and the importance of delay time of detonator are addressed.

A Study on the Application of Landfill Liners with Stone Dust Sludge (석분슬러지를 이용한 쓰레기매립장 차수재의 적용성에 관한 연구)

  • Cho, Jae-Hyung;Yoon, Tae-Gook;Yeo, Byeong-Chul;Ahn, Sang-Ro;Chun, Byung-Sik
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2005.03a
    • /
    • pp.483-490
    • /
    • 2005
  • At present around 50 companies have their own crushing plants, which manufacture rock into crushed sand, over around 350 different quarry throughout the nation. However, in most plants the stone dust sludge is left as it is in their plants so that they have difficulty to utilize. Furthermore, environmental pollution may be even caused due to dust generated when it is dried. Recycling is starting capturing the attention of the people working over the quarry due to the reasons described above. This research has studied in the quarters the usability as landfill liner of the stone dust sludge, which is industrial waste. We investigated what technological properties it would have after mixing the stone dust sludge with SM(sandy soil) first and then with blast furnace slag or reject ash, which is waste, and cement as the stabilizer. As the result of three tests; compacting test, strength test, and permeability test; to satisfy the regulatory guideline of the government that is the compress strength over 5 $kgf/cm^2$, the flexibility over 1 $kgf/cm^2$, and the permeability under $1.0{\times}10^{-7}cm/sec$ From this research, we could confirm that stone dust sludge would be used as waste landfill liner if it were mixed with other waste by the proper mixing ratio.

  • PDF

A manual for the revised TBM tunnel specification (개정 TBM 터널 표준시방서 해설 연구)

  • Sagong, Myung;Jung, Chi Kwang;Moon, Joon Bai;Kim, Jeayoung;Yun, Do Sik;Yu, Myeong Han
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.4
    • /
    • pp.415-428
    • /
    • 2015
  • With increase of the extension of long tunnels and urban tunnelling, demands on the new tunnelling technologies are raised. Currently, drilling and blasting tunnel construction method is mostly used, however, because of sever blast vibration for some occasions, complaints from local residents and rock damages are inevitable. Accordingly, TBM tunnelling is more efficient and effective for such conditions. Nevertheless, tunnel construction costs of TBM cannot compete that of the drill and blasting method in Korea. To overcome such limitations, various TBM equipments and construction technologies are required. In addition, continuous revision of the design standard and specification are required. In this study, a detailed explanation regarding the revised version of TBM section in the tunnel standard specification at 2015 is shown.

A Comparison of Operation Time between the Standard of Estimate and Actual Operations in Tunnel Blasting (터널발파시 실제 작업시간과 품셈의 비교 분석)

  • Kim, Yang-Kyun;Kim, Hyung-Mok
    • Explosives and Blasting
    • /
    • v.33 no.3
    • /
    • pp.14-20
    • /
    • 2015
  • Tunnel blasting that plays the most important role in the construction of a drill & blast tunnel, shows a big difference in operation time according to various factors such as rock mass quality, tunnel dimension, machine performance, and the skill level of tunnel crews. This paper analyzes the differences between the time calculated by the standard of estimate and actual operation time based upon field investigations on blasting operation time in three tunnels of Korea. The result shows that actual blasting time is generally about 8%~16% less than the standard of estimate in cases that normal operations are performed. If the time delayed by unforeseen situations is included, however, it is presumed that the number of cases that actual operation time exceeds the standard of estimate are considerable. This study aims to help make a judgement over the appropriacy of the standard of estimate through continuous investigations on actual operation time, as well as improve the productivity of tunnel excavation.

A study on analysis of vibration and crack measurement data on granite-bed rock (화강암 지반에서 진동 및 크랙측정치 분석에 관한 연구)

  • Han, Dong-Hun;Ahn, Myung-Seog;Lee, Kwang-Yeol;Oh, Byung-Sam;Kang, Moon-Gu
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.5 no.3
    • /
    • pp.251-260
    • /
    • 2003
  • Tunnel blasting has been performed with V-cut to investigate the characteristics. Blasting vibrations were measured at two directions, the proceed direction and side direction. Propagation characteristics were determined by regression analysis; square root scaled distance and cube root scaled distance with maximum charge per delay of the blast. Testing result, The cross point was 62m in the allowable vibration velocity of 3mm/sec and 46m in 5mm/sec. Also, vibration level with measuring point was highest and decayed fastest, adapting to cube root scaled distance, for the proceed direction on ground.

  • PDF

Influence of EDZ on the Safety of a Potential HLW Repository

  • Hwang Yong-Soo;Kang Chul-Hyung
    • Journal of Nuclear Fuel Cycle and Waste Technology(JNFCWT)
    • /
    • v.2 no.4
    • /
    • pp.253-262
    • /
    • 2004
  • Construction of tunnels in a deep crystalline host rock for a potential High-Level Radioactive Waste(HLW) repository inevitably generates an excavation disturbed zone (EDZ). There have been a series of debates on whether a permeability in an EDZ increases or not and what would be the maximum depth of an EDZ. Recent studies show mixed opinions on permeability. However, there has been an international consensus on the thickness of an EDZ; 30 cm for TBM and 1 meter for controlled blast. One of the impacts of an EDZ is on determining the distance between adjacent deposition holes. The void gap by the excavation hinders relaxation of temperature profiles so that the current Korean reference designing distance between holes should be stretched out more to keep the maximum temperature in a buffer region below 100 degrees Celsius. The other impact of an EDZ is on the long-term post closure radiological safety. To estimate the impact, the reference scenario, the well scenario, is chosen. Released nuclides diffuse through a bentonite buffer region experiencing strong sorption and reach a fracture surrounded by a porous medium. Inside a fractured porous region, radionuclides migrate by advection and dispersion with matrix diffusion into a porous medium. Finally, they reach a well assumed to be a source of potable water for local residents. The annual individual dose is assessed on this well scenario to find out the significance of an EDZ. A profound sensitivity study was performed, but all results show that the impact is negligible. Even though the role of an EDZ turns out to be limited on overall safety assessment, still it is worthwhile to study the chemical role of an EDZ, such as a potential source for natural colloids, potential sealing of an open fracture by fine clay particles generated by the process of an EDZ, and alteration of a sorption mechanism by an EDZ in the future.

