Modeling and Simulation for Dynamic Behaviors of SOVR for Electric Power Plant (P&S를 활용한 발전용 SOVR의 모델링과 동특성 해석)

  • 노태정
    • 제어로봇시스템학회:학술대회논문집
    • /
    • 2000.10a
    • /
    • pp.203-203
    • /
    • 2000
  • The P&S(Power Plant Simulation System) is a powerful simulation software system for the dynamic behavior of power plants. The P&S module libraries provide plant models with higher flexibility of dynamic simulations for process and control designs. The P&S software was effectively available for PCS based on Linux and modem workstations based on Unix. The P&S was applied for simulating the dynamic behaviors of the SOVR(Supercritical Once-Through Variable Pressure Reheater) according to the operations such as stan-up, shutdown, load following, load change and trip in order to obtain an optimal operation procedure for Unit 5/6 of Taeahn fossil power plant consisted of SOVRs and steam turbines.

  • PDF

A Study on the Availability Evaluation with Failure Density Function of Equipment of Small-scale Plant (소규모 플랜트 기자재의 고장밀도함수가 가용도에 미치는 영향 평가)

  • Lee, Hongcheol;Hwang, Inju
    • The KSFM Journal of Fluid Machinery
    • /
    • v.19 no.3
    • /
    • pp.33-36
    • /
    • 2016
  • The investigation on the verification of availability simulation for small-scale plant has been carried out. This study focuses on the availability variation induced by number of equipment and iteration with failure density function. The equipment classification of small-scale plant and failure type and the methodologies on Monte-Carlo simulation are established. The availability deviation with programs showed under Max. 1.7% for the case of normal function. This method could be used to availability evaluation of small-scale plant, but calibration of the failure density function is necessary for general application.

Lessons Learned from an Implementation of Plant Monitoring System for Simulation (발전소 감시계통의 Virtual Simulation시 권고사항)

  • Seo In-Yong;Hwang Do-Hyun;Lee Yong-Hwan;Han Hwan-Ho
    • Proceedings of the Korea Society for Simulation Conference
    • /
    • 2005.11a
    • /
    • pp.102-107
    • /
    • 2005
  • PMS(Plant Monitoring System) for simulation is the program for training that users such as instructor, operator, and supervisor can operate the plant virtually. Presented in this paper, are some lessons learned from implementation of PMS for simulation. First, this PMS fer simulation is based on LINUX instead of UNIX. These two OS(Operating System) have different platform and compiler version on it, so debugging needs to be done about variable defining part. Second, In LINUX system, the size of shared memory and message queue is already designated as a default value that user has to set up and use the RTAP DB. Third, to decrease the dummy data size, it has to be changed into binary formation. Lastly, PMS software for simulation provides several environments according to the command, so considered should be status monitoring, alarm, system organization, point and group monitoring, history storage and searching function.

  • PDF

System architecture and simulation strategy for dynamic process simulation (화학공정 동적모사기 개발에 있어서 시스템구조 및 전략)

  • 이강주;한경택;윤인섭
    • 제어로봇시스템학회:학술대회논문집
    • /
    • 1992.10a
    • /
    • pp.315-320
    • /
    • 1992
  • This paper presents the simulation architecture and strategy for dynamic simulation of chemical process and describes key features of developed dynamic simulation system, MOSA(Multi-Objective Simulation Architecture). A plant structure may be partioned into several strong coupling units, called cluster. If this cluster is solved simultaneously, it is possible to simulate whole plant without introducing convergence problem of tear streams. In this study, a flexible modular approach based on clusters was proposed as a promising architecture for dynamic chemical process simulator.

  • PDF

A Method for Generating a Plant Model Based on Log Data for Control Level Simulation (제어시뮬레이션을 위한 생산시스템 로그데이터 기반 플랜트 모델 생성 방법)

  • Ko, Minsuk;Cheon, Sang Uk;Park, Sang Chul
    • Korean Journal of Computational Design and Engineering
    • /
    • v.18 no.1
    • /
    • pp.21-27
    • /
    • 2013
  • Presented in the paper is a log data based modeling method for effective construction of a virtual plant model which can be used for the virtual PLC (Programmable Logic Controller) simulation. For the PLC simulation, the corresponding virtual plant, consisting of virtual devices, is required to interact with the input and output symbols of a PLC. In other words, the behavior of a virtual device should be the same as that of the real device. Conventionally, the DEVS (Discrete Event Systems Specifications) formalism has been used to represent the behavior a virtual device. The modeling using DEVS formalism, however, requires in-depth knowledge in the simulation area, as well as the significant amount of time and efforts. One of the key ideas of the proposed method is to generate a plant model based on the log data obtained from the production system. The proposed method is very intuitive, and it can be used to generate the full behavior model of a virtual device. The proposed approach was applied to an AGV (Automated Guided Vehicle).

