A Study on the Wiring Plan Considering Construction and Frame Performance Degradation of BIPV System

BIPV시스템 시공 및 프레임 성능저하를 고려한 배선처리방안 제시에 관한 연구

  • Oh, Min-Seok (Department of Architectural Engineering, Dankook University) ;
  • Kim, Gi-Cheol (Department of Architectural Engineering, Dankook University)
  • Received : 2018.05.08
  • Accepted : 2018.08.06
  • Published : 2018.08.30

Abstract

In the application of the BIPV system, it is expected that the workability is lowered due to the difficulty in securing the space for wiring in the frame and the performance of the frame due to the wiring hole processing is lowered. Therefore, In this study, we propose a method to improve the wiring of the inner space of the BIPV frame, and through the simulation evaluation process, the thermal and condensation performance are secured by complementing the problems caused by the hole machining, and the time and effort required for BIPV construction are reduced. For this purpose, a wiring treatment method using a flange insertion tube was proposed, and the thermal and condensation performance was evaluated through simulation analysis.

Keywords

References

  1. Han, M. J., Seo, Y. S., Oh, M. S., and Kim, H. S., The Design Method and Environmental Performance Evaluation for Unit Type BIPV in High Rise Buildings, Journal of KIAEBS, Vol. 5, No. 4, pp. 236-243, 2011.
  2. Kim, J. S., Han, M. J., Oh, M. S., and Kim, H. S., A Study on an Construction Method by Simulations of Insulation and Condensation Performance of Inner Wiring Space in the BIPV System, Journal of the Architectural Institute of Korea Planning & Design, Vol. 26, No. 12, pp. 333-340, 2010.
  3. LBNL, THERM 7 / WINDOW 7 NFRC Simulation Manual, 2015.
  4. KATS, KS F 2295 Test Method of Dew Condensation for Windows and Doors, 2014.