A Case Study of Underpinning for Building Settlement Reduction (건물 침하방지를 위한 Underpinning 사례연구)

  • 박병기;이인모
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1993.10a
    • /
    • pp.57-62
    • /
    • 1993
  • Settlements of maximum 23cm have occurred in and Apartment building consturcted on a fill layer with pile foundations. The main reason of the settlements was due to the negative skin friction applied to the pile, and settlement of adjacent ground since most pile tips are acted as a floating foundation founded on the stratum where the SPT N value was mostly less than 30. To underpin this building, the Jumbo Special Pile grouging was adopted, and instrumented data showed little differential settlement after the JSP underpinning.

  • PDF

Application of D-ROG technology for restoration of the subsided building (침하건물 복원을 위한 정밀 다점 주입공법의 적용)

  • Lee, Ju-Hyung;Koh, Hyo-Seog;Hong, Jin-Pyo;Park, Jae-Hyun;Cho, Sam-Deok
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2009.03a
    • /
    • pp.405-410
    • /
    • 2009
  • This paper presents a case study that achieved both of serviceability and safety of the building through soil reinforcement and restoration around foundations subjected to serious differential settlement using D-ROG method. The building which has one basement floor and three ground floors is founded on soft ground and differential settlement occurred to the maximum extent of 678mm. The foundation type of the building is a independent mat foundation. Soil profiles consist of landfill layer, alluvial layer, weathered rock, and soft rock. The bearing layer consisting of gravel and weathered rock is located 16.0~17.0m below the bottom of the building. As a result of soil reinforcement and restoration, the recovery ratio of more than 90% can be attained with the maximum set-up of 657mm.

  • PDF

Tunneling-induced Building Damage Risk Assessment System (터널굴착에 따른 인접건물 손상위험도 평가시스템)

  • Park, Yong-Won;Yoon, Hyo-Seok
    • Journal of the Korean Geotechnical Society
    • /
    • v.18 no.3
    • /
    • pp.51-59
    • /
    • 2002
  • This paper deals with development of a damage risk assessment system for adjacent buildings to under-passing tunnel face considering 3D-ground movement. The system consists of building and ground information module, monitoring data module, settlement evaluation module, and building damage risk assessment module. The major modules, settlement evaluation module and building damage assessment module, are based on settlement estimation model suggested by Attewell et al (1982) and the building damage assessment method by Mair et al. (1996). After estimating 3D-ground movements due to tunneling with settlement evaluation module, damage assessment far buildings is performed using building damage risk assessment module. The developed system has two major functions; 1) calculation of 3D-settlement with ground loss ($V_{s}$)or maximum settlement ($w_{max}$) and inflection point (i) using various empirical formulae, monitoring data, numerical results, and so on; 2) assessment of damage risk for adjacent buildings of arbitrary section with position change of tunnel face. The field data given by Boscadin and Cording (1989) leer the case of two-storied masonry building near the Metro tunnel in Washington D.C. was simulated to verify the applicability of the developed system.

Influence characteristics of isolation piles on deformation of existing shallow foundation buildings under deep excavation

  • Liu, Xinrong;Liu, Peng;Zhou, Xiaohan;Wang, Linfeng;Zhong, Zuliang;Lou, Xihui;Chen, Tao;Zhang, Jilu
    • Geomechanics and Engineering
    • /
    • v.31 no.1
    • /
    • pp.1-14
    • /
    • 2022
  • Urban deep excavation will affect greatly on the deformation of adjacent existing buildings, especially those with shallow foundations. Isolation piles has been widely used in engineering to control the deformation of buildings adjacent to the excavation, but its applicability is still controversial. Based on a typical engineering, numerical calculation models were established and verified through monitoring data to study the influence characteristics of isolation piles on the deformation of existing shallow foundation buildings. Results reveal that adjacent buildings will increase building settlement δv and the deformation of diaphragm walls δh, while the isolation piles can effectively decrease these. The surface settlement curve is changed from "groove" type to "double groove" type. Sufficiently long isolation pile can effectively decrease δv, while short isolation piles will lead to a negative effect. When the building is within the range of the maximum settlement location P, maximum building rotation θm will increase with the pile length L and the relative position between isolation pile and building d/D increase (d is the distance between piles and diaphragm walls, D is the distance between buildings and diaphragm walls), instead, θm will decrease for buildings outside the location P, and the optimum was obtained when d/D=0.7.

