지중송전계통에서 OF 및 XLPE 케이블 혼용 연계 운용의 효용성 평가 (Effectiveness Evaluation on Combined Connection Operation of OF and XLPE Cable)

  • 채직병;이종범
    • 전기학회논문지
    • /
    • 제64권6호
    • /
    • pp.857-863
    • /
    • 2015
  • OF cable with excellent reliability and economic efficiency, has been used as the main cable of underground transmission in Korea. However, as XLPE cable is excellent in view points such as reduction of loss, convenience on the construction/operation, and manufacturing technology, it has been replaced as instead of OF cable. Also, when the aging occurs in some sections of OF cable, the section is replaced as XLPE cable without changing of whole cable line. However, there are some differences like electrical constants between both types of cables. Therefore if underground transmission system will be operated as combined connection composited of both cables, it should be proved that overvoltage is stable in steady and transient state. This paper describes the effectiveness of connection operation in combined OF and XLPE cable. For the evaluation of effectiveness, some important analysis such as sheath component voltage, lightning and switching overvoltage, single line-to-ground fault are carried out in steady and transient state. EMTP/ATPDraw is used for modeling and analysis of system.

초초고압용 OF 케이블 접속함의 국산화를 위한 연구 (A Study on the Ultra-high Voltage Oil Filed Cable Joint)

  • 이수길;전승익;박완기;김화종;박양호
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1996년도 하계학술대회 논문집 C
    • /
    • pp.1825-1827
    • /
    • 1996
  • In this study, the Joint of 345kV OF $1C{\times}2000mm^2$ cable was developed to keep up with the trends that need higher-voltage & capacity underground transmission line. The type of joint developed was based on the two kinds of models that have had a good reliability internationally. The mechnic and electric characteristics of the sample specimen was managed in detail when it was manufactured and estimated. Especially, in order to prove the reliability of usage for 30 years, the method of long term aging test was studied. As a result of test, we knew that the joint developed had a good performance. From this study, it can be thought that future ultra-high voltage underground transmission line could be constructed by domestic technology.

  • PDF

전력케이블 대 용량화에 따른 환경과의 조화 및 보수의 고 신뢰도화 (A Study of Large Capability of Underground Power Transmission Line, Environmental and High reliability)

  • 정무영;권병일;남정세
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1996년도 하계학술대회 논문집 C
    • /
    • pp.1841-1843
    • /
    • 1996
  • To meet recent increasing demand for electric power in large cities in Korea, and to improve reliability of the power supply. Especially, demand for electric power apparatus places great emphasis on not only function but also environmental factors. In this paper, environpolitics describes according to large capacity demand for extra high voltage underground transmission lines and high reliability of the power supply.

  • PDF

지중송배전계통에서 과도상태시 공통접지의 영향 분석 (Analysis of Common Grounding Effect during the Transient State in Underground Transmission and Distribution Systems)

  • 임광식;이종범
    • 전기학회논문지
    • /
    • 제57권2호
    • /
    • pp.191-197
    • /
    • 2008
  • This paper describes the effect of transient state in underground transmission and distribution lines installed together in the same tunnel. Two systems installed in the same tunnel are operated by the common grounding. This paper analyzed that how much one of the two kinds of systems influences the other systems during the transient state by EMTP/ATPDraw. Single line-to-ground fault and lightning surge were selected in transient state condition. These cases were simulated variously according to the variation of common grounding magnitude, fault location and lightning surge magnitude. It is evaluated that the analyzed results will be used for establishment and operating materials of common grounding in the same tunnel.

케이블 삼상단락 실증시험을 통한 전자력 영향 검토 (The Study of Electromagnetic Force by Three Phase Short-Circuit Test of Cable)

  • 홍동석;김해준;박성민;장우석;박흥석;장태인;강지원
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 2009년도 제40회 하계학술대회
    • /
    • pp.395_396
    • /
    • 2009
  • This paper handles with effect of electromagnetic force on the cables by fault current accompanied by accident of underground transmission cable. Even though underground transmission cable is an essential transmission method to supply stable power for downtown and population center, interaction of electromagnetic force from fault current is very large comparing to overhead transmission line due to restricted installation space such as tunnel, etc. and close consideration is required for it. This paper describes the effect of electromagnetic force through results of three phase short-circuit test and electromagnetic force analysis using theoretical calculations and electrical evaluation test after three phase short-circuit test, which will be utilized as basic materials for improvement and development of cleat, hanger, etc. to reduce and release effect of electromagnetic force in the future.

  • PDF

154kV 지중 POF 케이블의 부식방지(腐蝕防止)에 관한 연구(硏究) (A Study on the Corrosion Control and Protection of 154kV Underground Pipe-type Oil Filled (POF) Cable)

  • 이동일;김정부;정동원;김대경;이종범;정성환
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 1990년도 추계학술대회 논문집 학회본부
    • /
    • pp.161-165
    • /
    • 1990
  • KEPCO has experienced eight oil leakage failures due to POF cable corrosion in the 154KV underground POF cable transmission line since the line was operated in 1976. Experimentally, We have verified that the cause of the failure is electrolytic corrosion of the cable owing to subway leakage current. For the countermeasure, We adopted the total Cathodic Protection System by the use of Victim Anode, Forced Drainage Method and Impressed Current Method with polarization cell.

