Rock Mechanics-Major Projects and Research Topics in Korea (암반공학-우리나라에서의 과제와 연구주제)

  • Chung, So-Keul
    • Economic and Environmental Geology
    • /
    • v.39 no.4 s.179
    • /
    • pp.451-471
    • /
    • 2006
  • Major projects and research topics in the field of rock mechanics are analyzed to obtain the following results: $\cdot$ Rock mechanics deals with the behavior of deformation, failure and displacement of the rock and rock mass on the basis of geological basics. Discontinuities in the rock mass are the most important parameters to control the behavior of rock mass around underground openings. $\cdot$ The objective of site investigation and testing is to determine the strength properties of the rock mass and the in situ stress regime. Specimens for laboratory and in situ tests are to be selected in order that the results of the tests give the representative properties oi the rock mass of the site in question. $\cdot$ The result of a numerical model would be better evaluated not quantitatively but qualitatively. The displacement behavior of the rock mass has to be monitored properly for the NATM (New Austrian Tunneling Method) principles. $\cdot$ The stability of rock slope is to be evaluated preferably by back analysis with strength parameters, such as cohesion and friction angle.

Numerical simulation for surface settlement considering face vibration of TBM tunnelling in mixed-face condition (복합지반에서 TBM 굴진 진동을 고려한 지표침하에 대한 수치모델링)

  • Kwak, Chang-Won;Park, Inn-Joon
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.3
    • /
    • pp.333-339
    • /
    • 2015
  • In this paper, the surface settlement resulted from the shallow TBM tunnelling has been numerically simulated. TBM tunnelling is especially used in urban area to avoid serious vibration and noise caused by explosion in NATM. Surface settlement is one of the most important problems encountered in all tunnelling and critical in urban areas. In this study, face vibration of TBM excavation is considered to estimate surface settlement trend according to TBM extrusion. The dynamic excavation forces are calculated by total torque on the TBM cutterhead in mixed-face of soil and weathered rock condition with shallow depth. A 3-dimensional FDM code is employed to simulate TBM tunnelling and mechanical-dynamic coupling analysis is performed. The 3D numerical analysis results showed that dynamic settlement histories and trend of surface settlement successfully. The maximum settlement occurred at the excavation point located at 2.5D behind the face, and the effect of face vibration on the surface settlement was verified in this study.

Suggestion of a Design Method for UAM (강관 다단 그라우팅 공법(UAM)의 설계법 제안)

  • 박이근;임종철
    • Journal of the Korean Geotechnical Society
    • /
    • v.20 no.3
    • /
    • pp.97-106
    • /
    • 2004
  • In case of tunnel construction with a shallow soil cover in cohesionless soils or highly weathered rocks, reinforcement measures are required for a tunnel stability during the tunnel construction. Recent developments show that the use of Umbrella Arch Method(UAM) as tunnel reinforcement and water cut-off in domestic projects has increased. Unfortunately, guidelines for the design and construction of UAM have not been established, only empirical designs and applications in tunnel construction have been performed so far. In this study, behaviour of the steel pipes installed on the tunnel roof was analyzed through the monitoring of bending and axial stresses of the pipes with the advance of the tunnel face. The monitoring results were used in the establishment of the loading mechanism around the pipe. This paper suggests, the guidelines used in the determination of the total length, overlapping length and lateral spacing of the reinforcing pipes obtained from the established loading mechanism.

Numerical Analysis of Tunnel Lining under Loosening Load (수치해석을 통한 이완하중에 따른 터널 라이닝의 거동 분석)

  • Park, Jung-Jin;Kim, Yong-Min;Hwang, Taik-Jean;Jeong, Sang-Seom
    • Journal of the Korean Geotechnical Society
    • /
    • v.27 no.7
    • /
    • pp.35-45
    • /
    • 2011
  • Cost effective design and construction are necessary to establish the design concept of tunnel lining. Loosening load acting on the concrete lining is compared with Terzaghi tunnel theory and numerical analysis. It is analyzed under the condition of weathered rock and soil with varying in-situ stress ratio ($K_0$). Based on the result, loosening load calculated by Tcrzaghi tunnel theory is much greater than numerical analysis results. And the load calculated in weathered soil is lager than weathered rock condition. As in-situ stress ratio increases, the stress acting on the tunnel lining decreases in Terzaghi theory rapidly, whereas there is little effect in numerical analysis.

