• Title/Summary/Keyword: Urban Excavation

Search Result 291, Processing Time 0.033 seconds

Case Study of Earth Anchor Axial Force Change Characteristic through Monitoring during Construction Period (시공중 계측을 통한 어스앵커 축력변화 특성사례 연구)

  • Kim, Sung-Wook;Han, Byung-Won
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2004.03b
    • /
    • pp.285-292
    • /
    • 2004
  • Earth Anchor method as a supporting system is widely used in the large scale deep excavation of urban areas or slope excavation project. Considering the application frequency of that method and catastrophe of that method under unproper construction management, we can find out many problems relevant to the domestic design and construction management of earth anchor method. When we encounter the cases of rapid increments and various decrements in earth anchor axial forces, considering the characteristic of earth anchor method, it is an essential point to catch the reasons and to prepare countermeasures. This article introduces two actual monitoring examples based on the close analyses of measured data in a typical large scale deep excavation project and slope excavation project. One is a rapidly increasing case of earth anchor axial forces with the continuous advance of incremental deformation in a geological layer interface. And another is a decreasing case of earth anchor axial forces with the construction conditions. The effort of this article aims to improve and develop the technique of design and construction in the coming projects having similar ground condition and supporting method.

  • PDF

Measures to control deformation in deep excavation for cut and cover tunneling

  • Nam, Kyu-Tae;Jeong, Jae-Ho;Kim, Seung-Hyun;Kim, Kang-Hyun;Shin, Jong-Ho
    • Geomechanics and Engineering
    • /
    • v.29 no.3
    • /
    • pp.339-348
    • /
    • 2022
  • The bored tunneling method is generally preferred for urban tunnel construction, However the cut & cover tunnel is still necessary for special conditions, such as metro station and access structures. In some case, deep excavation for cut & cover construction is planed of irregular and unusual shape, as a consequence, the convex and concave corner is often encountered during that excavation. In particular, discontinuity or imbalance of the support structure in the convex corner can lead to collapse, which may result in damages and casualties. In this study, the behavior of the convex corner of retaining structure were investigated using 3-dimensional numerical models established to be able to simulate the split-shaped behavior of convex corners. To improve the stability in the vicinity of the convex corner, several stabilizing measures were proposed and estimated numerically. It is found that linking two discretized wales at the convex corner can effectively perform the control of deformation. Furthermore, it was also confirmed that the stabilizing measures can be enhanced when the tie-material linking two discretized wales is installed at the depth of the maximum wall deflection.

A simplified framework for estimation of deformation pattern in deep excavations

  • Abdollah Tabaroei;Reza Jamshidi Chenari
    • Geomechanics and Engineering
    • /
    • v.37 no.1
    • /
    • pp.31-48
    • /
    • 2024
  • To stabilize the excavations in urban area, soil anchorage is among the very common methods in geotechnical engineering. A more efficient deformation analysis can potentially lead to cost-effective and safer designs. To this end, a total of 116 three-dimensional (3D) finite element (FE) models of a deep excavation supported by tie-back wall system were analyzed in this study. An initial validation was conducted through examination of the results against the Texas A&M excavation cases. After the validation step, an extensive parametric study was carried out to cover significant design parameters of tie-back wall system in deep excavations. The numerical results indicated that the maximum horizontal displacement values of the wall (δhm) and maximum surface settlement (δvm) increase by an increase in the value of ground anchors inclination relative to the horizon. Additionally, a change in the wall embedment depth was found to be contributing more to δvm than to δhm. Based on the 3D FE analysis results, two simple equations are proposed to estimate excavation deformations for different scenarios in which the geometric configuration parameters are taken into account. The model proposed in this study can help the engineers to have a better understanding of the behavior of such systems.

A preliminary study on the use of analytic hierarchy process for selecting a optimum trenchless excavation method (최적의 비개착공법 선정을 위한 계층분석법의 적용에 관한 기초연구)

  • Kang, Tae-Ho;Chang, Soo-Ho;Choi, Soon-Wook;Lee, Chulho;Cho, Jinwoo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.6
    • /
    • pp.685-693
    • /
    • 2015
  • There have been high demands for urban underground structures. However, they should be rapidly constructed while maintaining the functions of adjacent structures and road systems especially in urban areas. In this respect, trenchless excavation methods are considered to very effective in minimizing ground displacements during excavation works. A variety of field conditions such as economic, technical and environmental aspects should be taken into consideration when an optimum trechless excavation method is to be chosen in a given condition. Therefore, this study aims to carry out a fundamental study to select an optimum trenchless excavation method by the decision making technique. Especially, AHP (Analytic Hierarchy Process) which is a kind of a multiple attribute decision making process is adopted to consider the opinions of experts and to derive reliable decision criteria. As a result, the weights of key factors and the most effective trenchless methods for different ground conditions were proposed in this study.

Development and Application of Construction Control System for Excavation (굴착 관리 정보화 시스템의 개발 및 적용)

  • 권오순;정충기;김재관;이해성;김명모
    • Journal of the Korean Geotechnical Society
    • /
    • v.15 no.4
    • /
    • pp.153-166
    • /
    • 1999
  • Since the reliability of results by the existing analyzing method is low, in the case of for excavation performed in urban area whose stability is of great importance, construction control based on field monitoring is always necessary. But the field monitoring reflects only the behavior of construction process that has already been carried out, and it has limitations in predicting the behavior of the expected construction process, which is practically more important for construction control. In this study, construction control system for excavation which can predict the behavior of the expected processes during construction with high degree of accuracy, is developed by adopting inverse analysis. The inverse analied applied field monitoring results to excavation analysis can improve the reliability of predicted results. The developed system uses an elasto-plastic soil spring model for the excavation analysis and the minimization of least squared errors between measured displacements and calculated displacements for the inverse analysis. All the required processes for construction control can be performed as an integrated work within the system reflecting real time application and user's convenience. Their applicabilitis are confirmed by two case studies.