Reliability assessment of EPB tunnel-related settlement

  • Goh, Anthony T.C.;Hefney, A.M.
    • Geomechanics and Engineering
    • /
    • v.2 no.1
    • /
    • pp.57-69
    • /
    • 2010
  • A major consideration in the design of tunnels in urban areas is the prediction of the ground movements and surface settlements associated with the tunneling operations. Excessive ground movements can damage adjacent building and utilities. In this paper, a neural network model is used to predict the maximum surface settlement, based on instrumented results from three separate EPB tunneling projects in Singapore. This paper demonstrates that by coupling the trained neural network model to a spreadsheet optimization technique, the reliability assessment of the settlement serviceability limit state can be carried out using the first-order reliability method. With this method, it is possible to carry out sensitivity studies to examine the effect of the level of uncertainty of each parameter uncertainty on the probability that the serviceability limit state has been exceeded.

Comparison of dynamic behavior of shallow foundations based on pile and geosynthetic materials in fine-grained clayey soils

  • Shariati, Mahdi;Azar, Sadaf Mahmoudi;Arjomand, Mohammad-Ali;Tehrani, Hesam Salmani;Daei, Mojtaba;Safa, Maryam
    • Geomechanics and Engineering
    • /
    • v.19 no.6
    • /
    • pp.473-484
    • /
    • 2019
  • In this paper, the geotechnical report of the Northern Fereshteh area in Tabriz is used and the characteristics of shallow foundation of a single pile and compared pile group and geogrid in terms of the settlement of a building foundation on clayey soil. Additionally, impacts of existing variables such as the number of geogrid layers, the length of the pile, and the depth of groundwater level affected by the dynamic load caused by the Taiwan Jiji earthquake via numerical analysis using PLAXIS software are examined. The results of fifty-four models indicated that the construction of a pile group with a diameter of 1 meter and a length of 14 meters significantly diminished the consolidation settlement of the soil in the Northern Fereshteh area, where the settlement value has been triggered by the load inflicted by earthquake. Moreover, the construction of four layers of geogrid at intervals of one meter led to a significant decrease in the settlement. Finally, after reaching a maximum depth, it had no reducing effects on the foundation settlement.

A Study on the Safety Assessment of Adjacent Structures Caused by Tunnel Excavation in Urban Area -Focused on the Characteristics of Geometries and Locations for Nearby Building- (도심지 터널 굴착에 따른 인접구조물의 손상평가에 관한 연구 (1) -지상 건물의 기하학적 및 위치적 특성을 중심으로-)

  • 김창용;문현구;배규진
    • Journal of the Korean Geotechnical Society
    • /
    • v.15 no.4
    • /
    • pp.19-42
    • /
    • 1999
  • In urban area, there are several major factors to be considered in tunnel design and construction. The first is to predict the magnitude and distribution of ground movements for particular ground conditions and construction procedures. The second is to assess the potential damage to nearby structures in response to the predicted ground movements. The third is to select the measures to be taken if a potential damage is foreseen. This study is concerned primarily with the first and second stages of the problem. Particularly, this paper is focused on the second stage to assess the potential damage to the nearby building with any type of geometries and locations above ground surface. In order to solve this problem, we introduced damage parameters(angular distortion, deflection ratio, maximum building settlements, maximum differential settlements, horizontal strain, etc.), and extended these parameters into 3-dimensional safety assessment. Also, to assess the safety of any walls existing in the building, we developed a 3-dimensional analysis program, and various parametric studies for the nearby building with any type of geometries and locations were presented. In addition to these parametric studies, we compared the results of the proposed techniques with some abroad case records for particular tunnels and adjacent buildings.

