• Title/Summary/Keyword: temporary retaining system

Search Result 36, Processing Time 0.023 seconds

Safety Management of the Retaining Wall Using USN Sonar Sensors (USN 초음파 센서를 활용한 흙막이 안전관리)

  • Moon, Sung-Woo;Choi, Eun-Gi;Hyun, Ji-Hun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.6
    • /
    • pp.22-30
    • /
    • 2011
  • In the construction operation, foundation work should be done in advance for the building structure to be installed. This foundation work include a number of activities such as excavation, ground water prevention, piling, wale installation, etc. Caution should be taken in the operation because the dynamics of earth movement can cause a significant failure in the temporary structure. The temporary structure, therefore, should be constantly monitored to understand its behavior. This paper introduces the USN-based monitoring system to automatically identify the behavior of the temporary structure in addition to visual inspection. The autonomous capability of the monitoring system can increase the safety in the construction operation by providing the detailed structural changes of temporary structures.

Field Application of Up-Up Construction Using Buried Wale Continuous Walt System Method (CWS공법(Buried Wale Continuous Wall System)을 적용한 Up-Up 시공사례)

  • Lee Jeong-Bae;Lim In-Sig;Kim Dong-Hyun;Oh Bo-Hwan;Ha In-Ho;Rhim Hong-Chul
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2006.05a
    • /
    • pp.1-4
    • /
    • 2006
  • A down construction method is frequently used in these days to reduce popular discontent and to assure sufficient working space at early stage in downtown area. There are two main problems in the existing down construction method. One is a confliction between frame works and excavation works, and the other is a cold joint in retaining wall which is unavoidable due to a sequence of concrete placement and induces a water leakage. Therefore, a new method is needed to overcome these problems. The CWS (buried wale Continuous Wall System) method was developed by authors. By replacing RC perimeter beam with embedded steel wale, the steel frame works of substructure can be simplified and the water leakage can be prevented using continuous retaining wall. Consequently, the improved duality and reduction of construction period can be obtained from CWS method.

  • PDF

Study on Development of CWS (buried wale Continuous Wall System) Method (CWS공법(buried wale Continuous Wall System)의 개발에 관한 연구)

  • Lee Jeong-Bae;Lim In-Sig;Chun Sung-Chul;Oh Boh-Wan;Ha In-Ho;Rhim Hong-Chul
    • Journal of the Korea Institute of Building Construction
    • /
    • v.6 no.2 s.20
    • /
    • pp.81-89
    • /
    • 2006
  • A down construction method is frequently used in these days to reduce popular discontent and to assure sufficient working space at early stage in downtown area. There are two main problems in the existing down construction method. One is a confliction between frame works and excavation works, and the other is a cold joint in retaining wall which is unavoidable due to a sequence of concrete placement and induces a water leakage. Therefore, a new method is needed to overcome these problems. The CWS (buried wale Continuous Wall System) method was developed by authors. By replacing RC perimeter beam with embedded steel wale, the steel frame works of substructure can be simplified and the water leakage can be prevented using continuous retaining wall. Consequently, the improved qualify and reduction of construction period can be obtained from CWS method.

An Experimental Study on Compressive Loading Capacity of Precast Concrete Truss System (프리캐스트 콘크리트 트러스 시스템의 압축 내하력 실험 연구)

  • Han, Man-Yop;Jeon, Se-Jin
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.33 no.3
    • /
    • pp.889-900
    • /
    • 2013
  • In a large scale of excavation for the foundation of large-sized structures and underground structures, a considerable amount of earth pressure can occur. Steel beams that have been used to form a temporary structure to support earth pressure may be less economical and less efficient in resisting the high earth pressure. To cope with this problem, PCT(Precast Concrete Truss) system has been devised and investigated both experimentally and analytically. A proper connection method between the concrete truss members was proposed to accommodate fast assembly and disassembly. Full-scale test of PCT system was performed to verify the load-carrying capacity of the PCT system including the connections. The test results were compared with those of structural analysis. The test specimen which corresponds to PCT strut attained the ultimate load without buckling, but the detail of connector members needs to be improved. It is expected that precast concrete truss members can be efficiently incorporated into a temporary structure for deep and large excavation by replacing conventional steel beams.

A Study on Deformation Analysis of the Earth Retaining Wall (흙막이벽체의 변형해석에 관한 연구)

  • Lee, Song;Kim, Seong-Koo
    • Journal of the Korean Geotechnical Society
    • /
    • v.24 no.2
    • /
    • pp.27-36
    • /
    • 2008
  • This paper analyzed the effects related to the difference of the geometrical shape of the ground excavation by comparing the displacements of the earth retaining wall of the strut resulting from the change of the excavation breadth B and the excavation length L, adopting the three dimensional FDM analysis. It appeared that the displacement of the earth retaining wall of the strut increases in accordance with the increase of L/B and it decreases as it becomes nearer from the center to the comer where the temporary structural system forms, and the wale member is closured because of the effects of the confining effect by the closure of the earth retaining wall and the wale member. This paper proposed a formula in which the results of three dimensional FDM analysis which considers the shape of the excavation plane can be obtained from those of two dimentional FDM analysis which does not consider the shape of the excavation plane. And the results of the formula were compared with those of the site instrumentation analysis.

