• Title/Summary/Keyword: 지보 설계

Search Result 170, Processing Time 0.027 seconds

The Evaluation on the Type of Support Element by Field Test Data in 4-lane Wide Road Tunnel (4차로 광폭터널의 계측결과를 이용한 암반등급에 따른 지보수준 평가)

  • Do, Jongnam;Kim, Yeonjoong;Lee, Chanbok;Chun, Byungsik
    • Journal of the Korean GEO-environmental Society
    • /
    • v.13 no.1
    • /
    • pp.15-20
    • /
    • 2012
  • Field measurement is a very essential factor for economic aspect and estimation of stability of tunnels. In this paper, various types of support element based on field test data in 4-lane wide road tunnel were evaluated. And stability and economical efficiency were also estimated. The estimated value were compared with design value and the type of support element which is applicable to site condition was evaluated. The results show that most of support elements were modified under the standard value(30mm) and type of support element which is already constructed was overestimated. So, appropriate level of support element have to be presented to save the time and cost during construction.

NATM시공 산악터널에서 암반분류 및 계측에 의한 지보공 선정 사례연구

  • 김영근;장정범;정한중
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 1996.03a
    • /
    • pp.25-34
    • /
    • 1996
  • 터널은 긴 선상구조물로서 사전지질조사에 의해 설계에 필요한 정보를 정밀도 높게 구하는 것이 매우 어렵다. 따라서 터널시공 중 암반 및 지질상황을 관찰하고, 터널주변 지반의 거동을 계측하여 지반에 적합한 지보공을 설계ㆍ시공하는 것이 필수적이다. 이를 위해서 터널시공 중 정량적인 암반분류와 계측(일상관리계측과 대표단면계측)이 주기적으로 실시되고 있지만, 이러한 결과를 어떻게 시공에 반영하느냐는 터널의 합리적인 시공에 있어 매우 어려우면서도 중요한 문제라 할 수 있다. (중략)

  • PDF

블록반응곡선을 이용한 불연속 암반내 공동에 대한 지보설계에 관한 연구

  • 이영주;이희근
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 1995.03a
    • /
    • pp.41-47
    • /
    • 1995
  • NATM공법에서 지보는 주로 암반반응곡선(Ground Reaction Curve, GRC)상에서 설계된다. 그러나 GRC는 유도과정에서 많은 가정을 지니고 있어 시공에 직접 반영하기에는 많은 한계를 지닌다. 특히 과지압에 의한 소성거동의 문제가 심각하지 않고, 암반의 거동이 불연속면에 영향을 많이 받는 지역에서는 GRC의 가정 중에 하나인 등방 연속체라는 가정은 큰 결점 중의 하나이다. (중략)

  • PDF

숏크리트 거동에 대한 갱도모형실험과 수치해석의 비교

  • Yu, Gwang-Ho;Lee, Min-Ho;Park, Yeon-Jun
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 2007.03a
    • /
    • pp.112-121
    • /
    • 2007
  • 지보재의 파괴가 고려된 터널의 안전율을 산정하기 위해 허용응력 설계법에 기초하여 숏크리트 내에 발생하는 응력이 허용응력을 초과하면 숏크리트가 파괴된다고 가정하고, 전단강도 감소기법을 이용하여 수치해석적(2차원)으로 구하는 방법이 유광호 등(2005)에 의해 제시되었다. 하지만 허용응력 설계법에 근거한 방법은 숏크리트의 허용 휨응력을 과소평가하여 터널의 안정성 및 안전율을 과소평가하는 경향이 있다. 따라서 본 논문에서는 숏크리트의 파괴거동을 갱도모형실험을 통해 확인하고 3차원 수치해석에 의해 검증하였다. 갱도모형실험에 사용된 터널은 실제 터널의 거동을 모사하기 위해 폭 3.3m, 높이 2.9m, 깊이 0.5m의 마제형으로 제작되었다. 지보재인 숏크리트는 거푸집을 이용하여 타설하고 28일간 양생하였고 7개의 실린더와 30cm의 모래 뒷채움을 이용하여 지보재에 최대한 등방하중이 가해질 수 있도록 하여 실험을 수행하였다.

  • PDF

A Study on Quantity of Shotcrete Sprayed in a NATM Tunnel Based on Field Measurements (현장 실측자료 분석을 통한 NATM 터널의 숏크리트 투입량에 관한 연구)

  • Lee, Cheol Ju
    • Journal of the Korean GEO-environmental Society
    • /
    • v.12 no.9
    • /
    • pp.47-54
    • /
    • 2011
  • This study has analysed overbreaks, shotcrete rebound and the ratio between the actual quantity of shotcrete sprayed compared to designed quantity measured during a NATM tunnel construction. Based on the measurements of size of the excavated tunnel faces, an average overbreak was about 28.5 cm, which is about 260% of allowable overbreak. The measured shotcrete rebound was about 7.2% in average which is about half the allowable rebound(15%). In addition, due to overbreaks and rebound the actual quantity of shotcrete used in the tunnelling work was about 116.5 % of the designed value. It has been found from the field measurements that the quantity of shotcrete showed some relation with rock mass rating(RMR) and the standard guideline of tunnel supports, but the size of overbreak showed less correlation with RMR and the standard guideline of tunnel supports. Hence, the current tunnel design specifications stating the size of overbreak based entirely on the standard guideline for tunnel supports should perhaps be reestablished. The insight into the design guideline regarding overbreak and actual quantity of shotcrete will be reported and discussed.

