• Title/Summary/Keyword: 공기지연 분석방법

Search Result 41, Processing Time 0.022 seconds

A Case Study on Delay Analysis Methods in the Construction Projects (건설공사 공기지연 분석방법의 사례연구)

  • Kim, Young-Jae;Lee Woo-Chang;Hong Jung-Suk;Kim Kyung-Rai;Shin Dong-Woo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.5 no.6 s.22
    • /
    • pp.129-137
    • /
    • 2004
  • When we consider the present state of construction delay claim analysis, the delay analysis methods generally used from the abroad construction industries are not applied to our industry. By reviewing the existing methods of delay analysis, this study investigated the important concepts and characteristics of the delay analysis methods. Selection of the delay analysis methods could be decided among 1)As-planned versus as-built comparison method,2)What-if method,3)But-for method.4)CPA method, and 5)DAMUDS method. In order to make clear the characteristics and mechanisms of the analysis methods, this study performed a case study.

Delay Analysis Method Considering Productivity (생산성을 고려한 공기지연 분석방법)

  • Koo Ja-Min;Lee Jae-Seob
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.438-441
    • /
    • 2003
  • Construction delays are a common occurrence of most construction projects and difficult to analyze. there are some techniques to analyze delays, such as using CPM, Bar Chart but they are not enough to analyze concurrent and productivity lost delays. Productivity lost delays are different to interruption delays in computing the number of delays and analyzing concurrent delay. This paper describes the delay analysis method considering productivity including concurrent delay analysis.

  • PDF

Exploring Delays of The Mega Construction Project: The Case of Korea High Speed Railway (대형 건설사업의 공기지연분석: 경부고속철도 건설사업을 중심으로)

  • Han, Seung Heon;Yun, Sung Min;Lee, Sang Hyun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.26 no.5D
    • /
    • pp.839-848
    • /
    • 2006
  • Korea has become the 5th country to own and operate the high speed railroad in 2004. However, there were many difficulties until Koreans enjoy the first bullet train service with the average hourly speed of 300km. The high speed railroad requires elevated quality standards differently from the traditional railways. In addition to the technical difficulties, the construction project itself was an unpleasant case with huge delays and cost overruns mainly due to the lack of experiences, deficiency of owner$^{\circ}{\O}$s role, and increase of public resistances triggered by environmental concerns. This paper analyzes the reasons for delays on this mega-project. With respect to the characteristics of the whole project level, it is very complicated/linear project, whose total length is around 412 km with the composition of various sections in the route of the railway which have basically different conditions. For that reason, the analysis is performed in both macro and micro level. First, macroscopic analysis is performed to find critical subdivisions in the railway route that induces the significant delay in the opening due date. Then, microscopic analysis is followed to quantify the causes and effects of delays focused on these critical subdivisions in more detailed way. Finally, this paper provides lessons learned from this project to avoid the decisive delays in performing the similar large-scaled projects.

A Study on Substantiation Methodology for Extension of Time in International Mega-Project Claims (해외 대형건설공사 공기지연클레임의 공기연장기간 입증방법)

  • Kim, Young-jae;Kim, Tae-kyoung;Jo, Duk-sang;Lee, Hwang-ku
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.3
    • /
    • pp.165-176
    • /
    • 2015
  • Recently many Korean large-sized construction companies as well as specialty contractors have been expanding their business in the overseas market to mitigate impacts from long-term stagnation in the domestic market. Such as a result, it has been arisen as a major issue that contractors effectively manage the delays which have been commonly faced with in international mega-projects. Therefore it can be said that the ability of the delays management leads a success of project. This paper presents a review of literature for delay analysis methods such as time impact analysis(TIA) and raises practical problems to rationally substantiate the duration of extension of time(EoT) in international mega projects which have wide scope of works as well as complicated and detailed contract baseline programs by taking theoretical approaches. We suggest the two improvement concepts to substantiate the EoT claims which are effectively applicable to practical projects. The first is to sort out dominant delays among numerous delays in advance of applying a delay analysis. The second is to set up the delay sections with the advanced concept for analysing delays' effects by TIA. This study performed a case study on an actual international mega-project. to confirm the effectiveness of improvement concepts that this practical approach is applicable for the assessment of EoT. In conclusion, this paper supposes to provide practitioner in charge for an EoT claim with an advanced substantiation methodogy when they not only analyse the construction delays by using TIA, but also negotiate with stakeholders about with the assessment of EoT.

A Study on the Delay Analysis Methodologies in Construction of Korea High Speed Railway (경부고속철도 건설사업의 공기지연분석에 관한 연구)

  • Yun Sung-Min;Lee Sang-Hyun;Chae Myung-Jin;Han Seung-Heon
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2004.11a
    • /
    • pp.250-255
    • /
    • 2004
  • To analyze delay, Seoul - Daegu line of Korea High Speed Railway was divided into three sections and analyzed independently by the business characteristics. The analysis on the project delay reasons was performed on macro and micro scales. This analytic method was named as 'Macro-Micro Delay Analysis Method (MMDAM)'. The macro scale analysis has three approaches, which are (1) scheduling, (3) structural characteristic, (3) and responsibility of project administrative works. Micro analysis also has three, methodologies which are (1) As Planned Method, (2) As Built method, (3) Modified Time Impact Analysis for analyzing the most influential section which the largest delay occurred. Using elicited project delay reasons from above analysis, the questionnaire was carried out for analyzing the influence of project delay reason. The reasons of the delay were driven from two different aspects (1) structural characteristic and (2) responsibility of the people involved in the project. The reasons that were identified from aforementioned three sections are the factors of the delay of the large-scale government driven projects. Finally, the author suggested the methodology of identifying the project delaying factors. The author also analyzed delay reasons in both the overseas and domestic cases of high rapid railway construction and has elicited some benchmarks for the future projects.

