Improvement contract sum adjustment method caused by price fluctuation

물가변동에 의한 계약금액 조정방안 개선 기초연구

  • 조훈희 (한국해양대학교 해양공간건축학부) ;
  • 서장우 (삼성중공업건설)
  • Published : 2004.10.01

Abstract

Index adjusted ration method has been widely utilized in public construction secter for contract sum adjustment by price fluctuation. In this method. the Production Price Index are used for calculating the base ratio. but the PPI can't reflect the property of construction project in respect of the selected item and weight structure. In this research we prove the problem of using the index adjusted ration method in contract sum adjustment by price fluctuation. and improve it by using the construction cost index. which has the property of construction project. And the result. we figure out the difference between the PPI and CCI by $6.7\%$ in maximum value.