Comparative Analysis of Conventional Tact and Compositive Tact in Apartment House Finishing Construction (공동주택 마감공사의 기존 Tact와 복합병행 Tact 비교분석 - 공동주택 미장공사 중심으로 -)

  • Hwang, SuHyeon;Sim, JeaHyung;Ham, NamHyuk;Kim, JaeJun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.23 no.4
    • /
    • pp.47-56
    • /
    • 2022
  • In a construction project, process planning is an important factor in determining the success or failure of a project. In particular, it is necessary to systematically establish a process plan in the early stage because the finishing work of an apartment house involves more interference than the foundation work or the frame work. First, in this study the problems of Tact process management were identified, Based on the data from the case project, conventional Tact process management and compositive Tact process management were compared and analyzed. Second, cost analysis was performed on applicable plastering work to suggest the necessity and direction of compositive Tact process management. Third, the appropriateness of manpower according to the number of construction households is analyzed through cost analysis. Through this, the validity and effectiveness of compositive Tact process management were verified based on the results derived from this study.

IMPROVEMENT OF TACT SCHEDULE MANAGEMENT PROCESS FOR THE FINISH WORK OF APARTMENT HOUSES

  • Joo-Young Jung;Sang-Ho Yoon;Kyung-Kook Lee;Chang-Gyo Kim;Jae-Youl Chun
    • International conference on construction engineering and project management
    • /
    • 2007.03a
    • /
    • pp.554-562
    • /
    • 2007
  • This study determined tact process paths by separating the finish works according to the properties of work areas and work relations in order to apply the tact schedule management to the finish works. In addition, by suggesting preparing and sharing the workflow charts, the experiments can be shared between the executors and any possible frictions between the specialist works can be identified in advance. In addition, any errors on the plan can be reviewed and modified through the measurement stage of tact plan attainment rate. The process of tact schedule management is improved with such tools and methods and the efficiency of the process through the application of cases was verified.

  • PDF

Reengineering of TACT Process Management Analyzed on Task Information (업무정보 분석을 통한 TACT공정관리 프로세스 재설계)

  • Kim, Ok-Kyue;Park, Jun-Mo;Kim, Beop-Su
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.5
    • /
    • pp.113-124
    • /
    • 2012
  • TACT process reengineering is applied to the finish work of apartment buildings and extra tall buildings to conduct efficient process control in Korea. Non-systemized information on the performances, however, causes difficulties in building a database for such records and it takes long time to find the relevant information. In order to solve such problems, scientific and quantitative understanding on the construction information and data is required to perform TACT process reengineering satisfactorily and also proper management plan should be provided for the working level staff to understand the required information and data more easily. In this regard, this paper reorganizes the TACT process reengineering based on the general process control and classifies the items of required information to redesign. Redesigned process was verified by specialists making use of work-information matrix. As a result, paper contributed to increasing comprehension level of the working level people and when the persons in charge are transferred to other duty, it makes them understand all the working procedure faster, which enables the departments involved to carry out their cooperation and adjustment more efficiently.

TACT Scheduling & Monitoring of Apartment Finish Works based on the BDM Technique (BDM기법을 적용한 공동주택 마감공사 TACT공정계획 수립 및 운영)

  • Kim, Seon-Gyoo;Yoo, Jae-Woo;Kim, Dong-Sub;Park, Jong-Il
    • Korean Journal of Construction Engineering and Management
    • /
    • v.15 no.2
    • /
    • pp.3-11
    • /
    • 2014
  • As the recent construction projects have been carried out as a mixed-use complex project that includes architecture, civil, mechanical, electrical, and landscape, as well as become bigger and high-rise with the increased repetitive works, the TACT technique has received more attention as an effective method for achieving a target completion date by securing the continuous works. Although the TACT technique can maintain a steady flow without the interruption of works in order to utilize the resources of the repetitive works, it can not be considered as the systematic scheduling technique because the schedule computations are not possible as well as a critical path can not be recognized. This paper proposes the applicabilities of scheduling and monitoring the TACT schedule by the BDM technique as comparing and analyzing the methodologies for apartment finish works by the Excel, the Primavera(P6) based on the PDM technique, and the Beeliner based on the BDM technique that is a new networking technique, respectively.