  • PDF

A Study on the Vibration Propagation Characteristics of Controlled Blasting Methods and Explosives in Tunnelling (터널 제어발파 공법 및 화약류의 진동전달 특성에 관한 연구)

  • Jung, Hyuksang;Jung, Kyoungsik;Mun, Hongnyeon;Chun, Byungsik;Park, Duhee
    • Journal of the Korean GEO-environmental Society
    • /
    • v.12 no.2
    • /
    • pp.5-14
    • /
    • 2011
  • The most common problem encountered in domestic tunnel construction sites are solving public resentments caused by damage to adjacent structures and buildings. The most effective excavation method in rock tunnelling is the drilling and blasting, which is the main cause of vibration resulting in the public resentments. In this study, numerical analysis is conducted to compare the vibration reduction effect of line drilling and pre-splitting methods. Furthermore, the numerical simulations are verified and the results are quantified. Finally, various combinations of explosives used in controlled blasting are used and the vibration reduction effects are evaluated, thereby proving the applicability of the controlled blasting for reduction of vibration in tunnelling.

A Case Study of Deep Shaft Blasting for Reducing Ground Vibration in Urban Area (도심지의 대심도 수직구 발파에서 지반진동저감 시공 사례)

  • Hwang, Nam-Sun;Kim, Kyung-Hyun;Kim, Jeoung-Hwan;Jung, Min-Sung;Lee, Hyeung-Jin;Na, Gyeong-Min
    • Explosives and Blasting
    • /
    • v.39 no.2
    • /
    • pp.15-26
    • /
    • 2021
  • Domestic electronic detonators are used widely in many quarry and construction sites since its launch at 2013. In the case of SOC projects conducted in the city, most of them are designed in high-depth to reduce complaints. The high-depth excavation needs a long construction period and huge cost for building shaft and ventilation hole. Mechanical excavation method is applied when safety things are located nearby the site. Solidity of rock and machine's performance affect on the method's efficiency. So as the efficiency is getting lower, the construction period is extended, and the cost is increases as well. This case study is about changing the machine excavation method to the blasting method which is electronic detonator applied at the shaft construction site in the city. This is an example of using electronic detonators on the construction site in reducing blast-noise and vibration while meeting environmental regulatory standards.

On the vibration influence to the running power plant facilities when the foundation excavated of the cautious blasting works. (노천굴착에서 발파진동의 크기를 감량 시키기 위한 정밀파실험식)

  • Huh Ginn
    • Explosives and Blasting
    • /
    • v.9 no.1
    • /
    • pp.3-13
    • /
    • 1991
  • The cautious blasting works had been used with emulsion explosion electric M/S delay caps. Drill depth was from 3m to 6m with Crawler Drill ${\phi}70mm$ on the calcalious sand stone (soft -modelate -semi hard Rock). The total numbers of test blast were 88. Scale distance were induced 15.52-60.32. It was applied to propagation Law in blasting vibration as follows. Propagtion Law in Blasting Vibration $V=K(\frac{D}{W^b})^n$ were V : Peak partical velocity(cm/sec) D : Distance between explosion and recording sites(m) W : Maximum charge per delay-period of eight milliseconds or more (kg) K : Ground transmission constant, empirically determind on the Rocks, Explosive and drilling pattern ets. b : Charge exponents n : Reduced exponents where the quantity $\frac{D}{W^b}$ is known as the scale distance. Above equation is worked by the U.S Bureau of Mines to determine peak particle velocity. The propagation Law can be catagorized in three groups. Cubic root Scaling charge per delay Square root Scaling of charge per delay Site-specific Scaling of charge Per delay Plots of peak particle velocity versus distoance were made on log-log coordinates. The data are grouped by test and P.P.V. The linear grouping of the data permits their representation by an equation of the form ; $V=K(\frac{D}{W^{\frac{1}{3}})^{-n}$ The value of K(41 or 124) and n(1.41 or 1.66) were determined for each set of data by the method of least squores. Statistical tests showed that a common slope, n, could be used for all data of a given components. Charge and reduction exponents carried out by multiple regressional analysis. It's divided into under loom over loom distance because the frequency is verified by the distance from blast site. Empirical equation of cautious blasting vibration is as follows. Over 30m ------- under l00m ${\cdots\cdots\cdots}{\;}41(D/sqrt[2]{W})^{-1.41}{\;}{\cdots\cdots\cdots\cdots\cdots}{\;}A$ Over 100m ${\cdots\cdots\cdots\cdots\cdots}{\;}121(D/sqrt[3]{W})^{-1.66}{\;}{\cdots\cdots\cdots\cdots\cdots}{\;}B$ where ; V is peak particle velocity In cm / sec D is distance in m and W, maximLlm charge weight per day in kg K value on the above equation has to be more specified for further understaring about the effect of explosives, Rock strength. And Drilling pattern on the vibration levels, it is necessary to carry out more tests.

  • PDF