A Full Scale Fossil Power Plant Simulator For Hadong (하동 화력 발전소 전범위 시뮬레이터 개발)

  • 김성호;김종현;조창호
    • 제어로봇시스템학회:학술대회논문집
    • /
    • 2000.10a
    • /
    • pp.204-204
    • /
    • 2000
  • This paper describes the development of training simulator for Hadong fossil Power Plant. The simulator was developed to train operator, test new control Logic and evaluate alternative operating procedure for expert engineer of control system. The most control logics such as Siemens TELEPERM ME and GE Mark V are translated directly from microprocessors. Those HMI are also directly emulated. The simulation was performed by ProTRAX modeling software. The paper discusses the configuration of simulator and the simulation results of 30%, 50%, 75% and 100% normal rate load test.

  • PDF

Development of Nuclear Power Plant Simulator using Shared Memory Variables (공유메모리 변수를 사용한 원자력발전소 시뮬레이터 개발)

  • 박근옥;서용석
    • Proceedings of the Korea Society for Simulation Conference
    • /
    • 2001.05a
    • /
    • pp.153-156
    • /
    • 2001
  • We have developed CNS(Compact Nuclear Simulator) which can be used for the fundamental training of the nuclear power plant operators. The application software for CNS consists of simulation engine(analyzer code), instructor station software, and man-machine interface software. Each application software is regarded as one black box and the communication of black boxes is performed by the predefined shared memory variables. In this paper, we discuss our experience for CNS development.

  • PDF

Fault Simulation and Analysis of Generator (발전기의 사고 시뮬레이션과 분석)

  • Park, Chul-Won;Oh, Yong-Taek
    • The Transactions of the Korean Institute of Electrical Engineers P
    • /
    • v.62 no.3
    • /
    • pp.151-158
    • /
    • 2013
  • Large generator of power plant is very important. In order to protect large generator from faults, digital protective relay or IED is required. However, all protective relays for generators of the domestic power plant are operated by foreign products. And now, for technological independence from foreign and improvement of import substitution effect, IEDs using domestic technology are being developed. To evaluate performance of developing next-generation power devices, the study of the dynamic characteristics of the power plant, generator system modeling, fault simulation and analysis, should be considered. Specially, To obtain IEEE Standards COMTRADE format for relay operation test, generator system modeling and fault simulation using PSCAD/EMTDC tools must be preceded. Until now, a complete modeling of generator internal windings and fault simulation techniques dose not exist. In this paper, for evaluation performance of relay elements of developing IED, the generator system modeling and various faults simulation using PSCAD/EMTDC tools were performed. And then, the various transient phenomena through obtained relaying signal of developed modeling were analyzed.

Dynamic Simulation of Heat Recovery Steam Generator (폐열회수 보일러의 동특성 시뮬레이션)

  • Lee, Ki-Hyun;Lee, Dong-Su;Cho, Chang-Ho
    • Proceedings of the KSME Conference
    • /
    • 2001.11b
    • /
    • pp.847-852
    • /
    • 2001
  • A thorough understanding of the transient behavior during load following and start-up is essential in the design and operation of an heat recovery steam generator(HRSG). During this period of time, material that is exposed to high temperature and experiences a large temperature variation is subject to high thermal stress. APESS(Advanced Plant Engineering & Simulation System) is a dynamic simulation software for power plant which is under being developed by Doosan Heavy Industries & Construction Co., Ltd. This paper present the introduction of APESS and the result of simulation for an heat recovery steam generator.

  • PDF

The Simulation of Boiler System for HADONG Fossil Power Plant

  • Choi, Jin-Ho;Ma, Sam-Sun;Lee,Yong-Kwan
    • Proceedings of the Korea Society for Simulation Conference
    • /
    • 1999.10a
    • /
    • pp.56-61
    • /
    • 1999
  • The Simulation of Boiler System for Hadong Fossil power plant has been made by Korea Electric Power Research Institute (KERRI) in an attempt to develop Windown NT based full scope replica simulator for Hadong Fossil power plant, 500MWe once-through boiler. In the project KERRI developed Once Through, Super Critical type Boiler System, the core part of the Simulation and integrated the system with other process systems such as BOP System, and AUX System. This paper is to introduce the basic concept of the simulation for the Boiler System. It will also introduce PRO-TRAX System, for used as a modeling tool.