Improvement contract sum adjustment method caused by price fluctuation (물가변동에 의한 계약금액 조정방안 개선 기초연구)

  • Cho Hun-Hee;Seo Jang-Woo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • v.y2004m10
    • /
    • pp.83-86
    • /
    • 2004
  • Index adjusted ration method has been widely utilized in public construction secter for contract sum adjustment by price fluctuation. In this method. the Production Price Index are used for calculating the base ratio. but the PPI can't reflect the property of construction project in respect of the selected item and weight structure. In this research we prove the problem of using the index adjusted ration method in contract sum adjustment by price fluctuation. and improve it by using the construction cost index. which has the property of construction project. And the result. we figure out the difference between the PPI and CCI by $6.7\%$ in maximum value.

  • PDF

A Study on Improvement of Contract Regulations for Adjusting Contract Amount in Public Construction - Focused on examples of price fluctuation classification - (공공건설 계약금액 조정의 계약예규 개선방안 연구 - 물가변동 분류 사례 중심으로 -)

  • Lee, Wonjei;Shin, Manjoong
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.4
    • /
    • pp.82-89
    • /
    • 2020
  • Article 64 of the Enforcement Decree of the National Contract Act The requirement of the pre-amendment statute related to the adjustment of the contract price was 5% or more of the price fluctuation rate from the date of the contract. However, the meeting requirement was changed from 5% or more to 3% or more from the date of signing of the Presidential Decree No. 19035 to 2005. 9. 8. The method of adjusting the contract amount was also changed to determine the contractor's desired adjustment method at the time of contract. Alleviating these requirements and revising the empowerment of contract partners is intended to prevent difficulties in achieving smooth objectives by applying to public construction contractors without unfairly benefiting or unfavorable to contract partners. Even if the standards are relaxed and the rights are secured as described above, if the existing provisions for the adjustment of price fluctuation are applied, unlike the original purpose of the government system, the Korea Bank's price economic statistics classification method and the contract construction classification criteria applied in public construction work Due to the inconsistency, it can be seen that the amount of adjustment for price fluctuation by construction type is excessive and underestimated. Therefore, the purpose of this study is to analyze problems through cases and to make appropriate construction cost adjustment through improvement measures.

An Improvement Plan of Contract Price Adjustment through the Problem Analysis of the Current Price Escalation Regulation in Construction Projects (현행 건설공사 물가변동 제도의 문제점 분석을 통한 계약금액조정 개선방안)

  • Park, Yang-Ho;Kown, Beom-Jun;Kim, Yong-Su
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2006.11a
    • /
    • pp.435-439
    • /
    • 2006
  • The purposes of study is to propose a new method contract price adjustment in construction projects. The research method of this study includes a case analysis and questionnaire survey. The results of this study are as follows: 1) For improvement method of contract amount adjustment, enactment for legislation pertaining to computation methods such as military's organization through total unit cost, and price flexibility computation at the point of design modification were presented. 2) Arithmetic formulas for cases in which volume is deleted or modified below the price flexibility exemption amount or in which there is no change to quantity, at the occurrence of design modification resulting from price flexibility, were proposed.

  • PDF

CONSTRUCTION COST INDEX FOR APPLYING INDEX ADJUSTMENT RATE IN THE ROAD PROJECT

  • Jin-Young Chun;Sungkwon Woo
    • International conference on construction engineering and project management
    • /
    • 2005.10a
    • /
    • pp.1112-1117
    • /
    • 2005
  • Construction cost index is generally used to estimate the new project cost based on past construction data and to adjust contract cost when the price change of various articles and items of expenditure composing the contract occurs. In Korea, it is mostly used for adjustment of construction contract cost due to fluctuation of prices. However index adjustment rate which is used for adjustment of construction contract cost had some problems in calculating cost index of each expenditure item that could not reflect properly the change of construction cost. For supplementing these problems, the research of developing construction cost index has been executed. Through the precedent research, these problems were partially resolved but still remain. Therefore this research proposes method of making cost index that utilizes representative items of labor, material, and equipment by analyzing bill of quantity of road construction, through analysis and comparison of precedent study. By using this method, it is expected to solve problems which were not reflected in precedent studies.

  • PDF

Improvement of contract sum adjustment method caused by price fluctuation using construction cost index (건설공사비지수를 활용한 물가변동에 의한 계약금액 조정방안 개선)

  • Cho Hun-Hee;Doe Geun-Young
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.1 s.23
    • /
    • pp.162-168
    • /
    • 2005
  • Index adjusted ratio method has been widely utilized in public construction sector for contract sum adjustment by price fluctuation. In this method, the Production Price Index are used for the base ratio, but the PPI can't reflect the character of construction project in respect of the selected items and weight. In this research we prove the problem of using the index adjusted ration method in contact sum adjustment by price fluctuation, and improve it by using the construction cost index, which has the property of construction project. And we figure out the efficiency of the proposed method by case study.

