Prediction of Strength Development of the Slab and Wall Concrete at Jobsite Applying Wireless Sensor Network (CIMS) based on Maturity (적산온도 기반의 무선센서 네트워크(CIMS)를 이용한 현장타설 슬래브 및 벽체 콘크리트의 압축강도 추정)

  • Kim, Sang-Min;Shin, Se-Jun;Seo, Hang-Goo;Kim, Jong;Han, Min-Cheol;Han, Cheon-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2020.06a
    • /
    • pp.23-24
    • /
    • 2020
  • In this study, the concrete compressive strength estimation system Concrete IoT Management System (hereinafter referred to as CIMS) was developed, and CIMS was applied to domestic field structure slabs and wall concrete to check whether CIMS is practically available and to estimate the accuracy of the initial strength estimation of concrete. As a result, it shows a very high correlation when the compressive strength of the specimen for structural management is compared with the estimated strength of CIMS in terms of integrated temperature, and it is expected to be gradually applied to domestic construction sites in the future.

  • PDF

Estimation of Compressive Strength of Fly Ash Concrete subjected to High Temperature (고온조건하에서 플라이애시를 사용한 콘크리트의 압축강도증진 해석)

  • Han Min-Cheol
    • Journal of the Korea Institute of Building Construction
    • /
    • v.6 no.3 s.21
    • /
    • pp.99-105
    • /
    • 2006
  • In this paper, the estimation of compressive strength of concrete incorporating fly ash subjected to high temperature is discussed. Ordinary Portland cement and fly ash cement(30% of fly ash) were used, respectively. Water to binder ration ranging from 30% to 60% and curing temperature ranging from $20^{\circ}C{\sim}65^{\circ}C$ were also adopted for the experimental parameters. According to results, at the high temperature, FAC had higher strength development at early age than OPC concrete and it kept its high strength development at later age due to accelerated pozzolanic reaction subjected to high temperature. For strength estimation, Logistic model based on maturity equation and Carino model based on equivalent age were applied to verify the availability of estimation model. It shows that fair agreements between calculated values and measured values were obtained evaluating compressive strength with logistic curve. The application of logistic model at high temperature had remarkable deviations in the same maturity. Whereas, the application of Carino model showed good agreements between calculated values and measured ones regardless of type of cement and W/B. However, some correction factors should be considered to enhance the accuracy of strength estimation of concrete.

Estimation of Compressive Strength of Concrete Using Blast Furnace Slag Subjected to High Temperature Environment (고온환경 조건하에서 고로슬래그를 사용한 콘크리트의 압축강도 증진 해석)

  • Han, Min-Cheol;Shin, Byung-Cheol
    • Journal of Environmental Science International
    • /
    • v.16 no.3
    • /
    • pp.347-355
    • /
    • 2007
  • In this paper, estimation of the compressive strength of the concrete incorporating blast furnace slag subjected to high temperature was discussed. Ordinary Portland cement and blast furnace slag cement (BSC;30% of blast furnace slag) were used, respectively. Water to binder ratio ranging from 30% to 60% and curing temperature ranging from $20^{\circ}C{\sim}65^{\circ}C$ were also chosen for the experimental parameters, respectively. At the high temperature, BSC had higher strength development at early age than OPC concrete and it kept its high strength development at later age due to accelerated latent hydration reaction subjected to high temperature. For the strength estimation, the Logistic model based on maturity equation and the Carino model based on equivalent age were applied to verify the availability of estimation model. It was found that fair agreements between calculated values and measured values were obtained evaluating compressive strength with logistic curve. The application of logistic model at high temperature had remarkable deviations in the same maturity. Whereas, the application of Carino model showed good agreements between calculated values and measured ones regardless of type of cement and W/B. However, some correction factors should be considered to enhance the accuracy of strength estimation of concrete.

