클레임코스트를 고려한 프로젝트의 시간-비용 혼합정수계획모형

Considering Claim Costs in Project Time-Cost Mixed Integer Programming Model

  • 김종열 (한양대학교 산업공학과) ;
  • 강창욱 (한양대학교 ERICA캠퍼스 산업경영공학과) ;
  • 황인극 (공주대학교 산업시스템공학과)
  • Kim, Jong-Yul (Dept. of Industrial Engineering, Hanyang University) ;
  • Kang, Chang-Wook (Dept. of Industrial and Management Engineering, ERICA Campus, Hanyang University) ;
  • Hwang, In-Keuk (Dept. of Industrial and Systems Engineering, Kongju National University)
  • 투고 : 2011.08.02
  • 심사 : 2011.09.15
  • 발행 : 2011.09.30

초록

Previous researches have focused on the efficiency of project execution and the satisfaction of internal customers In view of the fact that a project is successful if any defects are not found in the short-term performance test of the project final outcome. To execute a project that both internal customer and external customer are satisfied in terms of longer-term benefit perspective, the project claim costs (PCC) which may occur for the warranty period of the project final outcome should be considered. We propose a model included PCC to the linear programming between time and cost to expedite a project and perform the validity test by applying the model to an example project. This model and related procedure will contribute to overall project activities' cost reduction by taking preventive actions for PCC.

