Abstract
Construction Management means a comprehensive plan of given the resources and the operation of the elements to complete the construction within the construction period. The construction period of these shall be determined by calculation based on reliable initial business. However, in actual field, inaccurate task duration is determined to the intuitive judgments of representative, reference of a similar project construction period of the past. As previous studies for the improvement of existing methods, This study presented a standard model that can be utilized in the early stages of construction projects for the TBM method operating by diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m), and This study presented and calculated construction period which can estimated quickly the entire outline the construction period Therefore, When performing TBM construction work in the future, the total construction period which presented and analyze by TBM diameter, can be used as a useful material which plan and manage construction contracts, construction estimating, construction planning to the basic planning stage, and the basic design stage.
건설공정관리는 주어진 공기 내에 공사를 완료하기 위해 투입되는 자원과 요소작업들의 종합적인 계획을 말한다. 이중 공사기간의 산정은 사업초기 신뢰할만한 근거에 의해 결정되어야 한다. 그러나 실제 현장에서는 담당자의 직관적 판단, 과거 유사 프로젝트의 공기 참고 등의 부정확한 방법으로 개별 작업기간이 결정되고 있다. 이러한 기존 방식의 개선을 위한 선행연구로 본 연구는 TBM공법 $({\phi}2.6m,\;{\phi}3.0m,\;{\phi}3.5m,\;{\phi}5.0m,\;{\phi}8.0m)$ 운영을 위한 건설사업의 초기단계에서 활용할 수 있는 표준모델을 제시하여 신속하게 전체 개략공기를 추정할 수 있는 공기를 산정하여 제시하였다. 따라서 본 연구에서 TBM 구경별로 분석하여 제시한 총 공사기간은 향후 TBM 공사를 수행할 때, 기본계획단계와 기본설계단계에서 공사계약, 공사비 산정, 공정계획을 수립하고 관리하는데 유용한 자료가 될 것으로 확신한다.