A numerical study on the analysis of behavior characteristics of inclined tunnel considering the optimum direction of steel rib (강지보재 최적 설치방향을 고려한 경사터널의 거동특성에 대한 수치해석적 연구)

  • Park, Sang-Chan;Kim, Sung-Soo;Shin, Young-Wan;Shin, Hyu-Soung;Kim, Young-Geun
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.10 no.3
    • /
    • pp.245-256
    • /
    • 2008
  • The steel rib, one of the main support of tunnel, plays a very important role to stabilize tunnel excavation surface until shotcrete or rockbolt starts to perform a supporting function. In general, a steel rib at the horizontal funnel is being installed in the direction of gravity which is known favorable in terms of constructability and stability. However, as the direction of principal stress at the inclined tunnel wall is different from that of gravity, the optimum direction of steel rib could be different from that at the horizontal tunnel. In this study, a numerical method was used to analyze the direction of force that would develope displacement at the inclined tunnel surface, and that direction could be the optimum direction of steel rib. The support efficiency of steel rib could be maximized when the steel rib was installed to resist the displacement of the tunnel. Three directions which were recommended for the inclined tunnels in the Korea Tunnel Design Standard were used for the numerical models of steel rib direction. In conclusion, the results show that all displacement angle of the models are almost perpendicular to the tunnel surface regardless of face angle. So if the steel rib would be installed perpendicular to the inclined tunnel surface, the support efficiency of steel rib could be maximized.

  • PDF

Evaluation of the Standard Support Pattern in Large Section Tunnel by Numerical Analysis and Field Measurement (수치해석 및 현장계측에 의한 대단면 터널 표준지보패턴의 적정성 검증)

  • Byun, Yoseph;Chung, Sungrae;Song, Simyung;Chun, Byungsik;Park, Duhee
    • Journal of the Korean GEO-environmental Society
    • /
    • v.12 no.7
    • /
    • pp.5-12
    • /
    • 2011
  • When choosing the support pattern of tunnel, the characteristics of rock are identified from the result of the surface geologic survey, boring, and geophysical prospecting and laboratory test. And a rock mass rating is classified and excavation method and standard support pattern are designed considering rock classification, domestic and international construction practices, numerical analysis. According to the revised design standard for tunnel, it was recommended to classify the rock mass rating for the design of tunnel into a rating based on RMR. If necessary, it proposed a flexible standard allowed applying more atomized the rock mass rating and Q-System. Also, the resonable verification of the support pattern must be accompanied because the factors affecting the structure and behavior of ground during the construction of tunnel are the main factors of uncertainty factors such as the nature of ground, ground water and the characteristics of structural materials. These days, such verification method is getting more specialized and diversified. In this study, the empirical method, numerical analysis and comparative analysis of in situ measurements were used to prove the reasonableness in the support pattern by RMR and Q-value on the Imha Dam emergency spillway.

A Study on Concrete Lining Stress Changes Considering Load Supporting Capacity of Primary Supports of NATM Tunnel (NATM 터널에서 1차지보재의 지보압을 고려한 콘크리트라이닝 응력변화에 관한 연구)

  • Jeon, Sang Hyun;Shin, Young Wan;Yoo, Han Kyu
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.31 no.4C
    • /
    • pp.147-154
    • /
    • 2011
  • Currently NATM tunnels are designed by applying the initial ground loads caused during construction to the primary supports, conisting of shotcrete, steel ribs and rock bolts. For long term considerations, it is assumed that the primary supports lose its functionality and therefore the secondary support, i.e. concrete lining, is design to resist against the entire ground loads. But the steel ribs, usually applied to bad ground conditions, are embedded in shotcrete causing very little corrosion and therefore the assumption that the primary support will lose all of its functionality is too conservative. Also even though shotcrete carbonates in long term, excluding it from design is also too conservative. In this study, we have, through analytical and numerical analysis, set a rational level of support pressure and allowable relaxed rock mass height sustainable by the primary support for long term design. Changes in sectional forces of the concrete lining considering the calculated support pressure of the primary supports was also carried out. Shallow subway tunnels were considered in the analysis with weathered rock and soft rock ground conditions. The analysis results showed that, by considering the support pressure of steel ribs, an economical design of the concrete lining is possible.

Application of Holden Swellex Bolt for the Design of Long, and Large Profile Traffic Tunnels (대단면 장대터널에서의 Swellex Bolt의 설계적용)

  • 지왕률;이호성;정해성
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 2001.10a
    • /
    • pp.25-36
    • /
    • 2001
  • 록볼트의 작용효과는 지반이 굴착되어 안정화되는 초기 1달간이 가장 중요하고 품질관리 문제는 지반조건에 따라 부식에 대한 문제가 있으나, 기존의 전면접착형 록볼트의 경우도 작업여건상 그 확실성은 떨어지는 것이 현실이다. 또한 작업이 시간소모가 크고, 볼트의 지지효과도 충진재가 고결되어야 발효되는 약점을 갖고 있어, 일본, 말레이시아, 유럽 등에서 전면 마찰형 즉시 지보기능이 가능한 Swellex Bolt를 영구지보재로 사용하고 있는 경향이 있다. 기존의 전면 접착형 SN Bolt(이형철근)로써 Grouting 몰탈볼트와 Cem Bolt로 설계된 장대·대단면 도로터널 지보재를 현대식 Swellex Bolt로 대체 설계변경이 가능한 것인지에 대하여 볼트의 지지력 시험(Pullout Test), 볼트재질의 내구성 연구 및 설계변경에 따른 수치해석 등을 실시하여, 볼트로써 지지력을 확인하고, 재질의 안전성을 조사한 후 시공 사이클 타임을 줄이며, 견고하고 시공성이 우수한 Swellex Bolt로의 설계변경을 제안하게 되었다.

  • PDF