  • PDF

A Delay Analysis based on the Comparison of the As-planned Schedule, As-built Schedule including All Delays and As-built Schedule absent Owner Delays (계획공정표, 모든 지연을 포함한 준공공정표, 발주자 지연을 제외한 준공공정표의 비교를 통한 공기지연분석)

  • Yun Chul-Sung;Chu Hae-Keum;Kim Seon-Gyoo
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.426-429
    • /
    • 2003
  • In the construction process, there are many change orders differing to the initial contracts came from the social needs and environmental changes. Most of them will impact to the construction process so that its effects occur project delays. Time extension and liquidated damage in the construction process come from schedule delay whether it is excusable or not non-excusable by the owner. However, those become the delay claims if the owner and the contractor are not agreed on this situation. One of the most important thing on the delay claims is the calculation of delay. The purpose of this study is to present the method of the time delay calculation by comparison of As-Planned schedule, As-Built schedule including all delay and As-Built schedule absent owner delay.

  • PDF

Function Development for Apportioning System of Responsible Number of Days by Construction Delay (공기지연에 따른 책임일수 산정 시스템 구축방안)

  • Kang, Leen-Seok;Kwon, Jung-Hui;Park, Seo-Young;Yun, Seon-Mi
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.805-808
    • /
    • 2007
  • Recently there are many contract claims, which are caused by duration delay, in construction industry. Many kinds of research for solving such duration delay problem are being progressed and an effective computerized system needs to improve it. This study suggests an improved methodology and necessary functions to make a time impact analysis system. This results will be useful for quantifying responsible number of days caused by duration delay.

  • PDF

Case Analysis on Application of Project Delay Analysis Method in Domestic Construction Project (국내 건설공사에서 공기지연 분석방법 적용 사례 분석)

  • Kim, Seon-Gyoo;Kwon, Soonwook
    • Korean Journal of Construction Engineering and Management
    • /
    • v.20 no.6
    • /
    • pp.98-106
    • /
    • 2019
  • Recently, the number of project delay-related claims and disputes in Korean construction projects has been increasing rapidly. This suggests that the domestic construction contract practice, which has traditionally been superior to the client, is changing into a mutually balanced relationship among the contracting parties. The project delay analysis selects the application method according to the type of schedule approved at the start of the construction and how the schedule management was performed during the construction. The most important prerequisite for project delay analysis is that a complete CPM schedule agreed at the beginning of the construction is prepared and the actual progress of such schedule is well documented. This study is about applying the project delay analysis methodology of a case where a contractor claims damages to a client while constructing a large new private building construction project. In this study, it is determined whether the application of the as-planned analysis method is appropriate to the incomplete CPM schedule and then proposes the as-planned vs. as-built analysis method based on the new standard as an alternative. Next, apply the as-planned vs. as-built analysis method to the schedule in the case project, and then compare it with the result of the as-planned analysis method. The purpose of this study is to suggest a project delay analysis method suitable for the domestic schedule management practices, so that it can be used as a meaningful reference in project delay disputes and litigations of domestic construction projects.

A Study on the Analysis of Delay Claim Risk in Apartment Housing Projects (공동주택공사에서의 공기지연 리스크분석에 관한 연구)

  • Kim Jae-Wook;Woo Kwang-Min;Lee Hak-Ki
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.217-221
    • /
    • 2003
  • This study proposes a new classification system and analysis methodology for time delay risk of apartment projects. And this study proposes the classification of major trades and risk level and risk index by performing expert-oriented interview and survey report on a national scale. The purpose of this study is to present basic data for time delay risk management system through the analysis of risk level, risk index and rank of major 5 trades(earth work, structure work, masonry work, window and door/glass work, and interior finish work) in apartment projects.

  • PDF

Estimating System for Responsible Days of Schedule Delay for Construction Projects through Time Impact Analysis (건설공사 공기지연 영향분석을 통한 책임일수 산정체계 구축방안)

  • Kang, Leen-Seok;Kwon, Jung-Hee
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.28 no.5D
    • /
    • pp.685-694
    • /
    • 2008
  • Recently, construction projects are being gradually changed to large projects with complicated work processes. As a result, claims are increasing as well. Of these, the claims by delayed construction duration are given much weight in the general construction claims. To solve this problem, researches to estimate damages due to delay are carried out in research institutes by analyzing the causes of schedule delay. A system to easily estimate responsible days by analyzing the complicated processes needs for project manager. This study suggests a methodology based on the time impact analysis method, which can utilize the consequential analytical method with the consideration of reduced construction period. The suggested methodology is verified by comparing with actual data of case study by the computerized system for estimating the responsible days.