Study on the structure of the articulation jack and skin plate of the sharp curve section shield TBM in numerical analysis (수치해석을 통한 급곡선 구간 Shield TBM의 중절잭 및 스킨플레이트 구조에 관한 연구)

  • Kang, Sin-Hyun;Kim, Dong-Ho;Kim, Hun-Tae;Song, Seung-Woo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.19 no.3
    • /
    • pp.421-435
    • /
    • 2017
  • Recently, due to the saturation of ground structures and the overpopulation of pipeline facilities requires to development of underground structures as an alternative to ground structures. Thus, mechanized tunnel construction of the shield TBM method has been increasing in order to prevent vibration and noise problems in construction of the NATM tunnel for the urban infrastructure construction. Tunnel construction plan for the tunnel line should be formed in a sharp curve to avoid building foundation and underground structures and it is inevitable to develop a shield TBM technology that suits the sharp curve tunnel construction. Therefore, this study is about the structural stability technology of the articulation jack, shield jack and skin plate for the shield TBM thrust in case of the mechanized tunnel construction that is a straight and sharp curve line. The construction case study and shield TBM operation principle are examined and analyzed by the theoretical approach. The torque of the cutter head, the thrust of the articulation jack and the shield jack, the amount of over cutting for curve is important respectively in shield TBM construction of straight and sharp curve line. In addition, it is very important to secure the stability of the skin plate structure to ensure the safety of the inside worker. This study examines the general structure and construction of the equipment, experimental simulation was carried out through numerical analysis to examine the main factors and structural stability of the skin plate structure. The structural stability of the skin plate was evaluated and optimizes the shape by comparing the loads of the articulation jack by selecting the virtual soil to be applied in a straight and sharp curve line construction. Since the present structure and operation method of the shield TBM type in domestic constructions are very similar, this study will help to develop the localized shield TBM technology for the new equipment and the vulnerability and stability review.

Evaluation of bonding state of tunnel shotcrete using impact-echo method - numerical analysis (충격 반향 기법을 이용한 숏크리트 배면 접착 상태 평가에 관한 수치해석적 연구)

  • Song, Ki-Il;Cho, Gye-Chun;Chang, Seok-Bue
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.10 no.2
    • /
    • pp.105-118
    • /
    • 2008
  • Shotcrete is one of the main support materials in tunnelling. Its bonding state on excavated rock surfaces controls the safety of the tunnel: De-bonding of shotcrete from an excavated surface decreases the safety of the tunnel. Meanwhile, the bonding state of shotcrete is affected by blasting during excavation at tunnel face as well as bench cut. Generally, the bonding state of shotcrete can be classified as void, de-bonded, or fully bonded. In this study, the state of the back-surface of shotcrete is investigated using impact-echo (IE) techniques. Numerical simulation of IE technique is performed with ABAQUS. Signals obtained from the IE simulations were analyzed at time, frequency, and time-frequency domains, respectively. Using an integrated active signal processing technique coupled with a Short-Time Fourier Transform (STFT) analysis, the bonding state of the shotcrete can be evaluated accurately. As the bonding state worsens, the amplitude of the first peak past the maximum amplitude in the time domain waveform and the maximum energy of the autospectral density are increasing. The resonance frequency becomes detectable and calculable and the contour in time-frequency domain has a long tail parallel to the time axis. Signal characteristics with respect to ground condition were obtained in case of fully bonded condition. As the ground condition worsens, the length of a long tail parallel to the time axis is lengthened and the contour is located in low frequency range under 10 kHz.

  • PDF

A Study on the Evaluation of Environmental Load Based on LCA Using BIM - Focused on the Case of NATM Tunnel - (BIM을 활용한 LCA기반 환경부하평가에 관한 연구 - NATM 터널 사례 중심으로 -)

  • Lee, Yang-Kyoo;Han, Jung-Geun;Kwon, Suk-Hyun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.38 no.3
    • /
    • pp.477-485
    • /
    • 2018
  • To control manage environmental load during construction work, it is required to ascertain an accurate quantity for materials those are using during the construction. In construction industrial nowadays, especially on design part, there are lots of mistakes occurred on quantity take-off between plan documents and actual work. That mistakes are caused by omission of design items, overcount because of interference each materials or simple calculate error. Besides, in case of a construction project, engineers are impossible to design perfectly due to a lot of invalid variable in a construction site. Thus, design errors and changes occur frequently in the process of construction work or design due to such unclear elements. And in case of LCA assessment based on 2D design, there is difficult for an engineer who is in charge to calculate the volume of materials manually using drawings and relevant specifications. This study is aimed for examining and verifying a high reliable method of evaluating environmental load which is useful in construction process through comparing LCA analysis. In addition, this study provides the method of calculating the volume of materials and LCA assessment in working on the basis of 2D design, using the specifications which is used for LCA evaluation, and possibility of utilizing the LCA assessment by introducing BIM design technic to improve the former problem through comparing and analyzing the previous method with 3D-based evaluation process.

