• Title/Summary/Keyword: 표준 공사기간

Search Result 59, Processing Time 0.025 seconds

Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model (초기 사업단계에서 표준공정모델을 이용한 가스 플랜트 공사의 개략적 공사기간 산정)

  • Moon, Sung-Woo;Park, Sang-Chun;Kwon, Ki-Nam
    • Korean Journal of Construction Engineering and Management
    • /
    • v.10 no.2
    • /
    • pp.26-33
    • /
    • 2009
  • The required level of detail in scheduling depends on the stages in the construction life-cycle. The objective of this study is to provide a Standardized Schedule Model (SSM) with an aim to facilitate the estimating of construction duration in the planning stage. The SSM modularizes work items; establishes relations between preceding and succeeding activities; and calculates approximate construction duration. The estimated duration of the SSM was compared with the detailed duration from the commercial scheduling tool using actual work activities. The difference showed to be ranged between -3.1% and +15%, which demonstrates that the SSM can be feasibly applied to the approximate estimation of construction duration.

A Study on Estimating Normal Project Duration of Apartment Remodeling Project (공동주택 리모델링공사 표준공기 설정에 관한 연구)

  • Yoon, Jongsik;Yu, Ilhan
    • Korean Journal of Construction Engineering and Management
    • /
    • v.18 no.2
    • /
    • pp.12-20
    • /
    • 2017
  • The biggest reason to prefer the remodeling is a relatively short period of time (5~6 years) compared to the reconstruction work that takes 8~9 years. In addition, from the perspective that the period of temporary residence is usually 24 months, the necessity of shortening is greater. Also, since the remodeling construction period is approximately 28~35 months on average, the strategies and efforts are needed to make up for the shortening the remodeling construction period. For these reasons, this paper is to develop an estimating model for normal project duration of apartment remodeling project. This model is reflected in the remodeling properties thorugh difference analysis of the new apartment construction project. Demolition works, reinforcement works, extension works are different, so this paper newly defines these construction work's duration in normal project duraion of remodeling. Case study and experts interviews are used to validate normal project duration. This model can be used to calculate rough construction period each alternatives, and will help a strategic decision making among the stakeholders.

Standardization of Factors Classification Associated with Cost and Schedule Variations in Road Construction Projects (도로건설공사 공사비·공사기간 증감요인 분류체계 표준화 연구)

  • Mun, Junbu;Lee, Juhui;Baek, Seungwon;Lee, Kangwook;Yun, Sungmin
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.43 no.6
    • /
    • pp.821-830
    • /
    • 2023
  • Various studies has tried to unveil causes of cost overrun and schedule delay in the road construction project. However, these causes need standardization due to difference by guidelines, relevant research, and facilities. Therefore, this study identifies and elaborate standard road construction cost and schedule variation factors that can be used in the planning and execution of the project. variation factors have been derived and grouped through literature review and modified and supplemented through expert interview. In addition, the connection with the relevant guidance factors is confirmed and the usability is reviewed by applying actual road construction cases. The factors suggested in this study comprehensively include factors of related guidelines and previous research, more clearly distinguish, support decision making.

A Study on Normal Project Period for Parking Lot of Aged Apartment Housing (노후 공동주택 주차장 리모델링 공사 표준공기 설정에 관한 연구)

  • Bang, Seongbae;Jang, JunYoung;Koo, Choongwan;Kim, Taewan;Lee, Chansik
    • Korean Journal of Construction Engineering and Management
    • /
    • v.22 no.6
    • /
    • pp.107-119
    • /
    • 2021
  • Recently, interest in remodeling apartment houses has been increasing due to problems such as a lack of parking spaces for old apartment houses. However, no method was suggested to predict the construction period of the apartment remodeling project. Unlike general apartment new construction, apartment remodeling construction involves demolition or reinforcement work, so a realistic remodeling construction period calculation plan differentiated from the existing construction period should be proposed. Therefore, this study intends to present a model for deriving the construction period of the underground parking lot of the apartment remodeling construction. Each construction period was calculated based on 19 activities of underground parking lot remodeling work through review of previous studies and expert advice. Activity's workload data and productivity data were derived to calculate the construction period, and the number of inputs and equipment inputs by Activity were determined to correct the productivity data. The construction period of Activity was calculated using the derived data, and the criteria for calculating the overlapping period for each Activity were presented to enable realistic construction period and scheduled schedule. As a result of predicting the accuracy of the construction period through the verification of the case complex, it is expected that it will be possible to predict the approximate construction period of the underground parking lot of the apartment remodeling construction in the future.

A Study on Standard Construction Process Management System for Prediction of Proper Construction Period of Subsea Tunnel (해저터널 적정 공사기간 예측을 위한 표준공정관리 체계 연구)

  • Bae, Keunwoo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.18 no.4
    • /
    • pp.36-47
    • /
    • 2017
  • As a typical domestic subsea tunnel construction the Gadeok subsea tunnel applying the method of immersed tunnel has been completed and the Boryeong-Taean subsea tunnel is under construction using NATM. The high-speed railway subsea tunnels between the Honam and Jeju are under consideration, and the feasibility of constructing subsea tunnels with Japan and China is also under consideration. However, it is difficult to provide the process plan information for the construction work such as the analysis of the feasibility of the subsea tunnel and the prediction of the proper construction period because there is no case of domestic construction for it applying the shield TBM method. Due to economic and other reasons, government organizations are reluctant to apply the shield TBM, and there is lack of data on the construction process management field using the shield TBM method. Therefore, a standard construction process management system for the subsea tunnel is needed to analyze the feasibility of the subsea tunnel and to predict the proper construction period. By presenting the standard construction process management system of subsea tunnels such as WBS, Network Diagram, and construction period calculation model, I hope to contribute technically and economically to future subsea tunnel projects.

