BIM is effective to improve the labor productivity of construction participants. From this point of view, it is important to analyze the outcome related with BIM Labor which covers most of the BIM investment costs. This research focuses on BIM RFI which is one of the major task of the BIM labor and analyze the outcomes. In addition, this research was quantitatively analyzed by the standby time and related cost caused by BIM labor, which affect the results of the project participants. To this end, analytical standby queue model was utilized to analyze the labor focusing on micros TASK. 11 projects were selected to analyze the results of BIM labor and RFI that the project participants requested to the BIM labor was collected. Through this, it collected variables for analyzing results, and Finally, we pulled out 4 projects for analysis. In this study, the basic results analysis of RFI processing of the BIM labor, the probabilistic analysis of BIM labor service status, and the economic analysis of BIM labor optimal inputs were performed by using the research model presented. The results of this study can be utilized to formulate the optimal strategy for BIM labor inputs(e.g. number of employees, level, time point, etc.) of the construction phase. Moreover, it can contribute to ensuring the credibility of the BIM ROI results by presenting the cost of BIM services in BIM ROI analysis and the standby cost of project participants.