Effect of Steel-fiber Distribution on Flexural Strength and Toughness of Shotcrete-mimicked Concrete Specimen (숏크리트 모사 콘크리트 공시체에 혼합된 강섬유의 분산도가 휨강도 및 인성에 미치는 영향)

  • Park, Sung-Sik;Kim, Sang-Jung
    • Journal of the Korean Geotechnical Society
    • /
    • v.29 no.6
    • /
    • pp.53-62
    • /
    • 2013
  • A 5-20 cm thick shocrete has been routinely constructed for NATM tunneling method to stabilize and confine the excavated rock of tunnel construction site. A $40kg/m^3$ of steel fibers are usually mixed into such shotcrete but these steel fibers may not be evenly distributed depending on shotcrete machines, mixing ratios and excavated rock conditions. In this study, square column shotcrete-mimicked concrete specimens of $15cm{\times}15cm{\times}55cm$ were prepared with 5 equal layers and 5 or 20% cement ratio. The specimens were prepared with different reinforced-patterns: non-reinforced, middle layer-reinforced, 1, 3, and 5 layers-reinforced, or all layers reinforced. The specimens were air-cured for 7 days and tested for flexural strength. The influence of steel-fiber distribution on flexural strength and toughness of shotcrete-mimicked concrete specimens was investigated. In the case of a specimen with cement ratio of 20%, a flexural strength increased as a number of fiber-reinforced layer increased. The flexural strength of one-layer reinforced specimen showed 20% less than that of evenly fiber-distributed specimen. On the other hand, a specimen with cement ratio of 5% decreased as the number of fiber-reinforced layers increased. A toughness index increased as the number of fiber-reinforced layers increased, regardless of cement ratios. The toughness index of evenly fiber-distributed specimen showed 2-3 times as large as that of one-layer reinforced specimen.

Analysis of Errors in Tunnel Quantity Estimation with 3D-BIM Compared with Routine Method Based 2D (2D기반 기존방법 대비 BIM기반 터널 물량산출 오차 분석)

  • Shin, Jae-Choul;Baek, Yeong-In;Park, Won-Tae
    • Journal of the Korean Geotechnical Society
    • /
    • v.27 no.8
    • /
    • pp.63-71
    • /
    • 2011
  • In case of applying BIM method to the civil engineering of irregularly shaped structure, BIM method is recognized to have relatively high construction productivity. In this paper, we developed quantity calculation algorithms applying BIM method to NATM tunnel construction method and implemented BIM based 3D-BIM Modeling Quantity Calculation. The results showed that BIM-based method has high reliabilty in structure work in which errors occurred only in the range between 0.00% and -1.45%. On the other hand, BIM method applied to earth work showed great error range of -19.78% to 35.30%. So the benefit and applicability of BIM method in civil engineering were confirmed. In addition, routine method for the quantity of earth work has negligible error as in the case of structure work. But, rock type's quantity calculation showed significant errors so that the reliability of 2D-based volume calculation is problematic. It may thus be concluded that 3D-BIM is more reliable than the routine method in estimating the quantity of earth work. Considering the reliability and merits in the stage of its design, construction and maintenance levels, the application of BIM to civil engineering works is recommended.

A fundamental study on the automation of tunnel blasting design using a machine learning model (머신러닝을 이용한 터널발파설계 자동화를 위한 기초연구)

  • Kim, Yangkyun;Lee, Je-Kyum;Lee, Sean Seungwon
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.24 no.5
    • /
    • pp.431-449
    • /
    • 2022
  • As many tunnels generally have been constructed, various experiences and techniques have been accumulated for tunnel design as well as tunnel construction. Hence, there are not a few cases that, for some usual tunnel design works, it is sufficient to perform the design by only modifying or supplementing previous similar design cases unless a tunnel has a unique structure or in geological conditions. In particular, for a tunnel blast design, it is reasonable to refer to previous similar design cases because the blast design in the stage of design is a preliminary design, considering that it is general to perform additional blast design through test blasts prior to the start of tunnel excavation. Meanwhile, entering the industry 4.0 era, artificial intelligence (AI) of which availability is surging across whole industry sector is broadly utilized to tunnel and blasting. For a drill and blast tunnel, AI is mainly applied for the estimation of blast vibration and rock mass classification, etc. however, there are few cases where it is applied to blast pattern design. Thus, this study attempts to automate tunnel blast design by means of machine learning, a branch of artificial intelligence. For this, the data related to a blast design was collected from 25 tunnel design reports for learning as well as 2 additional reports for the test, and from which 4 design parameters, i.e., rock mass class, road type and cross sectional area of upper section as well as bench section as input data as well as16 design elements, i.e., blast cut type, specific charge, the number of drill holes, and spacing and burden for each blast hole group, etc. as output. Based on this design data, three machine learning models, i.e., XGBoost, ANN, SVM, were tested and XGBoost was chosen as the best model and the results show a generally similar trend to an actual design when assumed design parameters were input. It is not enough yet to perform the whole blast design using the results from this study, however, it is planned that additional studies will be carried out to make it possible to put it to practical use after collecting more sufficient blast design data and supplementing detailed machine learning processes.