• Title/Summary/Keyword: period of cold weather concrete

Search Result 40, Processing Time 0.025 seconds

Field Construction Applying the Insulating Method of Moderate-Cold Weather Concreting Using Double Bubble Sheets (2중 버블시트를 이용한 한랭기 콘크리트의 단열양생공법 현장적용)

  • Kim, Jong;Kim, Jong-Back;Jeon, Chung-Keun;Shin, Dong-An;Oh, Seon-Gyo;Han, Cheon-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2006.11a
    • /
    • pp.29-32
    • /
    • 2006
  • Experimental test results of field construction, Cheongju University Educational Liberal Art Building, applying the insulating curing method on slab concrete showed that the quality of concrete in fresh and hardened state satisfied all target values. Temperature history of slab concrete in A and B area secured more than $7.8{\sim}9.2^{\circ}C$ higher than outside atmosphere. After completing certain curing period of time on the surface of the structure, crack occurrence was not found. It is concluded that the preventing vaporization of moisture by the insulating curing method reduces plastic and drying shrinkage as welt as improves durability.

  • PDF

Field Application to Evaluate the Effect of Various Surface Covered Curing Blankets on Temperature Profile and Crack Occurrence of the Concrete under Hot Weather Condition (서중환경에서 표면피복 양생재 종류변화가 콘크리트의 초기 온도이력 및 균열발생에 미치는 영향에 관한 현장적용성 평가)

  • Han, Min-Cheol;Lee, Sang-Woon
    • Journal of the Architectural Institute of Korea Structure & Construction
    • /
    • v.34 no.5
    • /
    • pp.27-34
    • /
    • 2018
  • Concrete placed under hot weather condition suffers from larger slump loss, rapid moisture evaporation due to high air temperature. Proper measures for material, transportation and curing should be taken to prevent the quality deterioration of the concrete under hot weather condition. In Korea, Although the period of hot weather concrete in Korea occupies only 2 months, there are a lot of quality problems including plastic, drying shrinkage and cold joint. Therefore, the objective of this paper is to investigate and compare the temperature history and crack occurrence of the concrete, which was placed in the actual apartment house construction field under hot weather condition, in response to the application of surface covered curing blankets including PE film, single layer clear bubble sheet, white colored bubble sheet and aluminum metalized bubble sheet. Test results indicated that the application of white colored bubble sheet and aluminum metalized bubble sheet showed most favorable results in terms of reduction in temperature rise and crack occurrence as well as easiness in handling. But, due to light reflection by aluminum metalized bubble sheet, it is believed that white colored bubble sheet is preferable.

Application of Insulation Curing Method with Double Bubble Sheets Subjected to Cold Weather (이중 버블시트를 이용한 단열양생공법의 한중시공 적용 사례)

  • Hong, Seak-Min;Lee, Chung-Sub;Kim, Jong;Jeon, Chung-Kun;Han, Min-Cheol;Han, Cheon-Goo
    • Proceedings of the Korea Concrete Institute Conference
    • /
    • 2008.04a
    • /
    • pp.1001-1004
    • /
    • 2008
  • This study reviewed the results of utilization of insulation heat curing method using double layer bubble sheet in slab concrete and mass concrete in cold weather environment. First of all, when double layer bubble sheets are applied, it was shown that slab concrete was protected from early freezing by remaining between 6 and $10^{\circ}C$ even in case outside temperature drops $10^{\circ}C$ below zero until the 2nd day from piling, and in the case of mass concrete, with the maximum temperature difference between the center and surface less than $6^{\circ}C$, crack occurrence index was close to 2 and no hydration heat crack occurred by internal constraint. The insulation heat preservation curing method using the double bubble sheet applied in this field prevented early freezing owing to stable curing temperature management, deterring concrete strength development delay at low temperature, and obtained the needed strength. Also, it was proven that the method is highly effective and economic for cold weather concrete quality maintenance through curing cost reduction like construction period shortening and labor cost reduction, etc by reducing the process of temporary equipment installation and disassembling.

  • PDF

Effect of the Kind of Surface-Covered Curing Materials on the Temperature of Concrete in Hot Weather (서중환경에서 표면피복 양생재 종류가 콘크리트의 온도에 미치는 영향)

  • Lee, Je-Hyun;Kim, Min-Sang;Moon, Byeong-Yong;Lee, Sang-Un;Han, Min-Cheol;Han, Cheon-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2017.11a
    • /
    • pp.173-174
    • /
    • 2017
  • Although the application period of hot weather concrete in our country is two months of July~August which is relatively short, many problems in various aspects such as generation of plastic/dry contraction cracks and cold joints can be caused unless proper quality control measures are established at this time. Therefore, this study compared the temperature history of the placed concrete by applying a mono white and aluminum-deposited bubble sheet developed with surface coating curing materials for surface exposure and summer to an actually constructed apartment slab. The analysis result showed that the mono white bubble sheet is the best method.

