• Title/Summary/Keyword: KEPCO System

Search Result 1,667, Processing Time 0.032 seconds

The Gasifier Operation Method using Bio Gas (바이오가스를 이용한 가스화기 운전 방안)

  • Lee, Joongwon;Joo, Yongjin;Chung, Jaehwa;Park, Seik;Kim, Uisik
    • Transactions of the Korean hydrogen and new energy society
    • /
    • v.24 no.3
    • /
    • pp.249-254
    • /
    • 2013
  • The integrated gasification combined cycle (IGCC) system is well known for its high efficiency compared with other coal fueled power generation system. The aim of this study is to confirm the feasibility of using bio gas in coal feeding system and syngas recirculation system. The effects of using bio gas in the gasifier on the syngas composition were investigated through simulations using the Aspen Plus process simulator. It was found that these changes had an influence on the syngas composition of the final stream and bio gas can be used in a gasifier system.

Switching Impulse Flashover Tests and Analysis for 765kV Jumper V-strings with Damaged Insulators

  • Choi, In-Hyuk;Shin, Koo-Yong;Lee, Dong-Il;Lim, Jae-Sup;Kim, Young-Hong;Lee, Hyung-Kwon
    • Journal of Electrical Engineering and Technology
    • /
    • v.8 no.2
    • /
    • pp.359-363
    • /
    • 2013
  • The 765kV transmission line will be maintained by live-line works for efficient operation. In order to maintain the 765kV transmission lines safely by live-line works, lineman has to know switching impulse flashover characteristics of the jumper V-strings with damaged insulators in advance. In order to know the flashover characteristics this paper carried out experimental flashover mockup tests for jumper V-string with damaged insulators in the outdoors. And it suggests flashover characteristics of the 765kV jumper V-strings also. The results will be used in estimating the safety of live working for 765kV transmission lines.

The Development of Distribution Planning System and Distribution Line Planning System (배전계획 시스템(DISPLAN) 및 배전계통 운영계획 시스템(DLPLAN)의 개발)

  • Chae Woo Kyu;Park Chang Ho;Jeong Jong Man;Jeong Young Ho
    • Proceedings of the KIEE Conference
    • /
    • summer
    • /
    • pp.73-75
    • /
    • 2004
  • This paper presents the ability and the application of software packages for distribution planning which are DISPLAN(Distribution Planning System) and DLPLAN(Distribution Line Planning System) developed in KEPCO. After calculating size and position of maximum load by administration section for distribution, it forecasts the demand of distribution load considering growth location, increment, new load plan, etc of load by annual. Also it calculates distribution loss, voltage drop using modeled distribution line by you, and support for establishment and enlargement plan of substation and distribution line, decision of most optimal path. And it presents the abstract of used algorithm to develop this system.

  • PDF

Lessons Learned from Energy Storage System Demonstrations for Primary Frequency Control

  • Yu, Kwang-myung;Choi, In-kyu;Woo, Joo-hee
    • KEPCO Journal on Electric Power and Energy
    • /
    • v.4 no.2
    • /
    • pp.107-114
    • /
    • 2018
  • In recent years, ESS (Energy Storage System) has been widely used in various parts of a power system. Especially, due to its fast response time and high ramp rate, ESS is known to play an important role in regulating grid frequency and providing rotational inertia. As the number of installed and commercially operating ESSs increases, the reliability becomes an important issue. This paper introduces control schemes and presents its test method for grid-connected ESS for primary frequency regulation. The test method allows to verify the control operation in the individual operation mode and state. A validation of the method through actual ESS test in a electrical substation is presented in the case study section.

