Development of One-way Void Support Device for Flexible Table Form (가변형 테이블폼용 일방향 중공관 지지장치 개발)

  • Kwon, Woobin;Lee, Dongmin;Lee, Changsu;Cho, Hunhee;Kang, Kyung-In
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2019.11a
    • /
    • pp.12-13
    • /
    • 2019
  • Flexible Table Form is being used more frequently at the level of formwork in construction site. However, one of the most common structural frameworks, the RC column-beam structure, is having problems in these factors. To improve this problems, this study developed support devices and proposed installation specifications to enable application of the one-way void slab method to flexible table form. It is expected that the effects of reducing the self-weight of the slab in the floor slab construction using flexible table form.

  • PDF

Design and Construction of a 1:5 Scale 10-Story R.C. Apartment Building Model for Earthquake Simulation Tests (지진모의실험을 위한 10층 R.C. 공동주택의 1:5 축소모델 설계 및 시공)

  • Hwang, Seong-Jun;Lee, Kyung-Bo;Kang, Chang-Bum;Lee, Han-Seon;Lee, Sang-Ho;Oh, Sang-Hoon
    • Journal of the Earthquake Engineering Society of Korea
    • /
    • v.15 no.6
    • /
    • pp.55-66
    • /
    • 2011
  • The purpose of this study was to develop an efficient process in the design and construction of a 1:5 scale 10-story R.C. apartment building model for an earthquake simulation test. The reduction ratio of the specimen was determined by the size ($5m{\times}5m$) and pay load (600kN) of the available shaking table and the availability of model reinforcements. For efficiency and quality control of the reinforcement work, prefabrication was used. Construction was conducted in two steps, the wall in one step, and another step for the slab, because it was impossible to remove the formwork of a wall if the walls and slabs in a story were constructed in one step. The slip form construction method was used repetitively for walls. The formwork of a wall was made with veneer and acryl plate on each side, so it was possible to check the quality of the concrete placing. To construct this model, it took roughly six months with five full-time research assistants, for a total of 602 man days of labor in construction.

Experimental Study on the Development of Void Precast Concrete Slab using Rubber Tube Mold for Inner Core (고무튜브 몰드 프리캐스트 콘크리트 유공 슬래브 개발에 관한 실험적 연구)

  • Bae, Kyu-Woong;Hong, Sung-Yub
    • Journal of the Korea Institute of Building Construction
    • /
    • v.21 no.4
    • /
    • pp.293-303
    • /
    • 2021
  • The void PC slab has a structurally reasonable cross-section by forming the hollow section of the neutral axis that is unnecessary for bending behavior. Domestic PC factories have introduced automation equipment to produce hollow PC slabs, and are achieving hollow sections through inserts. However, since the excessive initial investment cost of the PC factory is the main factor in the increase in production cost, other alternatives are needed. Therefore, in this study, when producing hollow PC slab members, by using a rubber tube as a formwork to form an internal hollow space, it is intended to contribute to securing productivity through molding various hollow shapes, making it larger, lightweight, and enabling rapid production. To implement a hollow PC slab using a rubber tube mold, the shape of a hollow cross-section in which the tube is combined was implemented by considering the shape of the rubber tube first. In addition, to secure the concrete quality of the hollow part, the finish properties of the rubber tube mold and concrete were evaluated, and the hollow PC production process was established.

Lateral Resisting Capacity for CFT Column to RC Flat Plate Slab Exterior Connections (CFT 기둥-RC 무량판 슬래브 외부접합부의 횡저항 성능)

  • Song, Ho-Beom;Song, Jin-Kyu;Oh, Sang-Won;Kim, Byung-Jo
    • Proceedings of the Korea Concrete Institute Conference
    • /
    • 2008.11a
    • /
    • pp.61-64
    • /
    • 2008
  • A combination of CFT column and RC flat plate without formworks is very effectively rapid constructions. This paper verified the lateral resisting capacity of CFT column-RC flat plate exterior connection in comparison with general RC column-flat plate connection and detected moment capacity and ductility capacity of connection according to moment-displacement ratio. We made and tested specimens which have different variables respectively and as a result derive a following conclusion. In CFT-E2 specimen a critical section was extended and maximum moment increased 20% respectively in comparison to general RC column specimen. In BME and CFT-E1 specimens generally shear governed behaviors and CFT-E2 specimen complemented with seismic band, flexure behavior region of slab was extended and also ductility ratio and energy absorptance increased.

  • PDF

Development of Prefabricated Voided-Slab Bridge Using PSC-I Girders (프리캐스트 I형 거더를 이용한 조립식 중공슬래브교 개발)

  • Kim, Hyun-Gi
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.18 no.6
    • /
    • pp.742-752
    • /
    • 2017
  • The bridge type of steel concrete composite rahmen or pre-flex has been applied where a lower depth girder is required due to vertical clearance restrictions caused by the crossing of rivers and roads. On the other hand, because these types are not only complicated to manufacture and construct, but also expensive, void slab bridges may be an alternative. In this study, prefabricated PSC-I shape girder was used to make a void slab and all procedures for bridge development, such as analysis, design, fabrication, and real-scale test, were included in the scope of research. The results of this study will provide sufficient background data to be applied to the field and the structural safety has been verified through experiments.

