Standardization of Factors Classification Associated with Cost and Schedule Variations in Road Construction Projects

도로건설공사 공사비·공사기간 증감요인 분류체계 표준화 연구

  • 문준부 (한국건설기술연구원 건설정책연구소 사후평가센터) ;
  • 이주희 (영남대학교 건설시스템공학과) ;
  • 백승원 (연세대학교 건설환경공학과) ;
  • 이강욱 (한국건설기술연구원 건설정책연구소 사후평가센터) ;
  • 윤성민 (영남대학교 건설시스템공학과)
  • Received : 2023.08.08
  • Accepted : 2023.11.01
  • Published : 2023.12.01

Abstract

Various studies has tried to unveil causes of cost overrun and schedule delay in the road construction project. However, these causes need standardization due to difference by guidelines, relevant research, and facilities. Therefore, this study identifies and elaborate standard road construction cost and schedule variation factors that can be used in the planning and execution of the project. variation factors have been derived and grouped through literature review and modified and supplemented through expert interview. In addition, the connection with the relevant guidance factors is confirmed and the usability is reviewed by applying actual road construction cases. The factors suggested in this study comprehensively include factors of related guidelines and previous research, more clearly distinguish, support decision making.

건설공사의 공사비 초과 및 공기 지연에 대한 원인 파악을 위해 공사비·공사기간 변동 요인을 조사하고, 이를 분석·관리하기 위한 노력이 이루어지고 있다. 하지만 이러한 변동 요인들은 관련 지침, 관련 연구, 시설물별로 매우 다양하여 표준화된 정보 수집 분석·관리체계의 필요성이 대두된다. 따라서 본 연구는 사업의 계획 및 진행단계에서 활용 가능한 표준 도로건설공사 공사비·공사기간 증감요인 분류체계를 제시하고자 한다. 본 연구는 국내·외 문헌 고찰을 통해 공사비·공사기간 증감요인을 도출 및 그룹핑한 후 전문가 자문을 통해 수정, 보완하였다. 또한 관련 지침 요인들과 연계성을 확인하고 실제 도로건설공사 사례를 적용하여 활용성을 검토하였다. 본 연구에서 제시한 표준 도로건설공사 공사비·공사기간 증감요인 분류체계는 관련 지침 및 연구들을 포괄적으로 포함하고, 증감요인을 더 명확히 구분하는 것을 확인하였으며, 실무적인 의사결정을 지원할 것으로 기대된다.

Keywords

Acknowledgement

This research was carried out under the Korea Institute of Civil Engineering and Building Technology (KICT) Research Program (Project No. 20230026-001, Operation of Post-Construction Evaluation and Management Center), funded by the Ministry of Land, Infrastructure, and Transport (MOLIT) of Korea and was also supported by Korea Institute for Advancement of Technology (KIAT) grant funded by the Korea Government (MOTIE) (P0008475).