Construction of Database for Reliability Evaluation of the Large Power System (확률론적 공급신뢰도 평가를 위한 전압레벨별 데이터베이스 구축방안)

  • Moon, S.P.;Shin, T.W.;Jang, B.H.;Jeon, D.H.;Kwak, H.S.;Han, G.N.;Choi, J.S.
    • Proceedings of the KIEE Conference
    • /
    • 2006.07a
    • /
    • pp.74-75
    • /
    • 2006
  • The reliability evaluation methods for the bulk power system habe been studied by several electric utilities. The evaluation methods based on the probability theory and the computer packages are being developed or already practicalized. But without correct probabilistic data, accurate result couldn't be expected. In this point, the construction of database is needed. Some of probabilistic data for evaluation of bulk power system are shown in this paper.

  • PDF

Long Term Distribution Planning Process using the Forecasting Method of the Land Use (토지용도에 따른 부하예측을 이용한 중장기 배전계획 수립)

  • Kim, Joon-Oh;Park, Chang-Ho;Sun, Sang-Jin;Lee, Jae-Bong;Kwon, Sung-Chul
    • Proceedings of the KIEE Conference
    • /
    • 1999.07c
    • /
    • pp.1447-1449
    • /
    • 1999
  • The KEPCO is developing the load forecasting system using land-use simulation method and distribution planning system. A distribution planning needs the data of present loads, forecasted loads and substations. distribution lines information. By the distribution planning system, the distribution line designer determines the substations and feeder lines plan. This paper presents the method of formulation process for the long term load forecasting and optimal distribution planning, and describes the case study of long term distribution planning of Suwon-city according to the newly applied method.

  • PDF

State Estimation Method and MMI Format of KEPCO EMS (한전(韓電)EMS의 상태추정기법(狀態推定技法)과 MMI 형식(形式))

  • Lee, Kyung-Jae;Yu, Sung-Chul;Kim, Yeong-Han;Lee, Hyo-Sang
    • Proceedings of the KIEE Conference
    • /
    • 1988.07a
    • /
    • pp.866-869
    • /
    • 1988
  • In the operation of a power system, the security of the system has acquired significant importance to supply electric power of better quality. The State Estimator, a part of security functions, provides a complete real time solution estimate of the steady-state conditions of the power system for use by the Real Time Network Analysis functions. This paper briefly introduces the Fast Decoupled Weighted Least Square State Estimator which is adopted in the KEPCO EMS with features of Man-Machine Interface.

  • PDF

Construction of IED Conformance Testing System (IED 적합성 인증시험 장치 구축)

  • Lee, N.H.;Kim, J.H.;Jang, B.T.;An, Y.H.;Hwang, K.C.
    • Proceedings of the KIEE Conference
    • /
    • 2007.07a
    • /
    • pp.489-490
    • /
    • 2007
  • In order to construct a digital substation based on IEC61850, All of the utility company should used IEDs to be verified and also vendors should get a certification from the international conformance testing organizationsuch as KEMA. So KEPRI in charge of POWER IT project related to SAS was required to IED conformance testing system, which can perform the test previously. The system, KEPCO developed, consists of HMI, IED (Intelligent Electronic Device), network equipment, V/I generator etc

  • PDF

Technical Feasibility Study on Live-line Maintenance Robot System for Overhead Distribution Lines (가공 배전선로 활선 정비 로봇 시스템의 기술 타당성 검토)

  • Joon-Young, Park;Yoon-Geon, Lee;Young-Sik, Jang
    • KEPCO Journal on Electric Power and Energy
    • /
    • v.8 no.2
    • /
    • pp.49-53
    • /
    • 2022
  • The distribution live-line work method is an operation method of working in a state in which electricity flows through overhead distribution lines to minimize inconvenience to electric customers due to power failure. In June 2016, to strengthen the safety of electrical workers, Korea Electric Power Corporation announced that it would in principle abolish the rubber glove method, in which workers wore protective equipment such as rubber gloves and performed their maintenance work. In addition, KEPCO announced that it would develop a short-range live working method using smart sticks and an advanced live-line maintenance robot system where workers work without touching wires directly. This paper is a preliminary study for the development of the live-line maintenance robot system, and deals with the results of analyzing the technical feasibility of whether the live works performed by workers can be replaced by robots or not.