The Influence of Personality Traits on Airline Untact Check-in: Focusing on Mobile Check-in User

  • YANG, Jae-Pil;PARK, Sang-Beom
    • The Journal of Industrial Distribution & Business
    • /
    • v.12 no.1
    • /
    • pp.15-30
    • /
    • 2021
  • Purpose: Year of 2020, COVID-19 has been changing the people's everyday life to ways never been thought of before all over the world. The IT and electronic industry, the methods of supplying goods and services have been changed from contact to un-tact environments based on un-tact systems very rapidly. COVID-19 has been striking the tourism and the travel industry, especially the airline and hotel industry of which services are provided by human. For the passenger service of airliner, automation has been propelled and un-tact style of service has become mainstreams except cabin service since 2000's. For passenger transportation, due to traffic regulations and exclusions etc., switching to new ways is not easy. However, under the new environment made by COVID-19, kiosk check-in, web check-in and mobile check-in has become more important. In this study, the characteristics of airline customers using mobile goods are investigated to find ways to raise the rate of utilizing mobile check-in and to increase the efficiency of boarding process. Research design, data, and methodology: Considering the COVID-19 environment, survey was done by online research company. The research model is designed to integrate the user characteristics and usage/purchase motive and technology acceptance theory. Especially considering infectious diseases prevention, concern of safety is adopted as one of the usage motive variable. Results: Extraversion or conscientiousness characteristics prefers counter check-in(contact service), while openness characteristics prefers mobile check-in(un-tact service). Concern of safety for infectious disease shows strong non-preference on counter check-in. Conclusions: Regarding service type regardless of type of the industry, automation and un-tact have been mainstreams due to high costs of labor, efficiency and standardization issue, etc., and COVID-19 has given impetus to them. For airliner, un-tact service including boarding process service has been more and more important. To raise the rate of un-tact service use, the characteristics of the user should be analyzed first. The study results indicate that for extraversion or conscientiousness, some kinds of methods to induce them to use un-tact service more are needed.

The application of tact time at finish work for building construction - Focused on Office Building - (건축마감공사에서의 택트타임 설정을 통한 작업조정 프로세스 개발 - 오피스 건축물을 중심으로-)

  • Yoon, You-Sang;Suh, Sang-Wook
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.6 s.28
    • /
    • pp.90-97
    • /
    • 2005
  • Poor usage of work-continuity for planning and management is one of the leading causes of decreased productivity in high-rise and complexity construction projects. For efficient finish work, tact scheduling method needs to be implemented according to tact time. But there are the studies about zoning of work area, daily construction information and tact planning and management, there are not the studies about tact time yet. The purpose of this study is to help implementation of tact scheduling by tact time and adjusted work-plan. The main contents of this study are as follow; (1)Tact time has been calculated as coordination of work-plan between a general contractor and specialties. (2)Project-plan can be without delay by tact time calculation method.

A Study on "On-tact" Christian Education in the Post-Corona Era (포스트 코로나 시대의 "온택트(ontack)" 기독교교육에 관한 연구)

  • Yang, Kum Hee
    • Journal of Christian Education in Korea
    • /
    • v.68
    • /
    • pp.41-76
    • /
    • 2021
  • This paper begins with the question of whether "on-tact" Christian education, which has become the most new-normal phenomenon since Corona 19, will remain as a decisive form of Christian education even in the post-Corona era. In order to answer that question, this study explored whether on-tact Christian education has its own domain of experience and educational elements that cannot be replaced by face-to-face education, specifically focusing on "types of on-tact Christian Education", "discussion of digital church" and "digital epistemology". Through research on "types of onn-tact Christian education," it confirmed that, when viewed on the basis of 'participation' or 'communication', on-tact Christian education has an independent field of experience and educational elements. Through contemplation on "digital ecclesiology", it found that on-tact education is the decisive channel for Christian education to reach digital generation. It also found a new metaphor from the "network" concept for the public church and the Kingdom of God. This paper also found that we experience the perception of the body that is expanded through the combination between the body and technology in the digital world, and that this is a unique epistemology that occurs only in the digital world. Based on the above points, it affirmed that on-tact Christian education is not simply a means of supplementing face-to-face education in the era of COVID-19, but is a Christian education that has an independent field of experience and educational power that face-to-face education cannot replace. Thus it foresees that on-tact Christian education will continue to expand as a center and form of Christian education even in the post-corona era.