  • PDF

Parametric Study on Displacement of Earth Retaining Wall by the Bermed Excavation Using Back Analysis (역해석을 통한 소단굴착에 따른 흙막이 벽체변위의 매개변수 연구)

  • Lee, Myoung-Han;Kim, Tae-Hyung
    • Journal of the Korean Geosynthetics Society
    • /
    • v.14 no.4
    • /
    • pp.23-33
    • /
    • 2015
  • Together with the wall stiffness, a berm has the role of deciding the stability of a temporary retaining wall before structure installation after excavation. Especially in case of loose or soft soil excavated ground, the role of berm is very important. In this study, the measurement data obtained from the temporary retaining wall in the bermed excavation site in urban and numerical analysis are used to investigate the effects of berm's dimension (width and slope), excavation depth and ground property on the maximum horizontal displacement of the temporary retaining wall. The measurement data indicated that the wall displacement varied to the berm's width. That is, as the berm width decreased, the wall displacement increased. As a result of numerical analyses, the maximum wall displacement increased as slope increased and berm width decreased. This means that the berm is effectively restrained to the wall displacement. As excavation depth increased, the effect of berm's slope and width increased. In case of the same berm condition, the wall displacement restrained as ground property increased.

Investigation of crack growth in a brick masonry wall due to twin perpendicular excavations

  • Mukhtiar Ali Soomro;Dildar Ali Mangnejo;Naeem Mangi
    • Geomechanics and Engineering
    • /
    • v.34 no.3
    • /
    • pp.251-265
    • /
    • 2023
  • In urban construction projects, it is crucial to evaluate the impacts of excavation-induced ground movements in order to protect surrounding structures. These ground movements resulting in damages to the neighboring structures and facilities (i.e., parking basement) are of main concern for the geotechnical engineers. Even more, the danger exists if the nearby structure is an ancient or masonry brick building. The formations of cracks are indicators of structural damage caused by excavation-induced ground disturbances, which pose issues for excavation-related projects. Although the effects of deep excavations on existing brick masonry walls have been thoroughly researched, the impact of twin excavations on a brick masonry wall is rarely described in the literature. This work presents a 3D parametric analysis using an advanced hypoplastic model to investigate the responses of an existing isolated brick masonry wall to twin perpendicular excavations in dry sand. One after the other, twin perpendicular excavations are simulated. This article also looks at how varying sand relative densities (Dr = 30%, 50%, 70%, and 90%) affect the masonry wall. The cracks at the top of the wall were caused by the hogging deformation profile caused by the twin excavations. By raising the relative density from 30% to 90%, excavation-induced footing settlement is greatly minimized. The crack width at the top of the wall reduces as a result of the second excavation in very loose to loose sand (Dr = 30% and 50%). While the crack width on the top of the wall increases owing to the second excavation in medium to very dense sand (Dr = 70% and 90%).

Track Stability Assessment for Deep Excavations in Adjacent to Urban Railways (도시철도 인접지반 깊은 굴착 시 궤도 안정성 평가)

  • Jeon, Sang-Soo;Lee, Sang-Seung
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.19 no.6
    • /
    • pp.614-627
    • /
    • 2018
  • Urban railway lines have been constructed adjacent to residential buildings and urban areas. The expansion of transportation networks and reconstruction of residential buildings in highly populated urban areas require deep excavations in areas adjacent to urban railways. Mobilized soil stresses and changes in the groundwater level induced by deep excavations results in track irregularities in urban railways. In this study, a three-dimensional finite difference model using the commercial program FLAC3D was adopted to estimate the horizontal displacements of earth retaining structures, settlements of backfill, the stability of track irregularity and underground box structure based on the criteria of each railway organization and its relationships. In deep excavations, a change in groundwater level induces relatively very small differences for track gauge irregularities, whereas relatively large differences for longitudinal irregularities of 72.5%, twist irregularities of 83.3%, cross level irregularities of 61.9%, and alignments of 43.3% were found to be the maximum differences when the horizontal displacement of earth retaining wall and settlement of backfill were 65.1% and 21.4%, respectively, because the groundwater level (GWL) on the ground surface-mobilized tensile strength of the underground box structure exceeds the allowable value. Therefore, three-dimensional numerical analysis was performed in this study. Overall, real-time monitoring should be carried out to prevent railway accidents in advance when a deep excavation adjacent to urban railway structures is constructed.

A Study on Potential Risk of Landslide in Pusan (부산지역의 산사태 위험 연구)

  • Lee, Su-Gon
    • Journal of the Korean Society of Environmental Restoration Technology
    • /
    • v.2 no.2
    • /
    • pp.9-23
    • /
    • 1999
  • Pusan's reputation as the nation's most crowded city in terms of population density is attributable to its huge mountains which allow only small portion of residential area to its large population. Rapid increase of urban population on limited amount of land had naturally led its developments efforts to mountainous area giving rise to the concern of potential landslide. This study on urban Pusan and "Landslide Hazard Map" thereof is prepared in an attempt to avoid disasters created by landslide and also as a reference for city planners. The Map shows that the area covering 38% to 43% of urban Pusan has the potential for landslide. The study also shows that various civil works involving massive land excavation had been more direct cause of landslides in Pusan than such traditional factors as locations, ground slopes, rock types and topography of the area concerned.

  • PDF