1. Introduction
The constant increase in Vietnam’s population has contributed to the need to address a series of issues such as the building of infrastructure, urban transportation systems, and the building of houses (P. Nguyen & Nguyen, 2020; Pham, Dao, Cho, Nguyen, & Pham-Hang, 2019; Vu et al., 2020). Also, the recent, widespread increase in the number of high-rise office buildings, commercial centers, and apartment buildings has contributed to the dynamic growth of the construction market in Vietnam. This is both an opportunity and a challenge for construction companies when investing and applying new technology, construction methods, equipment and machines, and optimizing their utilization. Construction equipment can accomplish many more times than what the strength of human power can do. Also, Yeo and Ning (2006) confirmed a large proportion of equipment purchases and hired costs in the total cost of a construction project. The cost of the major equipment may be as high as 36% of the total project construction cost (Prasertrungruang & Hadikusumo, 2009; Prasertrungruang & Hadikusumo, 2007). However, construction companies in Vietnam do not have a strict or optimal equipment management system. Existing equipment managementrelated processes for some companies include equipment procurement, supply, maintenance, and transfer only. There has been no optimal way to manage equipment from the beginning of the project and to link these processes into a closed cycle. All these manual and uncontrolled processes are, therefore, prone to risks and losses. This paper provides an insight into the risk factors in creating effective equipment management, and, thus, enable managers to take appropriate actions to improve management efficiency in project success and economic optimization.
2. Literature Review
The emerging Vietnamese economy has grown well in the Southeast Asia region in the recent years (Nguyen & Bui, 2020a, 2020b; Nguyen, Dang, & Ngo, 2019). Thus, an ever-increasing infrastructure demand has developed with a need to construct industrial buildings, residential houses, schools, bridges, roads, ports, hydropower plants, underground structures, etc. (Luong, Tran, & Nguyen, 2018; Sy, Likhitruangsilp, Onishi, & Nguyen, 2017). The demand, therefore, for construction equipment with high productivity and technical specifications has grown commensurately. Equipment includes movable property of diverse and abundant nature. In the construction industry, in particular, the equipment can be repeatedly reused, especially for highrise building projects or other construction activities. The tendency is for the machinery to become more and more compact and versatile. Depending on how the installation or task is performed, some equipment can become machines with separate parts or include a synchronous machine line. This refers to mechanical, electrical, electronic, and other factors combined to transform energy and materials into specific products for a social life or to the fulfillment of one or more different functions for a project.
Equipment management involves the planning and control of equipment used for supply, import, and export during its life cycle. The goal of the management is to ensure that equipment is delivered on schedule, in the required quantity, quality, and type at affordable costs. Effective equipment management is meaningful for the performance of a project as well as of a construction company (Nugraha & Putranto, 2019). During the implementation phase of the project, the determination of the equipment period of usage and life cycle is vital to ensure the optimal use and to limit equipment downtime to avoid project delays (Randunupura & Hadiwattege, 2013). Besides, equipment also influences overall project costs and profitability (Prasertrungruang & Hadikusumo, 2009).
Equipment can be technically classified by construction phases (Schaufelberger & Migliaccio, 2019): (i) the underground construction phase: where there is a need for excavators, bulldozers, graders, compactors, pile drivers, rebar bending and cutting machines, concrete pumps, and cranes; (ii) the frame construction phase: steel bending and cutting machines, concrete pumps, concrete mixers, formwork and bracing construction machines, tower cranes, and hoists; and (iii) the finishing phase: mortar mixers, material screen machines, forklifts, material transport vehicles (trolleys and forklifts), tower cranes, hoists, and electric winches, etc.
Equipment management effectiveness include the management of procurement, replacement, operation, repair, and maintenance (Tatari & Skibniewski, 2006). The equipment management process of a construction company usually consists of the following:
(a) Procurement and payment processes: A supervisor first proposes a warehouse keeper who then forwards it to the equipment supervisor. Next, the proposal is submitted to a Manager. After the manager’s approval, it is returned to the warehouse keeper, who takes charge of sending the request to a supplier. After that, the supplier makes the delivery which is checked by the warehouse keeper. If the equipment satisfies the requirements, the warehouse keeper will receive it; otherwise, it will be returned to the supplier.
(b) Payment process: Upon the acceptance of the goods, the supplier sends a payment request to the equipment supervisor for inspection. Then, it is submitted to the manager for approval before payment.
(c) Delivery and receipt process: (i) Equipment reception process: Equipment is delivered to a construction site where it is received and checked by the warehouse assistant. If satisfactory, documents will be submitted to the warehouse keeper for signature and goods reception; conversely, if unsatisfactory, the warehouse keeper will return the equipment to the supplier; and (ii) equipment delivery process: Equipment is checked and certified by the warehouse assistant and warehouse keeper. After that, the documents are forwarded to the equipment supervisor for his or her review and signature and finally submitted to the manager. If approved, the document is returned to the warehouse keeper for the fulfillment of procedures and the release of the goods.
(d) Equipment repair process: Damage to the equipment is informed by the supervisor to the warehouse keeper, who then submits the proposal to the manager. If approved, the warehouse keeper makes a delivery request to send the equipment out of the site to a repairer. Once the repair is finished, the warehouse keeper will receive it back and put it in the warehouse.
