Study on Design and Construction of CFRD under Unfavorable Conditions (불리한 조건에서의 콘크리트 표면차수벽형 석괴댐 설계 및 시공)

  • Park Dong-Soon;Kim Hyoung-Soo
    • The Journal of Engineering Geology
    • /
    • v.16 no.1 s.47
    • /
    • pp.97-107
    • /
    • 2006
  • Or this study, prevailing design and construction methods of dam under various unfavorable conditions are summarized. for example, foundation treatment with large scale alluvium site or weathered rock mass, dam constructing techniques with unfavorable topographic conditions are studied for the better understanding of relating engineers. Also, zoning by using weak rocks and sand-gravel fill techniques are summed up.

Stability analysis on the concrete slab of the highest concrete-faced rock-fill dam in South Korea

  • Baak, Seung-Hyung;Cho, Gye-Chun;Song, Ki-Il
    • Geomechanics and Engineering
    • /
    • v.13 no.5
    • /
    • pp.881-892
    • /
    • 2017
  • Design and management of concrete slabs in concrete-faced rock-fill dams are crucial issues for stability and overall dam safety since cracks in the concrete face induced by stress, shrinkage, and deterioration can cause severe leakage from the reservoir into the dam. Especially, the increase of dam height to a certain level to enhance the storage capacity and to improve hydraulic stability can lead to undesirable deformation behavior and stress distribution in the existing dam body and in the concrete slabs. In such conditions, simulation of a concrete slab with a numerical method should involve the use of an interface element because the behavior of the concrete slab does not follow the behavior of the dam body when the dam body settles due to the increase of dam height. However, the interfacial properties between the dam body and the concrete slab have yet to be clearly defined. In this study, construction sequence of a 125 m high CFRD in South Korea is simulated with commercial FDM software. The proper interfacial properties of the concrete slab are estimated based on a comparison to monitored vertical displacement history obtained from the concrete slab. Possibility of shear strength failure under the critical condition is investigated based on the simplified model. Results present the significance of the interfacial properties of the concrete slab.

Characteristics Analysis of Principal Stress Ratio in Concrete Faced Rockfill Dam Using a Model Test (모형실험에 의한 콘크리트 표면차수벽형 석괴댐의 주응력비 특성 분석)

  • Kim Yong-Seong
    • Journal of The Korean Society of Agricultural Engineers
    • /
    • v.48 no.4
    • /
    • pp.33-40
    • /
    • 2006
  • In present study, the principal stress condition needed to conduct cubical large-scale triaxial test which can reflect three dimensional stress condition (or plain strain condition) in a dam was investigated by performing model test and numerical analysis and the principal stress ratio varying with the height of CFRD was examined. Also, the principal stress ratio in CFRD body was investigated from the monitoring results of horizontal and vertical earth pressure gages, installed in the center zone and lower part of transition zone of the dam body, respectively, in order to consider the principal stress condition in the large-scale triaxial test to model the behavior of CFRD. The result of the study indicated that the principal stress ratio decreased gradually from the lower to the upper part in the dam body for its center axis and was about 0.5 and 0.2 in the lower and upper part, respectively.

Recent Techniques for Design and Construction of CFRD (CFRD의 최근 설계ㆍ시공기술 동향)

  • Park Dong-Soon;Kim Hyoung-Soo;Lim Jeong-Yeul
    • The Journal of Engineering Geology
    • /
    • v.15 no.1
    • /
    • pp.77-86
    • /
    • 2005
  • CFRD(Concrete Faced Rockfill Dam) is in widespread use because this type of dam has superior characteristics in structural, material aspects comparing with earth cored rockfill dam. On this paper, up-to-date re-searches and techniques are summed up to be available for future needs in design and construction of CFRD. For example, such items as embankment using weak rock, experience of sand-gravel fill CFRD, connecting slab applied between plinth and face slab, raising experience of old dm, inverse filtration problem, environmental friendly zone, thickness and reinforcing of face slab, alluvial foundation treatment, and curb element method, are summarized for understanding of related engineers.