Improvement on the Managerial Method of Price Fluctuation System (물가변동제도 운영방식 개선방안)

  • Lee, Jae-Seob;Shin, Young-Chul
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.2
    • /
    • pp.3-11
    • /
    • 2011
  • There are several causes to recalculate the contract amount in public construction projects. Among them, the escalation clause was introduced in 1969 and now the condition to recalculate the cost is effective after 90 days from the date of contract and the rate of fluctuation should be more than 3% from the date of bidding. The two calculation methods for the rate of fluctuation are item-adjustment and index-adjustment. According to the results of investigation into 4 public institutions and 163 projects, all of them have used the method of index-adjustment and the rate of projects that spend over 6 months obtaining the approval of contract amount adjustment is more than 90%. The reason for spending lots of time is caused by problems of the calculation method on the price fluctuation rate. Therefore, it is necessary that the calculation method should be diversified to cope with the problems and a option of the builder should be expanded as well. Furthermore, if the way to apply correction factors to construction price index and average index based on the producer and consumer price index made by the bank of Korea is added, then the duration will be reduced without additional expenses. This study proposed the diversification of the calculation method using price fluctuation rate and builders' expanded options as improvement on the managerial method of Price Fluctuation System for the prompt and efficient contract amount adjustment.

A Study on Improvements of Regulation for the Preventing Commercial Disputes Related to Adjustment of Subcontract Price (하도급대금 조정 관련 분쟁의 예방을 위한 법규 개선방안에 관한 연구)

  • Min Byeong-Uk;Lee Jong-Gwang;Kim Yong-Su
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.1 s.23
    • /
    • pp.186-194
    • /
    • 2005
  • The purpose of this study is to examine the problems of the regulations regarding the modification of subcontact price. It also suggests several measures to improve the regulations related to the subcontact price adjustment which help to reduce unnecessary claims and commercial disputes. The literature research, structure and context analysis on the subcontract regulation and survey are adopted as basic research methods. The primary findings of this study are summarized as the following: (1) A provision outlining necessary procedures that an owner and a contractor should notify a subcontract or the adjustment of contact price needs to be made. (2) A provision allowing procedures that subcontactor could make the alteration of subcontract agreement and adjustment of subcontact price needs to be made. (3) The terminology like a unit cost and the rate of contact price needs to be clearly defined in order to improve the criterions of the subcontact price adjustment. (4) The criterions and additional expenses that the contractors ate responsible far need to be defined.

The Rationalization through Comparative Analysis of Price Fluctuation Adjustment Method (물가변동 조정방법의 비교분석을 통한 합리화 방안)

  • Kim, Seong-Hee
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.1
    • /
    • pp.67-76
    • /
    • 2012
  • There are index adjustment method and item adjustment method in estimation methods for price fluctuation rate of public constructions. A relevant regulation has put item adjustment method as a principle, but in most construction, contract sum adjustment has been made by index adjustment method. Hence, this study, by figuring out width and causes of the gap between index adjustment method and item adjustment method through direct comparative analysis, solved inequality caused by difference between them and suggested a rational way against irrationality of each method. For building operations of public housing construction, a detailed fluctuation rate by index adjustment method and item adjustment method of construction cost elements of the same construction, that is, direct material cost, direct labor cost and historical construction cost was estimated to analyze difference between two adjustments and establish its cause. Across the analysis, it was found that fluctuation rate by item adjustment method was estimated lower than that by index adjustment method and difference between methods for estimating fluctuation rate of quotation unit price and application of index unrelated to construction type and construction nature are main causes of the difference. This study has a significance in that, for smooth contract sum adjustment between contracting parties, it practically proved the real difference between adjustment methods by conducting comparative analysis of the difference in direct correspondence way.

A Delphi Study on the Price Escalation Clause in a Construction Contract

  • Choi, Min Soo;Kim, Moo Han
    • Architectural research
    • /
    • v.8 no.1
    • /
    • pp.69-76
    • /
    • 2006
  • The purpose of this study is to suggest policies to improve the price escalation system in a construction contract through a Policy Delphi technique. The Delphi, including two times questionnaires and a group discussion, was conducted by joining 14 experts. Also, the escalation provisions of various countries were examined. Results of the Delphi showed that the minimum fluctuation rate for price escalation was desirable at a level of 3%. To compute the fluctuation rate, calculating the price fluctuation of overall articles was more desirable than using price indices. A bidding date was more reasonable as the initial date of change in price. Losses caused by price change should be shared between contractor and owner; therefore a deduction rate should be introduced in price escalation. Meanwhile, overhead and profit should be adjusted in proportion to the fluctuation rate; but advance payment or the delayed construction amount should be deducted from the adjusted amount.

The Rationalization of Contract Sum Adjustment through Case Study of Price Fluctuation Adjustment based on Index Adjustment Method (물가변동조정 사례분석을 통한 지수조정방법기반 계약금액조정 합리화방안)

  • Kim, Seong-Hee
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.4
    • /
    • pp.70-78
    • /
    • 2011
  • In case of long time progressive construction work, we need contract sum adjustment due to escalation for a period of works and the process of applying, consistent and obvious criterion is required. In this study, it were attempted to figure out problem and study this rational improvement by giving examples based on core activities of escalation adjustment. Based on literature study and legal system analysis, we classified processes of contract sum adjustment for escalation and defined 20 core activities for each process. From this measured variable, we carried out case study by giving 37 examples of escalation. As a result of case study, problems of each process was found and we suggested rational improvement. As this study, providers will be able to waste budget and the other will be given smooth escalation adjustment.