Insulation Effect of Double Layered Bubble Sheet Application in Cold Weather Concrete and Initial Quality Control by Wireless Sensor Network (한중시공에서 2중 버블시트 포설에 따른 단열 효과분석 및 무선센서 네트워크에 의한 초기 품질관리)

  • Han, Min-Cheol;Seo, Hang-Goo
    • Journal of the Korea Institute of Building Construction
    • /
    • v.21 no.1
    • /
    • pp.21-29
    • /
    • 2021
  • The objective of this study is to evaluate the effect of the application of double layered bubble sheet on the curing of slab and wall concrete placed at the job site in cold weather and to offer a feasibility of Concrete IoT Management System(CIMS), which is wireless sensor network developed by the authors, to manage early age quality of the concrete in terms of temperature, maturity and strength development. Test results indicated that the application of bubble sheet enhances the insulation performance, which results in an increase of the temperature by around 1~20. 6℃. It is found that CIMS can gather the temperature, maturity and strength development data from the sensors embedded from 30 m far from CIMS successfully. Predicted compressive strengths by CIMS had good agreement with measured ones within 2 MPa error level until 7 days. It is thought that the combination of the bubble sheet application for cold weather protection and CIMS for quality management tool in cold weather concreting contributes to shorten the time for the form removal by one day.

An Experimental Study on the Early Strength Prediction of Concrete by Maturity Method (적산온도법을 이용한 콘크리트 조기강도 예측에 관한 실험적 연구)

  • Kwon, Hae-Won;Bae, Yeoun-Ki;Kim, Suk-Il;Jee, Suk-Won;Lee, Jae-Sam;Song, In-Myung
    • Proceedings of the Korea Concrete Institute Conference
    • /
    • 2008.04a
    • /
    • pp.753-756
    • /
    • 2008
  • Recently, construction work period reduction is a very important topic of construction business circles. Because that is just big cost reduction. There is an important part of construction to decide the removal time of form. For prediction strength for removal form, P type schmidt hammer method and maturity method is used that. In case early strength prediction of maturity method, that is problem. Because setting duration of concrete is not proper considering. So this experimental study is a coefficient(A) of maturity method.

  • PDF

On the Application of Risk Management by Levels of Project Management Maturity (프로젝트관리 성숙도별 리스크관리 적용)

  • Min, Taek-Kee
    • Journal of Korean Society of Industrial and Systems Engineering
    • /
    • v.34 no.2
    • /
    • pp.19-29
    • /
    • 2011
  • The uncertainty of a project generates risks hindering the goal achievement of the project, and the risks affect the success or failure of the project significantly. Risk management, a part of the project management, includes various processes, and there are also various tools or techniques applicable to that. In an organization, the application of project management develops gradually from low to high maturity, and the organization should choose and implement a method of application proper for the level of its maturity. This article suggests a method to reduce inefficiency of the management and how to apply risk management by levels of maturity for easier application. For this, the stages of project management maturity levels were divided into the introduction, development, and maturity step, and methods of risk management suitable for each stage were applied. And methods of risk management that need to be applied by the levels of project maturity are divided into three factors : risk management processes, risk management tools and techniques, and risk management standards and templates. It is expected to be favorable approaches for the application of risk management in an organization to divide those factors into more concrete processes, tools, techniques, and standards and apply them by the levels of management maturity.

EFFECT OF HEAT CURING METHODS ON THE TEMPERATURE HISTORY AND STRENGTH DEVELOPMENT OF SLAB CONCRETE FOR NUCLEAR POWER PLANT STRUCTURES IN COLD CLIMATES