  • PDF

Deformation characteristics and stability analysis of semi-covered deep excavations with existing buildings

  • Linfeng Wang;Xiaohan Zhou;Tao Chen;Xinrong Liu;Peng Liu;Shaoming Wu;Feng Chen;Bin Xu
    • Geomechanics and Engineering
    • /
    • v.34 no.1
    • /
    • pp.87-102
    • /
    • 2023
  • The cover plate and the building loads often make the semi-covered deep excavations with existing buildings bearing asymmetric load, presenting different deformation characteristics with normal excavations, which is not absolutely clear in current studies. Based on a typical engineering, the building storeys, the basement storeys, the pile length, the existence of the cover plate (CP) and the depth of the diaphragm walls (DW) were selected as variables, and 44 groups of simulation were designed to study the influence of existing buildings and the semi-covered supporting system on the deformation of the excavations. The results showed that the maximum lateral displacement of DW, δhm, and the depth of δhm, Hm, are affected seriously by the building storeys and the basement storeys. Asymmetric structures and loading lead to certain lateral displacement of DW at the beginning of excavation, resulting in different relationships between δhm and excavation depth, H. The maximum surface settlement outside the pit, δvm, increases significantly and the location, dm, moves away from the pit with the building storeys increases. δvm has a quadratic correlation with H due to the existing buildings. CP and building load will affect the style of the lateral displacement curve of DW seriously in different aspects.

Time dependent behavior of piled raft foundation in clayey soil

  • Fattah, Mohammed Y.;Al-Mosawi, Mosa J.;Al-Zayadi, Abbas A.O.
    • Geomechanics and Engineering
    • /
    • v.5 no.1
    • /
    • pp.17-36
    • /
    • 2013
  • Settlement of the piled raft can be estimated even after years of completing the construction of any structure over the foundation. This study is devoted to carry out numerical analysis by the finite element method of the consolidation settlement of piled rafts over clayey soils and detecting the dissipation of excess pore water pressure and its effect on bearing capacity of piled raft foundations. The ABAQUS computer program is used as a finite element tool and the soil is represented by the modified Drucker-Prager/cap model. Five different configurations of pile groups are simulated in the finite element analysis. It was found that the settlement beneath the piled raft foundation resulted from the dissipation of excess pore water pressure considerably affects the final settlement of the foundation, and enough attention should be paid to settlement variation with time. The settlement behavior of unpiled raft shows bowl shaped settlement profile with maximum at the center. The degree of curvature of the raft under vertical load increases with the decrease of the raft thickness. For the same vertical load, the differential settlement of raft of ($10{\times}10m$) size decreases by more than 90% when the raft thickness increased from 0.75 m to 1.5 m. The average load carried by piles depends on the number of piles in the group. The groups of ($2{\times}1$, $3{\times}1$, $2{\times}2$, $3{\times}2$, and $3{\times}3$) piles were found to carry about 24%, 32%, 42%, 58%, and 79% of the total vertical load. The distribution of load between piles becomes more uniform with the increase of raft thickness.

A Case Study of the Piled Raft Foundation (Piled Raft 기초 적용사례 분석)

  • 김홍택;강인규;최효범;박시삼
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2002.03a
    • /
    • pp.597-604
    • /
    • 2002
  • The piled raft foundation Is an innovative design concept to reduce both the maximum settlement and differential settlements caused by concentrated building loads and load eccentricities, and also to reduce the bending moments of the raft. The main concern given in the design of piled raft foundations is proper judgments both of relative proportions of loads carried by the raft and piles, and of the effect of the pile support on the maximum and differential settlements In the present study, the piled raft foundation used in the foundation system of Richensia Building at Youido, Seoul is introduced and is carried out analyzing the results of field tests such as plate load tests, large plate load test, pile load test, and piled raft load test.