Continuity for Double Tee Slabs (더블티 슬래브의 연속화)

  • 유승룡
    • Journal of the Korea Concrete Institute
    • /
    • v.13 no.2
    • /
    • pp.99-106
    • /
    • 2001
  • The main objective of this study is to develop a continuity of double tee slab with two modified dap-ends to solve the problems of excessive moment, slab depth, deflection, and joint cracking in the original simply supported double tee slab systems. The modified joint is produced in a combination with two slabs with modified dap and one rectangular beam. The modified joint can be justified as following different merits. The span capacity for a design load is increased, while the deflection of the slab is decreased due to the decrease of positive moment at the center span of the slab. The joint cracking between slab and beam, which occur frequently in the original slab systems of double tee will be reduced. No more additional form work is needed to cast topping concrete for continuity. Three point loading tests are performed on the specimens with a variable of an amount of main longitudinal reinforcement to evaluate flexural and shear behavior. Following conclusions are obtained from the experimental investigation. The continuity of double tee slab effectively is provided by placing longitudinal steel reinforcement in the topping concrete over the connection, and generally leads to an increase in span capacity of double tee slabs with reduced deflection. It is more effective to control the initial cracking at the connection than that of some simply supported double tee slab systems.

A Study on the Structural Behavior of the Composite Slabs Using the New Shaped Deck Plate (신형상의 데크플레이트를 이용한 합성슬래브의 구조적 거동에 관한 연구)

  • Kim, Chang Woo;Choi, Sung Mo;Kang, Do An;Kim, Dong Kyu
    • Journal of Korean Society of Steel Construction
    • /
    • v.9 no.4 s.33
    • /
    • pp.589-600
    • /
    • 1997
  • Cold-formed deck sections are used in many composite floor slab applications wherein the steel deck serves not only as the form for the concrete during construction but also as the principal tensile reinforcement for the bottom fiber of the composite slab. This paper provides the results of an experimental study performed for the composite slabs with the new shaped deck plates with the locking ribs, the dove tails, and the powerful embossment, which are the mechanical means to improve positive interlocking effect between the deck and the concrete. A total of 28 specimens are tested to investigate the composite effects between the concrete and metal deck plate. Important parameters in this are the span length, the thickness of the deck plate, support condition, and whether shear studs are placed at each support or not. The test results are summarized for the maximum load and failure behavior for the specimens.

  • PDF

Development of Steel Wire-Integrated Deck Plate Applicable to Slab with 180mm Thickness (두께 180mm 슬래브에 적용 가능한 철선일체형 데크 플레이트 개발)

  • Lee, Yong Jae;Yoon, Sang Chun
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.16 no.1
    • /
    • pp.89-98
    • /
    • 2012
  • A steel wire-integrated deck plate that welds integrated triangle truss steel wires on a galvanized steel sheet is developed to reduce construction costs of slabs or formworks such as shores and supports, and it is already widely applied in many construction fields. In this research, experimental tests for 14 full scale specimens, which are in the same field conditions, are conducted on several parameters such as the diameter of top, bottom and lattice steel wire, cutting methods of ends. According to the result, changes in final destruction types of the test bodies and cutting methods of ends didn't affect structural performance of test specimens, and for a 4.0m-span test specimen, there was no big problems in using bottom bar D7 or D8.

Investigation of Shrinkage around Small Box of Short Span Slab (단경간 슬래브 중앙 소형박스(개구부)주변의 건조수축 거동 조사 연구)

  • Kim, Sang-Yeon
    • Land and Housing Review
    • /
    • v.7 no.4
    • /
    • pp.323-328
    • /
    • 2016
  • There are small box opening for inserting of electric lamp box in the slab of apartment. Around this box opening, we normally use the detailing of WWF or plastic ring strengthening to protect cracks induced by shrinkage. The shrinkage amount of slab box around was measured and analysed in order to consider validity of these strengthening methods and to find out economical alternative. Alternative of strengthening methods are normally used strengthening methods in construction companies, which are WWF strengthening, plastic ring strengthening and no strengthening methods. The shrinkage amount was measured using contact guage at the spot of tip attached around the box on slab of small area unit apartment which have small exclusive area below $59m^2$. Measured data shows that there are no big differences between all the 3 strengthening methods and Measure data range is $-264{\mu}{\varepsilon}{\sim}+216{\mu}{\varepsilon}$. Measured shrinkage is on trend slightly increase till 3~5weeks after removal of forms and then decrease. But amount of shrinkage are very low for all the slabs and there are no probabilities of concrete crack by shrinkage.