• Title/Summary/Keyword: Progress Management System

Search Result 701, Processing Time 0.035 seconds

Development of Building Monitoring Techniques Using Augmented Reality (증강현실을 이용한 건물 모니터링 기법 개발)

  • Jeong, Seong-Su;Heo, Joon;Woo, Sun-Kyu
    • Korean Journal of Construction Engineering and Management
    • /
    • v.10 no.6
    • /
    • pp.3-12
    • /
    • 2009
  • In order to effectively distribute the resources, it is very critical to understand the status or progress of construction site quickly and accurately. Augmented Reality (AR) can provide this situation with information which is convenient and intuitive. Conventional implementation of AR in outdoor or construction site condition requires additional sensors or markers to track the position and direction of camera. This research is aimed to develop the technologies which can be utilized in gathering the information of constructing or constructed buildings and structures. The AR technique that does not require additional devices except for the camera was implemented to simplify the system and improve utility in inaccessible area. In order to do so, the position of camera's perspective center and direction of camera was estimated using exterior orientation techniques. And 3D drawing model of building was projected and overlapped using this information. The result shows that by using this technique, the virtual drawing image was registered on real image with few pixels of error. The technique and procedure introduced in this paper simplifies the hardware organization of AR system that makes it easier for the AR technology to be utilized with ease in construction site. Moreover, this technique will help the AR to be utilized even in inaccessible areas. In addition to this, it is expected that combining this technique and 4D CAD technology can provide the project manager with more intuitive and comprehensive information that simplifies the monitoring work of construction progress and planning.

A Study on Project Resource & Information Management with Internet Application(PRIMA system) (디지털 정보화를 통한 현장 자원 및 정보관리 기술에 관한 연구(PRIMA 시스템))

  • Kim Oe-Gon;Lee Dong-Ryul
    • Korean Journal of Construction Engineering and Management
    • /
    • v.2 no.1 s.5
    • /
    • pp.88-97
    • /
    • 2001
  • The Internet, the main issue of a new millennium, is being researched vitally for the progress of the construction industry, and the construction industry is considered to be led into a high-value added state-of-arts technology industry through CALS. Even if many construction companies gradually widen the use of the Internet for various purposes such as an electronic bidding system and an e-commerce system, the companies are still demanded to use the Internet more broadly and practically. Hence, the need for a tool for fast decision making and an effective construction management has risen. The PRIMA system has been developed specifically focused on meeting with those recent changes of the construction industry. This system is composed of three parts. Those are Just In Time(JIT) management, integrated application of man power${\cdot}$safety${\cdot}$work management and decision making process based on real-time information in the Internet. The usefulness of the PRIMA system has already been proved in a super-scale construction project. As the Internet environment get improved the use of the tool will be spread out gradually for many construction projects, regardless their size and location.

  • PDF

Development Measures for Korea's National Aviation Safety Management - Focused on Organizing and Handling Resources for Aviation Safety - (국가 항공안전관리체계 발전방안 - 항공안전 관련 자원의 조직·관리 중점 -)

  • Lee, Jang Ryong;Kim, Dae Ho
    • Journal of the Korean Society for Aviation and Aeronautics
    • /
    • v.26 no.2
    • /
    • pp.132-138
    • /
    • 2018
  • Aviation safety requires systematic national attention and management because aircraft accident produce greater undesired social impact, economical damage, and declining national credibility compare to other transportation accident. Specially, Republic of Korea has highly increased risk of air accident as a major air transportation point having small aerospace, connecting pacific ocean and Asia, and explosively increased air traffic produced by economical growth, operating numerous military aircraft for the South and North Koreas' confrontational situation. Also, greatly increased domestic and oversea air travels by Koreans and foreigners as well as air freight based on heightened Korea's national power, launching new low cost carriers, and popularized leasure aviation have produced large amount of aviation needs in various fields. However, national aviation safety management system gratifying increased aviation needs and aircraft operations is seem to be slow in progress. This paper will show optimized measures utilizing private, governmental, and military resources to prevent aircraft accident under circumstances of limited budget and an favorable conditions, then will propose several action items.

A Study on the Method of Implementation Assessment for Total Maximum Daily Load Management (수질오염총량관리를 위한 효율적 이행평가방안 연구)

  • Park, Jun-Dae;Park, Ju-Hyun;Rhew, Doug-Hee;Jeong, Dong-Hwan
    • Journal of Environmental Impact Assessment
    • /
    • v.17 no.2
    • /
    • pp.125-132
    • /
    • 2008
  • It is desirable that implementation assessment (IA) should be carried out efficiently in order to make successful progress of Total Maximum Daily Load (TMDL) in watershed management. There are many difficulties in the process of the implementation assessment because of the early stage in the application of TMDL in Korea. This study reviewed the present status of IA and proposed the methodology of its improvement such as flexible application of TMDL ledger, and standardization of assessment index and criteria. The deficient time for assessment period could be corrected by the consideration of the post-procedure after the submission of IA report.