Heavy Metal Contamination of Roadside Gully-Pot Sediments, Seoul, Korea

  • Kim, Sung-Hwan;Lee, Pyeong-Koo;Yun, Seong-Taek;So, Chil-Sup
    • Proceedings of the Korean Society of Soil and Groundwater Environment Conference
    • /
    • 2001.04a
    • /
    • pp.222-225
    • /
    • 2001
  • In urban environments, the surface land impermeability fundamentally related to urban growth emphasizes the environmental problems such as the storm water peak flow (so-called the urban flooding) and the pollution. The conventional urban drainage system provides a number of temporary reservoirs intercepting and retaining surface-derived pollutants following their introduction to and deposition upon the impermeable surface. Gully-pots are common features in urban drainage systems in Korea, which were installed for draining rainwater to prevent regurgitation in rainy season and retaining larger particles, hence minimizing pipe blockage problems. When the road runoff conveying sediment enters a gully-pot, the sediment mixes with the gully liquor causing direct pollution of receiving waters. The characteristics of local sediment contamination are usually related to the types of land use activities that take place or have taken place within the area., This study was undertaken to evaluate the spatial and temporal variations of the contamination of gully-pot sediments in Seoul with respect to heavy metals such as As, Cd, Co, Cr, Ni, Pb, Cu and Zn. The heavy metal data were examined according to the land use type. In this paper, sampling sites in Seoul were divided into six groups (commercial area, industrial area, residental area, motor way, rural area, and local pollution).

  • PDF

Development of a trench shield machine for the near-surface railway construction (저심도 철도 건설을 위한 트렌치 쉴드 장비 개발연구)

  • Lee, So-Oh;Sagong, Myung;Kim, Sang-Hwan
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.2
    • /
    • pp.175-187
    • /
    • 2015
  • In this paper, the development of trench shield machine for near-surface railway construction were presented. The Near-surface railway can be constructed by cut and cover construction method, because it is installed at the depth of 5~7 m below roads. The cut and cover construction method mostly use temporary supports. The limitation of the cut and cover method is high installation cost and long construction period. To overcome these disadvantages, development of the trench shield machine is proposed and expected to shorten the construction time and cost of near-surface railway system. The sliding retaining wall of trench shield equipment replaces the role of temporary support (solider piles and lagging) and excavator equiped to the bottom front of the machine shorten the excavation time. This paper deals with design of the bit attached to the excavator and required capacity of the motor.

Multi-Criteria Decision-Making Model Using Quality Function Deployment (QFD) Method for the Most Suitable Temporary Earth Retaining System

  • Jung, Bae Yu;Byung, Cho Han;Jin, Han Sang;Won, Kwon;Ho, Jo Jae;Youl, Chun Jae
    • International conference on construction engineering and project management
    • /
    • 2015.10a
    • /
    • pp.620-621
    • /
    • 2015
  • In this study, the multi-criteria decision-making model based on Quality Function Deployment Method is proposed. Multicriteria decision-making is an attempt to link QFD method with the TOPSIS. By this effort, a model that makes client's decision-making more rational and objective in design phase is suggested. The multi-criteria decisionmaking model confirming to the Owner's requirements will improve the productivity of the construction industry and the satisfaction of the customer. Further study extending the range of the requirements, not only the Owner's requirement will be necessary to cover the various factors as much as possible. And then, finally as a flexible platform to achieve a sustainable quality management, web-based multi-criteria decision-making model can be utilized by the relevant stakeholders simultaneously with the feed-back and sharing the necessary informations.

  • PDF

Estimation of Ponding Times for various Soil Textures and Ponding Depths -Using the Green-Ampt Infiltration Model- (토성별 특정 수심의 저류된 유출수의 지하침투 소요시간 산정에 관한 연구 -Green-Ampt 방정식 적용을 중심으로-)

  • 권경호;안동만
    • Journal of the Korean Institute of Landscape Architecture
    • /
    • v.27 no.5
    • /
    • pp.170-180
    • /
    • 2000
  • The surface-drainage system, which consists of bio-swale and detention-infiltration Basins and carries out the function of temporary detention-infiltration of runoff, is defined as the "natural drainage system". It is an environmentally sound and economically beneficial practice to reduce run-off by retaining it in swales as much as possible and letting run-off infiltrate into the ground. In order to estimate appropriate capacity of swales, it is necessary to know how long will it take for certain depths of water to infiltrate. The ponding times, or infiltration times, of various depths and of various soil textures, could be estimated with the Green-Ampt Infiltration Model. Included soil textures are loamy sand, sandy loam, loam, silty loam, sandy clay loam and clay loam. Ponding depths are from 10cm to 100cm intervals. Newton-Raphson method is used for the solution of the Green-Ampt equation by a computer program. The computer program was written with the FORTRAN Developer 4.0 v.. Selected ponding depth is acceptable when the sum of the ponding time and the breeding time of mosquitoes is less than the tolerance period of innundation of grasses and trees.and trees.

  • PDF

Weatherability Assessment of Nonwoven Geotextiles by Field Exposure Test (현장노출시험에 의한 부직포 지오텍스타일의 내후성 평가)

  • Jeon, Han-Yong;Yuu, Jung Jo;Kim, Young Yoon;Byun, Sung Weon;Byun, Sung Weon
    • Journal of the Korean Geosynthetics Society
    • /
    • v.3 no.1
    • /
    • pp.37-42
    • /
    • 2004
  • In the reinforced retaining wall system, non-woven geotextiles are placed at the face of reinforced earth until the facing blocks are built up. And when this system is used as temporary structure, geotextiles facings are exposed to sunlight during service lifetime. During these periods, degradation of nonwoven geotextiles are occurred by UV light. So the UV-resistance of nonwoven geotextiles must be assessed correctly, in considering of the site conditions. In this study, laboratory test and the field test have been performed to evaluate the UV resistance of non-woven geotextiles used in KOESWall system and the results are expressed in terms of tensile characteristics & SEM photographs.

  • PDF