Framework for Estimating Appropriate Construction Duration of CFRD in the Planning Phase

  • Kim, In Kyum;Kim, Kyong Ju;Yun, Won Gun
    • International conference on construction engineering and project management
    • /
    • 2015.10a
    • /
    • pp.604-605
    • /
    • 2015
  • To secure quality of dam construction needs appropriate construction duration. Tight construction schedule may have negative influence on infrastructure quality, work safety and maintenance cost. It is necessary to reflect proper construction duration in the planning phase. There have been standards for estimating construction duration of building and industrial complex development but dam construction have not. In order to estimate construction duration of CFRD, feasible study reports and design reports were analyzed to acquire available information. After that, considering on construction duration methods such as comparison with similar cases, approximate estimating formula, approximate quantity assumption were adapted to Critical Path items. Hence, this study present framework for construction duration estimating of CFRD in the planning phase. This framework can be applied other types of dam along the same line.

  • PDF

Study on Seepage Behavior of Concrete Faced Gravel-Fill Dam (표면차수벽형사력댐의 침투거동에 관한 연구)

  • Cho, Sung-Eun;Kim, Ki-Young;Park, Han-Gyu;Ha, Ik-Soo
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.10a
    • /
    • pp.836-841
    • /
    • 2008
  • CFRD (Concrete Faced Rockfill Dam) has been world-widely constructed due to a lot of advantages compared with rockfill dam and recently, sand/gravel materials, instead of crushed rock materials, are also utilized as a main rockfill material to overcome geological and environmental problems. In this paper, the process of water infiltration into the originally unsaturated sand/gravel-fill dam is studied using two-dimensional saturated-unsaturated seepage theory. According to the results of seepage analysis, if the effective drainage zone is installed in the dam, the reservoir water infiltrate into the dam along a downward flow path towards the lower drainage area. The main body constructed with sand/gravel materials, therefore, remains unsaturated.

  • PDF

Crest Settlement Prediction of Concrete Faced Rock-Fill Dam After Initial Impounding (CFRD의 담수 후 정부침하량 예측)

  • Kim, Yong-Seong;Park, Han-Gyu;Lim, Heui-Dae
    • Proceedings of the Korean Society of Agricultural Engineers Conference
    • /
    • 2005.10a
    • /
    • pp.349-354
    • /
    • 2005
  • In this study, settlement characteristics of 23 CFRD was investigated from monitoring data and the method to estimate the crest settlements considering internal settlement during constructions was proposed. Moreover, crest settlement smaller than 20cm and deflection of face slab smaller than 20cm are not considered to be critical to the stability of large dam whose height is over 40m. Therefore, we assigned the region as safe zone that can be used as a guideline of maintenance of dam. These estimated data can be used in the design, construction and long-term maintenance in domestic CFRD hereafter.

  • PDF

Study on Seepage Behavior of Concrete Faced Gravel-Fill Dam with Cracked Face Slab (차수벽에 균열이 발생한 표면차수벽형사력댐의 침투거동 연구)

  • Cho, Sung-Eun;Park, Han-Gyu;Im, Eun-Sang;Kim, Ki-Young
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2009.03a
    • /
    • pp.866-873
    • /
    • 2009
  • CFRD (Concrete Faced Rockfill Dam) has been world-widely constructed due to a lot of advantages compared with rockfill dam and recently, sand/gravel materials, instead of crushed rock materials, are also utilized as a main rockfill material to overcome geological and environmental problems. In this paper, the process of water infiltration into the originally unsaturated sand/gravel-fill dam is studied using two-dimensional saturated-unsaturated seepage theory. According to the results of seepage analysis, if the effective drainage zone is installed in the dam, the reservoir water infiltrate into the dam along a downward flow path towards the lower drainage area. The main body constructed with sand/gravel materials, therefore, remains unsaturated.

  • PDF

Evaluation of the Compaction Characteristics of CFRD Construction Materials (CFRD 시공시 축조재료의 다짐특성 평가)

  • Han, Sang-Hyun;Yea, Geu-Guwen;Park, Jong-Hwa
    • The Journal of Engineering Geology
    • /
    • v.20 no.4
    • /
    • pp.415-424
    • /
    • 2010
  • A prototype of a Concrete-Faced Rock-fill Dam (CFRD) was constructed to evaluate the behavior of the materials in each zone within the dam. The tested materials, selected based on their grain size distribution, were used in constructing the prototype dam with layers of variable thickness, settlement ratio, and water content. We investigated the suitability of various values of hydraulic conductivity, water content, dry unit weight, and settlement ratio for zones within the dam. The test results revealed the relationships between the number of passes and the dry unit weight, between the dry unit weight and the settlement ratio, and between the settlement ratio and the number of passes. This paper focuses on the relationship between hydraulic conductivity and the number of passes. The results of the present analysis could be used to establish reasonable compaction standards for materials used in dam construction.