Function Development for Apportioning System of Responsible Number of Days by Construction Delay (공기지연에 따른 책임일수 산정 시스템 구축방안)

  • Kang, Leen-Seok;Kwon, Jung-Hui;Park, Seo-Young;Yun, Seon-Mi
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.805-808
    • /
    • 2007
  • Recently there are many contract claims, which are caused by duration delay, in construction industry. Many kinds of research for solving such duration delay problem are being progressed and an effective computerized system needs to improve it. This study suggests an improved methodology and necessary functions to make a time impact analysis system. This results will be useful for quantifying responsible number of days caused by duration delay.

  • PDF

Datamodel for Productivity Management of Construction Project (건설공사 생산성 관리를 위한 데이터모델)

  • Ryu Han-Guk;Yu Jung-Ho;Lee Hyun-Soo
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.442-445
    • /
    • 2002
  • Construction delay claim occurs more often than any other claim. Delay claim impacts adversely the company's existence as well as the project's monetary problem. Because the calculation of the delay is not quantitative, owing not to have enough evidence, it is hard to solve evenly the delay claim. So, it is need to cumulate structurely the construction data or evidence during the construction. This study considers the established study about construction delay claim database and the problems and then presents the relation method between phase schedule and database. Finally, this study established the productivity claim database modeling for construction project through conceptual database modeling and logical database modeling based on information needed to make construction productivity database. So. the purpose of the study is to establish the datamodel for productivity management of construction project for calculating the delay days considering the lost productivity.

  • PDF

Delay Analysis Method Considering Productivity (생산성을 고려한 공기지연 분석방법)

  • Koo Ja-Min;Lee Jae-Seob
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.438-441
    • /
    • 2003
  • Construction delays are a common occurrence of most construction projects and difficult to analyze. there are some techniques to analyze delays, such as using CPM, Bar Chart but they are not enough to analyze concurrent and productivity lost delays. Productivity lost delays are different to interruption delays in computing the number of delays and analyzing concurrent delay. This paper describes the delay analysis method considering productivity including concurrent delay analysis.

  • PDF

Analysis of Delay Causation by Characteristics of Construction Projects (건설사업 특성에 따른 공기연장사유 분석)

  • Kim, Jong-Han;Kim, Kyung-Rai
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.1 s.35
    • /
    • pp.78-86
    • /
    • 2007
  • Top priority to manage construction projects is given to the planning and scheduling in order to keep the project duration, which is one of the most important factors in construction management. However, recently most of public construction projects especially for civil projects are delays and preventive research, many efforts were made concerning construction delays and preventive management methods. But analysis of delay causation, which is a main key to solve the problems is not done, yet. Therefore, in this research causation delays are analyzed by characteristics of construction projects, which are type of projects, type of contracts, project participants, and general condition. As a result of the analysis, delay causation are proved to be different by characteristics of the projects. The research results will be used for prevention of time extension and dispute resolution.

Optimal Scheduling based on Probabilitic Estimation of Construction Duration (확률적 공기산정에 의한 공정 합리화 방안)

  • Kim Sang-Joong;Lee Jae-Soeb
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.383-387
    • /
    • 2003
  • Construction project has many problem such as delay of the appointed date delivery, over budget, wether and site conditions. When several activities are influenced by the same factor, their duration may be delayed. This paper deals with the problem of construction duration estimating and schedule variation on the construction project. The theory of constraints technique for project management is referred to 'Critical Chain' technique. This paper shows optimal scheduling plan and time management technique, used probability construction duration estimating and scheduling buffer based on the critical chain project management.

  • PDF

An Administration Model for Causation of the Schedule Delays in Construction Projects (건설공사 공기연장사유 관리모델)

  • Kim, Jong-Han;Kim, Kyung-Rai
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.3
    • /
    • pp.125-133
    • /
    • 2007
  • If project time extension were required in the construction projects, either liquidated damages or extension costs should be applied according to causation of the schedule delays. However, in actual cases it is not applied so far according to the contract conditions. The reason why this situation happened Is that function of the present planning and scheduling is not working feasibly. The CPM schedule could not provide a proper solution for apportioning responsibility for the schedule delays. This situation could be considered as breach of contract and will cause potential disputes for schedule delay. Therefore, in this research process based contract administration model for construction delay claim is proposed to prevent schedule delay and solve the claims. The model is based on pro-active management for causation of delay to provide apportionment of responsibility and written evidences.