  • PDF

A Case Study on Field Construction of Cold Weather Mass Concreting Using Double Bubble Sheets and Hydration Heat Difference Method (이중 버블시트 및 수화발열량차 공법에 의한 한중매스콘크리트의 현장적용 연구)

  • Kim Jong;Yoon Jae-Ryung;Jeon Chung-Keun;Shin Dong-An;Oh Seon-Gyo;Han Cheon-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2006.05a
    • /
    • pp.15-18
    • /
    • 2006
  • The test result of mat concrete applying both hydration heat difference and insulation curing method on new construction of Cheongju university educational building are summarized as following. Both fresh concrete and compressive strength properties were satisfied In aimed value. Setting time of concrete incorporating 15% of fly ash(FA) retarded 1.2 hour than control concrete. Temperature history of mali concrete indicated that the highest temperature of center was exhibited at $126^{\circ}C$ after 51 hours while the highest temperature of upper section was $10.6^{\circ}C$ after 46 hours. Temperature Difference between center and surface was managed at less than $6^{\circ}C$ during whole curing period. In addition the temperature of upper section secured more than $3.3^{\circ}C$ while the temperature of outside was indicated at less than $-10^{\circ}C$. Maturity by parts of construction secured more than $30^{\circ}C$ DD higher than outside at 3 days. The more number of times, applying insulation curing method by double bubble sheets, increased, the higher economic effect was secured. Overall it was clear that applying both double bubble sheets and hydration heat difference method on this new construction can resist hydration heat crack, early frost demage and strength decrease. It also significantly contributed quality improvement of cold weather concreting

  • PDF

Experimental Study on High Strength and high Flowable Concrete Filled Steel Tube for Practical Construction Application (합성강관 충전용 고강도-초유동 콘크리트의 현장적용을 위한 실험적 연구)

  • 윤영수;이승훈;성상래;백승준
    • Magazine of the Korea Concrete Institute
    • /
    • v.8 no.2
    • /
    • pp.151-161
    • /
    • 1996
  • This paper presents a series of tests to produce the h~gh quality concrete to be filled Inside the steel tube columns. Thls concrete filled steel tube system requires not only the high strength, but a150 the flowable concrete. Laboratory test has been performed to clarlfy the material characteristics and to produce the optlmal mix design proportion. Full scale site mock up test has been then carried out to slnlulate the actual construct~on conditions including the product~on of concrete at the rermcon batch plant, transportation to the construction site, proper workabil~ ty and man power required , 4ddit1onal mock up test has finally been performec to irivesti gate any unfavorable construction s~tuatioils since the actual concrete placement has been sched uled in cold weather period, so that the high quality concrete construction is convinced to be successfully carried out.

Field Application of Surface Insulation Curing Method to Cold Weather Concreting (한중콘크리트의 현장 표면단열 양생공법 시공사례 연구)

  • Kim Jong-Back;Lim Choon-Goun;Han Min-Cheol;Kim Seoung-Soo;Han Cheon-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2005.11a
    • /
    • pp.25-28
    • /
    • 2005
  • This study investigates the field application of surface insulation curing method, which combined double layer bubble sheet(DBS) and thick-curing-material(TCM) for cold weather concreting. According to the test, deck slab, curing only upper section with DBS and TCM, does not make big different temperature history with that, curing both upper and bottom section during daily average temperature 6.5t. It is concluded that combination of DBS and TCM in only upper section can be safely cured in early period of time during cold water concreting. The field test was carried out with this favourable data. The upper deck slab was insulated by combination of DBS and TCM, and the construction was surrounded by tent. in order to protect from outside wind. The test result shows that the lowest temperature of deck slab indicated 6$ ^{circ}C $. It demonstrated that this curing method can resist early frost and save construction cost in the side of management and saving labor cost, compared with previous method. In addition, the column specimen, combined both form and bubble board, exhibited favorable temperature history, due to internal hydration heat insulation effect.