  • PDF

Signal Transmission Properties of the Inductive Coupler using the High Permeability Magnetic Materials

  • Kim, Hyun-Sik;Kim, Jong-Ryung;Lee, Hae-Yeon;Kim, Ki-Uk;Huh, Jeong-Seob;Lee, Jun-Hui;Oh, Young-Woo;Byon, Woo-Bong;Gwak, Kwi-Yil;Ju, Seong-Ho
    • 한국전기전자재료학회논문지
    • /
    • 제19권4호
    • /
    • pp.339-343
    • /
    • 2006
  • We observed the application possibility of inductive coupler for the underground high-voltage power line communication by means of analysis of signal transmission characteristics and magnetic properties on annealing temperatures for high-permeability Fe-base amorphous alloys. The best electromagnetic and transmission characteristics were shown in nano-crystalline precipitated alloy annealed at temperature $510^{\circ}C$. The transmission characteristics in the low-frequency band depend on permeability of magnetic core materials and its properties of high-frequency band can be improved by impedance matching. Using the high pass filter embedded in the coupler, other noise signal band except for communication signals could be cut off.

지중송전케이블룡 디지털 거리계전 알고리즘 개선 (An Improvement of Digital Distance Relaying Algorithm on Underground Transmission Cables)

  • 하체웅;이종범
    • 대한전기학회논문지:전력기술부문A
    • /
    • 제49권12호
    • /
    • pp.595-601
    • /
    • 2000
  • This paper describes the improvement method of distance relaying algorithm for the underground transmission cables. Distance relaying algorithms have been mainly developing to protect the overhead transmission lines than the underground cables. If the cable systems are directly protected using distance relaying algorithm developed for overhead line without any improvement, there will be really occurred many misoperation in cable systems, because the cable systems consist of the conductor, the sheath, several grounding method, cable cover protection units(CCPUs), and grounding wire. Accordingly, the complicated phenomena are occurred, if there is a fault in cable systems. Therefore, to develope a correct distance relaying algorithm, such cable characteristics should be taken into account. This paper presents the process to improve distance relaying algorithm which is now used. REal cable system was selected to establish modeling in EMTP and ATP Draw. It was discovered through the detailed simulation during the fault that the large error existed between impedance measured at the relay point and real impedance is due to the resistance of grounding wire in each grounding method. And also compensation factor obtained by the simulation is proposed in this paper. It is proved that the factor proposed can fairly improve the accuracy of impedance at the relay point. It is evaluated that the protective ability will be really much improved, if the algorithm proposed in this paper is applied for cable systems of utility.

  • PDF

배전선로 접지저항 및 누설전류 실태조사 (Investigation for Earth Resistance and Leakage Current of D/L)

  • 이현구;하태현;배정효;하윤철;김대경
    • 대한전기학회:학술대회논문집
    • /
    • 대한전기학회 2003년도 추계학술대회 논문집 전력기술부문
    • /
    • pp.379-381
    • /
    • 2003
  • The sharing of common corridors by electric power transmission lines and pipelines is becoming more common place. However, such corridor sharing can result in undesired coupling of electromagnetic energy from the power lines to the near facilities. This causes induced voltages on underground metallic pipelines due to the power line currents. This could cause AC corrosion in the pipeline, which could in turn lead to disastrous accidents, such as gas explosion or oil leakage. This paper investigates for the limitation of induced voltage on the buried metal structures which is used in the inside and outside of the country. And then we measure the earth resistance and leakage current of 22.9kV distribution lines and pipe to soil potential of near pipelines in Seoul Korea. Hereby we can see the leakage current flowing through the earthing electrode have an effect on near pipelines.

  • PDF

소음 및 진동을 고려한 도심지 내 대단면 수직구 발파설계 사례 -싱가포르 Transmission Cable Tunnel EW2 공구- (Blasting Design for Large Shaft in Urban Area Considering Noise and Vibration -Singapore Transmission Cable Tunnel EW2-)

  • 김지연;이효;김도훈;고태영;이승철
    • 화약ㆍ발파
    • /
    • 제31권1호
    • /
    • pp.55-63
    • /
    • 2013
  • 싱가포르 전력구 터널 건설공사는 싱가포르 내의 전력수요 증가에 대응하기 위해 지하에 400kV의 고압 전기 케이블 등 송전설비 설치를 위한 터널을 건설하는 공사이다. 본 전력구는 총연장 35km의 터널로서 18.5km의 North-South Line의 3개 공구 (NS1, NS2, NS3)와 16.5km의 East-West Line의 3개 공구 (EW1, EW2, EW3)로 나누어 건설된다. 총 6개의 공구 중 SK건설은 EW2 공구와 NS2 공구를 수주하여 현재 시공중이다. 본 프로젝트의 과업 중 지상과 고압 송전 케이블 터널을 연결하는 수직구가 공구당 3~4개소가 있으며, 시공 중에는 TBM 발진용으로 활용된다. 지하 전력구는 싱가포르 내 도심 한복판을 가로질러 건설되며, 수직구 또한 대부분 도심지 내에 있어 수직구 굴착 시 발파 효율의 극대화와 동시에 싱가포르 소음 및 진동 기준을 만족하는 최적의 발파 설계가 요구된다. 싱가포르 전력구 터널 EW2 공구의 수직구 발파는 현지 허용 진동속도기준을 준수하고 국내의 우수한 발파 설계기술을 적용하여 설계되었으며 본 설계를 통하여 국내의 우수한 발파 설계 및 시공 기술을 전파할 좋은 기회가 될 것으로 기대된다.