키워드

참고문헌

  1. Anbari, F. T., Carayannis, E. G., and Voetsch, R. J.; "Post-Project Reviews as a Key Project Management Competence," Technovation, 28(10) : 633-643, 2008. https://doi.org/10.1016/j.technovation.2007.12.001
  2. Aoieong, R. T., Tang, S. L., and Ahmed, S. M.; "A Process Approach in Measuring Quality Costs of Construction Projects: Model Development," Construction Management and Economics, 20 : 179-192, 2002. https://doi.org/10.1080/01446190110109157
  3. Ashley, D. V.; "New Trends in Risk Management," Internet's 10th International Expert Seminar on New Approaches in Project Management, Zurich (March 10-12, 2008).
  4. Atkinson, R.; "Project Management: Cost, Time and Quality, Two Best Guesses and a Phenomenon, its Time to Accept Other Success Criteria," International Journal of Project Management, 17(6) : 337-343.
  5. Avots, I.; "Information Systems for Matrix Organisations" in Cleveland I (Ed.), Matrix Management Systems Handbook Van Nostrand Reinhold, New York, 535-537, 1984.
  6. Babu, A. J. G. and Suresh, N.; "Project Management with Time, Cost, and Quality Considerations," European Journal of Operational Research, 88 : 320-327, 1996. https://doi.org/10.1016/0377-2217(94)00202-9
  7. Balachandran, K. R., and Radhakrishnan, S.; "Quality Implications of Warranties in a Supply Chain," Management Science, 51(8) : 1266-1277, 2005. https://doi.org/10.1287/mnsc.1050.0408
  8. Barber, P., Graves, A., Hall, M., Sheath, D., and Tomkins, C.; "Quality Failure Costs in Civil Engineering Projects," International Journal of Quality and Reliability Management, 17(4/5) : 479-492, 2000.
  9. Barnes, N. M. L. and Wearne, S. H.; "the Future for Major Project Management," International Journal of Project Management, 11(3) : 135-142, 1993. https://doi.org/10.1016/0263-7863(93)90046-P
  10. Brucker, P. and Knust, S.; "Complex Scheduling," Springer-Verlag, 2006.
  11. Bryde, D. J.; "Project Management Concepts, Methods and Application," International Journal of Operations and Production Management, 23(7) : 775-793, 2003. https://doi.org/10.1108/01443570310481559
  12. CII.; "Cost of Quality Deviations in Design and Construction," Construction Industry Institute, Quality Management Task Force Publication, 10-1, 1989.
  13. Cnuddle, M.; "Lack of Quality in Construction - Economic Losses," in Proceedings of 1991 European Symposium on Management, Quality and Economics in Housing and other Building Sectors, 508-515, 1991.
  14. Hall, M. and Tomkins, C.; "A Cost of Quality Analysis of a Building Project: towards a Complete Methodology for Design and Build," Construction Management and Economics, 19 : 727-740, 2001.
  15. Heagy, C. D.; "Determining optimal quality costs by considering cost of lost sales," Journal of Cost Management, 4(3) : 64-72, 1991.
  16. Hillson, D.; "Extending the risk process to manage opportunities," International Journal of Project Management, 20 : 235-240, 2002. https://doi.org/10.1016/S0263-7863(01)00074-6
  17. Icmeli-Tukel, O. and Rom, W.O.; "Ensuring Quality in Resource Constrained Project Scheduling," European Journal of Operational Research, 103 : 483-496, 1997. https://doi.org/10.1016/S0377-2217(96)00305-0
  18. Kendrick, T.; "Identifying and Managing Project Risk, American Management Association, New York, 2003.
  19. Kim, J. Y., Kang, C. W., and Hwang, I. K.; "A Practical Approach to Project Scheduling : Considering the Potential Quality Loss Cost in the Time-Cost Tradeoff Problem," Published online of : International Journal of Project Management, 2011.
  20. Love, P. E. D., Mandai, P., and Li, H.; "Determining the Casual Structure of Rework in Construction," Construction Management Economics, 17(4) : 505-517, 1999. https://doi.org/10.1080/014461999371420
  21. Miguel, P. A. C. and Pontel, S.; "Assessing Quality Costs of External Failures (Warranty Claims)," International Journal of Quality and Reliability Management, 21(3) : 309-318, 2004. https://doi.org/10.1108/02656710410522748
  22. Pinto, J. K. and Slevin, D. P.; "Project Success: Definitions and Measurement Techniques," Project Management Journal, 19(3) : 67-73, 1988.
  23. Pinto, J. K. and Covin, J. G.; "Critical Factors in Project Implementation : a Comparison of Construction and R&D Projects," Technovation, 9 : 49-62, 1989. https://doi.org/10.1016/0166-4972(89)90040-0
  24. Rwelamila, P. D. and Hall, K. A.; "Total Systems Intervention : an Integrated Approach to Time, Cost and Quality Management," Construction Management and Economics, 13 : 235-241, 1995. https://doi.org/10.1080/01446199500000027
  25. Shenhar, A. J., Levy, O., and Dvir, D.; "Mapping the Dimensions of Project Success," Project Management Journal, 28(2) : 5-13, 1997.
  26. Simon, P., Hilson, D., and Newland, K.; "Project risk analysis and management guide," The Association for Project Management, Norwich, 1997.
  27. Ward, S. C.; "Assessing and managing important risks," International Journal of Project Management, 17(6) : 331-336, 1999. https://doi.org/10.1016/S0263-7863(98)00051-9
  28. Wateridge, J.; "How can IS/IT projects be measured for success?," International Journal of Project Management, 16(1) : 59-63, 1998. https://doi.org/10.1016/S0263-7863(97)00022-7
  29. Wiest, J. D.; "The Scheduling of Large Projects with Limited Resources," Unpublished Ph.D Thesis, Carnegie Institute of Technology, Pittsburgh, 1963.
  30. Wit, A.; "Measurement of Project Success," Project Management Journal, 6(3) : 164-170, 1988. https://doi.org/10.1016/0263-7863(88)90043-9
  31. Yogeswaran, K., Kumaraswamy, M. M., and Miller, D. R. A.; "Claims for Extensions of Time in Civil Engineering Projects," Construction Management and Economics, 16 : 283-293, 1998. https://doi.org/10.1080/014461998372312
  32. Yun, W. Y.; "Expected Value and Variance of Warranty Cost of Repairable Product with Two Types of Warranty," International Journal of Quality and Reliability Management, 14(7) : 661-668, 1997. https://doi.org/10.1108/02656719710367389