An Enhanced TACT Technique for Finish Work of High-rise Residential Buildings

  • Kim, Sun-Kuk;Son, Ki-Young;Joo, Jin-Kyu;Lee, Dong-Hoon;Lee, Sung-Ho
    • Journal of the Korea Institute of Building Construction
    • /
    • v.11 no.4
    • /
    • pp.396-406
    • /
    • 2011
  • Execution of the finish work for high-rise residential construction occurs when a mixture of work progresses simultaneously at each floor or sector and is carried on by highly-specialized subcontractor teams. Therefore, the finish work plan requires an effective scheduling method that interfaces between the work and the teams. In order to address these issues, the TACT technique is utilized in Korea. This technique is based on Line-of-Balance and Lean construction. However, according to recent case studies, finish work using TACT technique was frequently delayed with cost overruns because the work was performed without a detailed schedule control plan outlining the relationship between architecture and mechanical, electrical, and plumbing work. This paper describes the enhanced-TACT technique which provides a detailed work flow chart and TACT work template. With improved TACT technique, this paper will contribute to improved cash flow and reduced cycle time and provide quality improvement through work continuity.

TACT Productivity Management for Finish Works of Residential Buildings using Productivity Achievement Ratio (PAR) (공동주택 마감공사 TACT 기법 생산성 관리 - Productivity Achievement Ratio를 활용한 생산성 관리 -)

  • Joo, Seonu;Park, Moonseo;Lee, Hyun-Soo;Lee, Kwang-Pyo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.3
    • /
    • pp.36-48
    • /
    • 2015
  • To complete various types of finish works with higher quality in much less time, TACT, which was mostly used for high-rise buildings, has been adapted to meet the needs for systematic schedule management in construction sites. However, the effectiveness of adapting TACT has not been shown as expected due to the different perspectives on productivity from both general contractor and subcontractors based on unforeseen conditions according to the types of site. Furthermore, not enough theoretical backgrounds, empirical data, and systematic approaches to solve the fundamental problems caused by each participants' different views on productivity has produced obstacles for establishing effective solutions. Therefore, this research aims to analyze the possible main reasons for having different point of views regarding productivity among various participants of residential building sites using TACT based on literature review, site survey, and interviews. Also, case study was conducted to propose obtainable productivity (OP) regression equation and productivity achievement ratio (PAR) with reduction factors (RFs) and actual productivity (AP) data from an actual construction site. The proposed outcome may assist general contractors converting output management with PPC to productivity management with actual data using PAR. On the other hand, subcontractors would be able to estimate theory-based maximum productivity of construction sites with TACT by using OP. The PAR will enhance the communication between general and sub-contractors for their decision making process. Finally, the main RFs derived from PAR could be used as essential keys for productivity management to increase the economical and operational effectiveness of the construction project.

Development of Optimal TACT Process for Eco-Friendly Demolition Works in Aged Housing Remodeling - Focus on Case Study - (친환경 리모델링 철거공사의 최적 TACT공정 개발 - 사례연구를 중심으로 -)

  • Woo, Joong-Pyung;Kim, Ki-Hyun;Hwang, Young-Gyu;Kim, Kyung-Rai;Cha, Hee-Sung
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.1
    • /
    • pp.3-12
    • /
    • 2011
  • Technology based civilization has made a sustained advancement, resulting in economic growth and material prosperity. The outcome was the beginning of environmental destruction. Especially, in regard to construction, it has been recognized as a key culprit for pollution. As such, the construction industry has recently shown interest in the environment, as it has been applying environment friendly method of construction and reducing wastes. As the number of old common housing increases in our country, reconstruction and remodeling are implemented as a means of improvement. However, it can be said that remodeling is the inevitable option because of cost and environmental problems associated with reconstruction. As part of its feature, remodeling work is preceded by removal work. And, removal work inevitably creates construction wastes. Treatment of wastes that takes into consideration environmental aspects is important and for this, removal work that is based on environment friendly remodeling to ensure selective separation must be implemented. Yet, a removal work based on environment friendly remodeling has a lower level of output compared to existing methods. Because remodeling work by its nature has a post construction work which proceeds after it, securing work efficiency is important as the removal work is a critical path activity. Thus, the present study improves the work process of a removal work that is based on environment friendly remodeling so that it becomes a work process that includes work efficiency. For this, as a case study, old common housing has been selected, and a TACT process has been developed which is based on data acquired from environment friendly removal work. And, this study develops an optimal TACT process which is based on environment friendly remodeling by conducting a simulation for a 15 floor apartment.