References

  1. Akal, A. Y., El-Maaty, A. E. A. and El-Hamrawy, S. (2017). "Mapping the causes of time, cost overruns and quality shortfall in Egyptian Public Highway Projects." European Business & Management, SciencePG, Vol. 3, No. 6, pp. 120-126, https://doi.org/10.11648/j.ebm.20170306.14.
  2. Akinradewo, O., Aigbavboa, C., Oke, A., Coffie, H. and Ogunbayo, B. (2022). "Unearthing causative factors of cost overrun on ghanaian road projects." The Baltic Journal of Road and Bridge Engineering, Riga Technical University, Vol. 17, No. 4, pp. 171-188, https://doi.org/10.7250/bjrbe.2022-17.584.
  3. Alfakhri, A., Ismail, A., Muhamad, A. K., Arhad, I. and Irtema, H. (2017). "A conceptual model of delay factors affecting road construction projects in Libya." Journal of Engineering Science and Technology, Taylor's University, Vol. 12, No. 12, pp. 3286-3298.
  4. Al-Hazim, N. and Abusalem, Z. (2015). "Delay and cost overrun in road construction projects in Jordan." International Journal of Engineering and Technology, SPC, Vol. 4, No. 2, pp. 288-293, https://doi.org/10.14419/ijet.v4i2.4409.
  5. Ammar, T., Abdel-Monem, M. and El-Dash, K. (2022). "Risk factors causing cost overruns in road networks." Ain Shams Engineering Journal, Ain Shams University, Vol. 13, No. 5, 101720, https://doi.org/10.1016/j.asej.2022.101720.
  6. Anigbogu, N. A., Ahmad, Z. B. and Molwus, J. J. (2019). "Cost overruns on federal capital territory authority road construction projects." FUTY Journal of the Environment, Federal University, Vol. 13, No. 1, pp. 1-14.
  7. Aziz, R. F. and Abdel-Hakam, A. A. (2016). "Exploring delay causes of road construction projects in Egypt." Alexandria Engineering Journal, Elsevier, Vol. 55, No. 2, pp. 1515-1539, https://doi.org/10.1016/j.aej.2016.03.006.
  8. Chamuwange, S. K. and Ning, Y. (2022). "Identifying the factors affecting the cost management of road construction projects in Tanzania." Journal of Civil, Construction and Environmental Engineering, SciencePG, Vol. 7, No. 3, pp. 35-39, https://doi.org/10.11648/j.jccee.20220703.13.
  9. Creedy, G. D., Skitmore, M. and Wong, J. K. (2010). "Evaluation of risk factors leading to cost overrun in delivery of highway construction projects." Journal of Construction Engineering and Management, ASCE, Vol. 136, No. 5, pp. 528-537, https://doi.org/10.1061/(ASCE)CO.1943-7862.0000160.
  10. Dolage, D. A. R. and Dasantha, O. M. C. (2022). "Critical factors affecting cost overrun in foreign funded road construction projects in Sri Lanka." Engineer, The Institution of Engineers, Sri Lanka, Vol. 55, No. 2, pp. 21-30, https://doi.org/10.4038/engineer.v55i2.7505.
  11. Elawi, G. S. A., Algahtany, M. and Kashiwagi, D. (2016). "Owners' perspective of factors contributing to project delay: case studies of road and bridge projects in Saudi Arabia." Procedia Engineering, Elsevier, Vol. 145, pp. 1402-1409, https://doi.org/10.1016/j.proeng.2016.04.176.
  12. Huo, T., Ren, H., Cai, W., Shen, G. Q., Liu, B., Zhu, M. and Wu, H. (2018). "Measurement and dependence analysis of cost overruns in megatransport infrastructure projects: case study in Hong Kong." Journal of Construction Engineering and Management, ASCE, Vol. 144, No. 3, 05018001, https://doi.org/10.1061/(ASCE)CO.1943-7862.0001444.
  13. Kaliba, C., Muya, M. and Mumba, K. (2009). "Cost escalation and schedule delays in road construction projects in Zambia." International Journal of Project Management, Elsevier, Vol. 27, No. 5, pp. 522-531, https://doi.org/10.1016/j.ijproman.2008.07.003.
  14. Kim, S. J. and Kim, N. G. (2013). "Improvement on the total project cost management system for public construction project in civil engineering field." Proceedings of the 40th KIISE Fall Conference, pp. 17-18 (in Korean).
  15. Korea Development Institute (KDI). (2021). A Preliminary Feasibility Study of the Five-year Road Plan (in Korean).
  16. Korea Institute of Civil Engineering and Building Technology (KICT). (2020). A Study on the Efficient Operation and Utilization of Post-Construction Evaluation (in Korean).
  17. Kurniawan, D., Mairizal, Masril, Sam, A. R. M. and Abd Majid, M. Z. (2022). "Critical Risk Factor Affecting Cost Overrun in Highway Project of West Sumatera." Proceedings of IOP Conference Series: Earth and Environmental Science, IOP, Vol. 1022, No. 1, 012013, https://doi.org/10.1088/1755-1315/1022/1/012013.
  18. Lee, Y. M. (2013). Study on Cost Increasing Factor of Road in the Construction Phase, Msc. Dissertation, Pukyong National University (in Korean).
  19. Ministry of Economy and Finance (MOEF). (2022). Total Project Cost Management Guidelines, Available at: https://www.law.go.kr/admRulLsInfoP.do;jsessionid=fDQvsD4SbBizzxkOoIMheJ5rs0KRANU5w5N6IMna1IXqailo9TkZVMGETNQad8V6.de_kl_a1_servlet_LSW2?admRulSeq=2100000071778 (Accessed: June 6, 2023) (in Korean).
  20. Ministry of Land Infrastructure and Transport (MOLIT). (2022). post-Construction Evaluation Guidelines, Available at: https://law.go.kr/admRulLsInfoP.do?chrClsCd=&admRulSeq=2100000203300 (Accessed: June 6, 2023) (in Korean).
  21. Na, S. Y., Lee, D. H. and Kim, H. W. (2022). "Impact of highway construction on the regional economy: Gangil-Chuncheon Highway." Journal of the Korean Society of Industry Convergence, KSIC, Vol. 25, No. 6, pp. 1183-1190, https://doi.org/10.21289/KSIC.2022.25.6.1183 (in Korean).
  22. Santoso, D. S. and Soeng, S. (2016). "Analyzing delays of road construction projects in Cambodia: Causes and effects." Journal of Management in Engineering, ASCE, Vol. 32, No. 6, 05016020, https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.
  23. Seboru, M. A. (2015). "An investigation into factors causing delays in road construction projects in Kenya." American Journal of Civil Engineering, Vol. 3, No. 3, pp. 51-63, https://doi.org/10.11648/j.ajce.20150303.11.
  24. Sohu, S., Halid, A., Nagapan, S., Fattah, A., Latif, I. and Ullah, K. (2017). "Causative factors of cost overrun in highway projects of Sindh province of Pakistan." Proceedings of IOP Conference Series: Materials Science and Engineering, IOP, Johor Bahru, Malaysia, Vol. 271, No. 1, 012036, https://doi.org/10.1088/1757-899X/271/1/012036.
  25. Woo, S. K., Lee, Y. H., Chang, C. K. and Lee, S. W. (2012). "A study on analysis of productive construction project and influential elements for public owner's perspective: focused on highway construction." KSCE Journal of Civil and Environmental Engineering Research, KSCE, Vol. 32, No. 6D, pp. 645-653, https://doi.org/10.12652/Ksce.2012.32.6D.645 (in Korean).
  26. Yoon, B. H. (2009). Risk Assessment of Cost Increasing by Change Orders of Road Projects, Msc. Dissertation, Yonsei University (in Korean).
  27. Zafar, I., Yousaf, T. and Ahmed, D. S. (2016). "Evaluation of risk factors causing cost overrun in road projects in terrorism affected areas Pakistan a case study." KSCE Journal of Civil Engineering, KSCE, Vol. 20, No. 1, pp. 1613-1620, https://doi.org/10.1007/s12205-015-0348-6.