A Study on Improving the Storm and Wind Damage Management System of Coastal Cities (연안도시 풍수해 관리체계 개선방안에 관한 연구)

  • Oh, Sang-Baeg;Lee, Han-Seok
    • Journal of Navigation and Port Research
    • /
    • v.43 no.3
    • /
    • pp.209-218
    • /
    • 2019
  • Coastal cities suffer a great deal of storm and wind damage. The storm and wind characteristics vary between cities. Therefore, a storm and wind damage management system suited for specific characteristics is required for each coastal city. In this study, we analyze the current situation and establish the problem of storm and wind damage management system in regards to urban management, coastal management and disaster management. We also review the storm and wind damage management system for the USA and Japan. We consequently propose a plan to improve the storm and wind damage management system. As a result of the study, in terms of city management, we recommend the compulsory identification of disaster prevention districts, implementation of the integrated coastal city management plan, designation of natural disaster risk mitigation area as disaster prevention district, the division of disaster prevention district into wind damage prevention district, storm damage prevention district, erosion damage prevention district, the building of restrictions at the disaster prevention district by ordinance, etc. In regards to coastal management, we suggest the delegation of authority to delegate coastal erosion management area to the local government, the subdivision of coastal erosion management area into erosion serious area, erosion progress area, erosion concern area, the building restrictions at coastal erosion management area by ordinance, development of erosion prediction chart, etc. In relation to disaster management, we recommend the integration of "countermeasures against natural disasters act" and "disasters and safety management basic act", the local government-led disaster prevention system, the local disaster management network, and the customized local disaster prevention plan, etc.

Construction Progress Management System for PPC Implementation (작업성취율 활용을 위한 공정관리체계)

  • Lim, Chul-Woo;Yu, Jung-Ho;Kim, Chang-Duk
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.3
    • /
    • pp.57-65
    • /
    • 2007
  • Last Planner System (LPS) developed by Lean Construction Institute consists of four steps: Master Schedule, Phase Schedule, Lookahead Planning and Weekly Work Plan. This paper focuses on the process of measuring Percent of Plan Completed (PPC) at the weekly Work Plan stage. PPC means the percentage of weekly assignments completed. According to the results of the researches that deal with PPC from many other countries, we can assure the benefits or using PPC. However the concept of PPC is unfamiliar in Korea construction industry. This paper analyzes the cases in which PPC is applied in other countries and compares them with the production control system in Korean construction industry. The results of this research will provide the time management system for using PPC in Korea.

A Practical 1 Page Contextual Diagram for Monitoring Multiple Projects: An Empirical Study of an IT Organization

  • Lee, Jung-Gyu;Jeong, Seung-Ryul
    • Journal of Internet Computing and Services
    • /
    • v.17 no.5
    • /
    • pp.121-129
    • /
    • 2016
  • Company A, an embedded system manufacturer, has been managing multiple development projects. Executives need to understand the risk level of every project and prioritize resource distribution. Traditional project monitoring tools or excel sheets are too complex for calculating the risk factors across a functional organization. Two new charts, "Spear-head Chart" and "Float Chart" were designed to assist high level decision making processes. Two charts were used for weekly executive meetings in order to monitor project progress and rectify project direction. One page graphical monitoring tools in Company A are good enough for high management decision making. Authors explain the characteristics of two charts and propose its practical implementation in real working environment. Spear-head chart was also implemented as a system.

건설 프로젝트 공정표 생성을 위한 사례기반 전문가시스템의 설계

  • 김현우;이경전;이재규
    • Proceedings of the Korean Operations and Management Science Society Conference
    • /
    • 1996.04a
    • /
    • pp.709-712
    • /
    • 1996
  • Generating a project network of a specific construction project is very time consuming and difficult task in the field. To effectiviely automate and support the planning process, we design a case-based project planning expert system inspired by the fact a human expert project planner uses previous cases for planning a new project. A construction project case consist of its specific characteristics and the corresponding project network (i.e. project plan). Using frame based representation. we represent the project features affecting the progress network and the entities composing the project plan such as the buildings, construction methods, WBS (work breakdown structure), activities, and resources. The project planning process runs through most similar case retrieval, case adaptation, and user requirement satisfaction. We represent the construction domain knowledge for each procedure using constraints and rules. We develop the methodology for constraint-based case adaption. Case adaptation process mainly consist of activity generation/deletion and predecence constraint satisfaction, for which we develop the dynamic constraint generation method and connect user-level requirement representation the system-level network modification knowledge. The methodology is being applied to the prototype for apartment construction project planning.

  • PDF

Development for Systems Engineering Framework Model of Next Generation High Speed Railway Train (차세대 고속전철 시스템 엔지니어링 체계 모델 개발)

  • 유일상;박영원
    • Journal of the Korean Society for Railway
    • /
    • v.4 no.4
    • /
    • pp.147-154
    • /
    • 2001
  • A high-speed rail system represents a typical example of large-scale multi-disciplinary systems, consisting of subsystems such as train, electrical hardware, electronics, control, information, communication, civil technology etc. The Systems Engineering, as a methodology for engineering and management of today's ever-growing complex system, must be applied to development of such systems. This paper presents systems engineering framework model to have to be applied to the systems engineering technology development task for the korean next-generation high-speed railway systems in progress and demonstrates data models and schema for computer-aided systems engineering software, RDD-100, for use in its development and management.

  • PDF

Using the MCDM of the Innovative Product Value Chain to Promote New Product Design

  • Liao, Shih-Chung
    • Asian Journal of Business Environment
    • /
    • v.4 no.3
    • /
    • pp.27-37
    • /
    • 2014
  • Purpose - In the past, designs for traditional products have usually focused on historic techniques. However, this tradition of using historic techniques has now been replaced by the trend of using the innovative design concept. Research design, data, and methodology - To measure future market trends and quality requirements, we apply the results of the questionnaires and analyze them with various experimental processes and a design methodology. In this way, we gauge the impact of the innovative product value chain on the promotion of new products. Results - Accompanied with an innovative product value chain, the product can stimulate the development of enterprise management, which has become the main issue in social and economic development in every developed country, and can facilitate the progress of enterprise management throughout the enterprise. Conclusions - Customer demand should be emphasized as the primary means to solve design problems, to design optimal solutions, to create differentiation with competitors, and to pursue optimal marketing strategies.