  • PDF

Performance Analysis of Strength Development of FRC Base Depending on Maturity (적산온도에 의한 FRC 기층의 강도발현 성능 분석)

  • Choi, Sung-Yong;Park, Young-Hwan;Jung, Woo-Tai
    • International Journal of Highway Engineering
    • /
    • v.18 no.1
    • /
    • pp.13-21
    • /
    • 2016
  • PURPOSES : In this study, we analyzed the compressive strength characteristics of lean base concrete in relation to changes in the outdoor temperature after analyzing the cold and hot weather temperature standards and calculated the minimum and maximum temperatures when pouring concrete. We examined the rate of strength development of lean base concrete in relation to the temperature change and derived an appropriate analysis formula for FRC base structures by assigning the accumulated strength data and existing maturity formula. METHODS : We measured the strength changes at three curing temperatures (5, 20, and $35^{\circ}C$) by curing the concrete in a temperature range that covered the lowest temperature of the cold period, $5^{\circ}C$, to the highest temperature of the hot period, $35^{\circ}C$. We assigned the general lean concrete and FRC as test variables. A strength test was planned to measure the strength after 3, 5, 7, 14, and 28 days. RESULTS : According to the results of compressive strength tests of plain concrete and FRC in relation to curing temperature, the plain concrete had a compressive strength greater than 5 MPa at all curing temperatures on day 5 and satisfied the lean concrete standard. In the case of FRC, because the initial strength was substantially reduced as a result of a 30% substitution of fly ash, it did not satisfy the strength standard of 5 MPa when it was cured at $5^{\circ}C$ on day 7. In addition, because the fly ash in the FRC caused a Pozzolanic reaction with the progress into late age, the amount of strength development increased. In the case of a curing temperature of $20^{\circ}C$, the FRC strength was about 66% on day 3 compared with the plain concrete, but it is increased to about 77% on day 28. In the case of a curing temperature of $35^{\circ}C$, the FRC strength development rate was about 63% on day 3 compared with the plain concrete, but it increased to about 88% on day 28. CONCLUSIONS : We derived a strength analysis formula using the maturity temperatures with all the strength data and presented the point in time when it reached the base concrete standard, which was 5 MPa for each air temperature. We believe that our findings could be utilized as a reference in the construction of base concrete for a site during a cold or hot weather period.

Analysis on the Heat Insulation Performance of Cold Weather Concrete according to Change of Laid Construction Conditions of Double Bubble Sheets (이중버블시트의 포설 시공조건 변화에 따른 한중 콘크리트의 단열보온 성능 분석)

  • Han, Cheon-Goo;Han, Min-Cheol;Baek, Dae-Hyun
    • Journal of the Korea Institute of Building Construction
    • /
    • v.10 no.5
    • /
    • pp.121-128
    • /
    • 2010
  • The present research examined heat insulation performance according to change of various laid construction conditions of double bubble sheet being used as material for heat insulation & curing construction of cold weather concrete, and its results are as follows. First, the change in a laid period of bubble sheet within 4 hours and the change in water content inside bubble sheet overall showed similar temperature history and maturity without a big difference in terms of the temperature history of concrete according to construction factors, but it could be confirmed that when a structure was thin or several bubble sheets are laid, requisites unfavorable for initial curing of concrete can occur if a lagger distance between sheets is generated. In terms of the compressive strength of concrete core specimens, it appeared that the initial compressive strength is declined when conditions unfavorable for concrete curing such as delay of a laid period of bubble sheets, induction of large distance between sheets, increase of water content inside bubble sheets and thinness of a structure of placing concrete, etc. were applied, but it appeared that as its age passes, the difference becomes small.

A study on the Effect of Calcium Chloride Admixture on strengths of Concrete (혼화제인 염화칼슘이 콘크리트 강도에 미치는 영향에 관한 연구)

  • Jun, Hyun-Woo;Lim, Chong-Kook
    • Magazine of the Korean Society of Agricultural Engineers
    • /
    • v.13 no.4
    • /
    • pp.2419-2425
    • /
    • 1971
  • In many cold weather concrete constructison jobs calcium chloride $CaCl_2$ can be used safely as an accelerating admixture. For producing satisfactory concrete during cold weather calcium chloride is used to develop the level of strength required in a shorter period by obtaining higher early strength, the resulting in crease in heat of hydration. In this paper, to get adequated data and information of the effect on strength of concrete in using calcium chloride as an accelerating admixture, Portland cement (Type I), High-early-strength cement(Type II) and Pozzolans cement with certain 1.5 percentage of calcium chloride by weight of the cement were tested. As the result of this experiment, followings were founded: 1. At the 1.5 percent of calcium chloride cement ratio, the early strength was accelerated to the highest level, and some 1.5 percent of calcium chloride cement ratio was suitable for the stabilization of the concrete structures. 2. For Some 50 percent of Water Cement ratio was suitable, making good Concrete in the Cold weather by admixture of Calicum Chloide. 3. The concrete of Pozzorans cement in early strength was weak but that in later rised by degree. 4. As abtaining higher early strength the curing period can be reduced, but the finishing work should be done as early as possible.

  • PDF