Analysis of Standard Construction by TBM Diameter through the Rock Scenario Models in the Field (현장 암반 시나리오 모델을 통한 TBM 구경별 표준 공사기간 분석)

  • Park, Hong Taea;Lee, Yang Kyu
    • Journal of the Society of Disaster Information
    • /
    • v.9 no.2
    • /
    • pp.195-205
    • /
    • 2013
  • Construction Management means a comprehensive plan of given the resources and the operation of the elements to complete the construction within the construction period. The construction period of these shall be determined by calculation based on reliable initial business. However, in actual field, inaccurate task duration is determined to the intuitive judgments of representative, reference of a similar project construction period of the past. As previous studies for the improvement of existing methods, This study presented a standard model that can be utilized in the early stages of construction projects for the TBM method operating by diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m), and This study presented and calculated construction period which can estimated quickly the entire outline the construction period Therefore, When performing TBM construction work in the future, the total construction period which presented and analyze by TBM diameter, can be used as a useful material which plan and manage construction contracts, construction estimating, construction planning to the basic planning stage, and the basic design stage.

The Impacts of Reduced Labor Hours on the Construction Period and Cost of Tunnel Project (근로시간 단축에 따른 터널 공사의 표준 공기 및 공사비 영향 분석)

  • Park, Taeil;Kim, Kyunghoon;Shin, Eun-Young
    • Korean Journal of Construction Engineering and Management
    • /
    • v.20 no.2
    • /
    • pp.37-43
    • /
    • 2019
  • After the new standards for labor hours has been released, various problems come up in construction field, such as income reduction of employees, extension of construction period and increased construction cost. Although it is expected that the impact of the new standard on the construction industry is more worse than other industries form the view of productivity, not much works have been done to identify those impacts. Thus, this research proposes the standard construction processes, excavation cycle, and unit construction period for NATM tunnel project based on 'Construction Standard Production Rates.'The study also investigated the impact of reduced labor hours on the management of work crews, construction periods and costs of tunnel projects. The results showed that under the 52 labor hour standard, the construction periods for the excavation work and whole project was increased by 20% and 8.9%, respectively, but the construction costs for the excavation work and whole project was decreased by 1.4% and 0.6%, respectively.

A Study on Normal Project Duration for Water Resource Project (수자원시설 건설공사 표준공기 산정을 위한 기초연구)

  • Lee, Bongsu;Kim, Kinam;Lee, Minjae
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.1
    • /
    • pp.35-43
    • /
    • 2015
  • It is important to have enough design and construction duration for infrastructure projects. However, recent water resource project in Korea shows several problems caused by their fast-tract schedule. National Audit Committee report several water resource projects have quality problems caused by insufficient project duration. Especially, water resource projects such as dam and water pipeline construction should have proper time to secure their structure quality. Normal project duration for these projects should be estimated based on previous similar projects' historical data analysis. However there is no standard model which can estimate normal project duration for water resource projects in Korea. There are several normal project duration estimation models for building project developed by public(LH) and private construction companies. However, there is no proper model for water resource projects. So, this study developed normal project duration model for dam and water pipeline projects using historical data and show application of models.

Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension (공사기간 연장에 따른 추가간접비 사전합의 제도 도입 방안 연구)

  • Jeong, Ki-Chang;Lee, Jae-Seob;Park, Yang-Ho
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.6
    • /
    • pp.33-44
    • /
    • 2012
  • This study is as to payment improvement method of additional incidental cost to be occurred upon extension of public construction time. According to the result of analysis about the cause of non-payment of additional incidental cost of construction time extension through site examples, it was found that difficulties exist in disputes & proofing over the scope of actual cost recognition, and in this regard the result of experts opinion indicated that a construction extension pre-agreement system can be executed which agrees the scope of recognition of additional incidental cost of construction time extension once the statistical standard is clear and accurate. Accordingly, in this study, by totalling multiple sites data, calculations were implemented in terms of type of construction projects, amount of constructions, period of constructions. According to the result of calculation, the element of type of construction project and construction period appears to have none direct effect to the occurrence of additional cost of construction time extension, but direct relationship was indicated related to the contract amount element. In view of above, in this study a standard additional incidental cost of construction time extension was proposed, and presented a system improvement plan to implement the construction extension pre-agreement system.

Analysis of Standard Cost and the Construction Period Applied TBM Excavation Method (TBM 굴착 공법 적용 구경별 표준 공사비 및 공사기간 분석 연구)

  • Park, Hong Tae
    • Journal of the Society of Disaster Information
    • /
    • v.8 no.4
    • /
    • pp.319-327
    • /
    • 2012
  • This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based the data analyzed TBM operating productivity, This research derived and presented excavation speed(m/day) by TBM diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m) and rock. Also, based on the excavation speed(m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. Based on hard rock 40.0%, soft rock 30.0%, usually rock 20%, weathered rock 10.0%, TBM boring velocity, m per cost, total construction period shall estimate the construction cost and the construction period by the effective use by diameter when future applying TBM method to the basic planning stages and in the preliminary design phase.