  • Lee, Gun-Che;Han, Min-Cheol;Baek, Dae-Hyun;Koh, Kyung-Taek
    • Nuclear Engineering and Technology
    • /
    • v.44 no.5
    • /
    • pp.523-534
    • /
    • 2012
  • The objective of this study was to experimentally investigate the effect of heat curing methods on the temperature history and strength development of slab concrete exposed to $-10^{\circ}C$. The goal was to determine proper heat curing methods for the protection of nuclear power plant structures against early-age frost damage under adverse (cold) conditions. Two types of methods were studied: heat insulation alone and in combination with a heating cable. For heat curing with heat insulation alone, either sawdust or a double layer bubble sheet (2-BS) was applied. For curing with a combination of heat insulation and a heating cable, an embedded heating cable was used with either a sawdust cover, a 2-BS cover, or a quadruple layer bubble sheet (4-BS) cover. Seven different slab specimens with dimensions of $1200{\times}600{\times}200$ mm and a design strength of 27 MPa were fabricated and cured at $-10^{\circ}C$ for 7 d. The application of sawdust and 2-BS allowed the concrete temperature to fall below $0^{\circ}C$ within 40 h after exposure to $-10^{\circ}C$, and then, the temperature dropped to $-10^{\circ}C$ and remained there for 7 d owing to insufficient thermal resistance. However, the combination of a heating cable plus sawdust or 2-BS maintained the concrete temperature around $5^{\circ}C$ for 7 d. Moreover, the combination of the heating cable and 4-BS maintained the concrete temperature around $10^{\circ}C$ for 7 d. This was due to the continuous heat supply from the heating cable and the prevention of heat loss by the 4-BS. For maturity development, which is an index of early-age frost damage, the application of heat insulation materials alone did not allow the concrete to meet the minimum maturity required to protect against early-age frost damage after 7 d, owing to poor thermal resistance. However, the combination of the heating cable and the heat insulating materials allowed the concrete to attain the minimum maturity level after just 3 d. In the case of strength development, the heat insulation materials alone were insufficient to achieve the minimum 7-d strength required to prevent early-age frost damage. However, the combination of a heating cable and heat insulating materials met both the minimum 7-d strength and the 28-d design strength owing to the heat supply and thermal resistance. Therefore, it is believed that by combining a heating cable and 4-BS, concrete exposed to $-10^{\circ}C$ can be effectively protected from early-age frost damage and can attain the required 28-d compressive strength.

Determination of the Protecting Periods of Frost Damage at Early Age in Cold Weather Concreting (한중콘크리트의 초기 동해 방지를 위한 초기 양생기간의 산정)

  • 한천구;한민철
    • Journal of the Korea Concrete Institute
    • /
    • v.12 no.3
    • /
    • pp.47-55
    • /
    • 2000
  • Protections from the frost damage at early ages are one of the serious problems to be considered in cold weather concreting. Frost damage at early ages brings about the harmful influences on the concrete structures such as surface cracks and declination of strength development. Therefore, in this paper, protecting periods of frost damage at early ages according to the standard specifications provided in KCI(Korean Concrete Institute) are suggested by appling logistic curve, which evaluates the strength development of concrete with maturity. W/B, kinds of cement and curing temperatures are selected as test parameters. According to the results, the estimation of strength development by logistic curve has a good agreement between calculated values and measured values. As W/B and compressive strength for protecting from frost damages at early ages increase, it is prolonged. It shows that the protecting periods of FAC(Fly Ash Cement) and BSC(Blast-furnace Slag Cement) concrete are longer than those of OPC(Ordinary Portland Cement) concrete. The protecting peridos from frost damage at early age by JASS are somewhat shorter than those by this paper.

Temperature and humidity effects on behavior of grouts

  • Farzampour, Alireza
    • Advances in concrete construction
    • /
    • v.5 no.6
    • /
    • pp.659-669
    • /
    • 2017
  • Grouts compared to other material sources, could be highly sensitive to cold weather conditions, especially when the compressive strength is the matter of concern. Grout as one the substantial residential building material used in retaining walls, rebar fixation, sidewalks is in need of deeper investigation, especially in extreme weather condition. In this article, compressive strength development of four different commercial grouts at three temperatures and two humidity rates are evaluated. This experiment is aimed to assess the grout strength development over time and overall compressive strength when the material is cast at low temperatures. Results represent that reducing the curing temperature about 15 degrees could result in 20% reduction in ultimate strength; however, decreasing the humidity percentage by 50% could lead to 10% reduction in ultimate strength. The maturity test results represented the effect of various temperatures and humidity rates on maturity of the grouts. Additionally, the freeze-thaw cycle's effect on the grouts is conducted to investigate the durability factor. The results show that the lower temperatures could be significantly influential on the behavior of grouts compared to lower humidity rates. It is indicated that the maturity test could not be valid and precise in harsh temperature conditions.