3. Research Methodology
Based on the review of published literature in coordination with interviews of experienced experts in construction equipment management, a questionnaire that included 32 risk factors for equipment management was developed as shown in Table 1 (Alaghbari et al., 2007; Assaf & Al-Hejji, 2006; Chan & Kumaraswamy, 1997; Gurmu & Aibinu, 2017; Naskoudakis & Petroutsatou, 2016; Petroutsatou & Giannoulis, 2020; Ramanathan, Narayanan, & Idrus, 2012; Samee & Pongpeng, 2016). Each question in the questionnaire involved two aspects, namely, the likelihood and consequence of a risk factor (Sy, Likhitruangsilp, Onishi, & Nguyen, 2017). “Likelihood,” also known as the “frequency,” was denoted by the letter “L” while “consequence,” also known as the “impact,” was denoted by the letter “C” (Nguyen & Nguyen, 2020) (See Table 1).
Table 1: Risk factors for construction equipment management
Table 1: Continued
Research methods and techniques used in this study are shown in Table 2:
Table 2: Research methods and techniques
4. Results and Discussion
A total of 75 questionnaires were sent to construction equipment management experts. This study was aimed at two types of construction companies: (i) large-size ones (ii) and small-sized ones in Ho Chi Minh City. However, only 67 out of 75 questionnaires were considered satisfactory. Thus, the ratio between the risk factor variables (32 factors) and the number of observed samples (67) was 1:2.1 times, which was acceptable. The survey results showed that the number of respondents with experience of 3-5 years, 1-3 years, 5-7 years, 7-10 years, and over 10 years accounted for 34.3%, 19.4%, 20.9%, 11.9% and 13.4%, respectively which are nearly equal (see Table 3). Fifty-nine point seven percent of respondents had participated in constructing apartment buildings, high-rise office buildings, shopping centers, townhouses, and villa projects at the highest, followed by 29%, 11.9%, 6%, and 1.5%, respectively. And the number of respondents who had participated in the projects of above VND 200 billion and below
Table 3: Sample characteristics
Testing of the differentiation between two groups of large-sized (A) and small-sized companies (B) in terms of the likelihood and the consequence of risk factors was conducted. The results showed differences in the assessment of the two groups regarding five variables (R2.6), (R3.3), (R1.5), (R2.2), (R4.1), and (R1.4), as shown in Table 4. Therefore, these were no longer under consideration.
Table 4: Results of variables in association with testing between the two types of companies
Afterward, testing of the differentiation between the two groups of office staffs and site workers were carried out. The results showed the differences in the viewpoints of the assessment of only variable (R1.4) in terms of its consequence, so this variable was excluded (See Table 5).
Table 5: Results of T-test between office staffs and site workers
After the above six variables were excluded using a t-test, scale reliability testing was conducted. This was essential to develop and verify the scale since it assessed the quality of the questionnaire. The scale reliability was tested in terms of “likelihood” and “consequence.” First, no measurement concepts failed to reach Cronbach’s Alpha of 0.70 and a higher and corrected item-total correlation of greater than 0.3 for the consequence. Second, the first time the scale was tested for “likelihood,” most of Cronbach’s Alpha coefficients were greater than 0.7, except for factor (R3.1) “Unwilling satisfaction of owners’ requirements for equipment use” was < 0.3 (0.258), which meant it was, therefore, no longer considered. The secondary result showed that for each factor group, the Cronbach’s alpha coefficient, and the corrected item-total correlation were ≥ 0.7 and ≥ 0.3, respectively. Accordingly, the scale is reliable, and subsequent analyses were possible. Then, after the scale was tested to ensure its eligibility, the variables in “consequence” were further included in the EFA. The EFA aimed to reveal the structure of the scales in the study model. The final EFA results, exclusive of three factors (R2.10), (R2.8), and (R1.3), showed that KMO and the Bartlett test reached 0.790 (> 0.5) and Sig. = 0.000 (<0.05), respectively (see Table 6 and Table 7). It was concluded that the observed variables were interrelated.
Table 6: KMO and Bartlett’s test results
Table 7: Total Variance Explained
At the Eigenvalues value = 1.033 (>1), EFA extracted 6 from 23 observed variables with a total variance of 73.005% (>50%), and no new factors that were not included in the original model were formed. In the framework of EFA, observed variables had factor loads ranging from 0.612 to 0.887 (i.e., greater than 0.5). Thus, after the third EFA, all of these 23 observed variables met the EFA criteria, so no variables were excluded at this stage. Details on the third EFA are presented in Table 8 below.
Table 8: Results of the third EFA
The new structure generated from the EFA (with 23 factors) for “consequence” was adopted to conduct the CFA on the “likelihood” data which had been examined in terms of differentiation and reliability. The adjustment results of the covariance relationship between the errors of observed variables through MI (Modification Indices) showed that the chi-square/df=1.318 0.9, RMSEA=0.069 < 0.8, and the standardized factor weights of observed variables against those of latent variables were greater than 0.5. These indicators all met the applicable conditions, so it was concluded that the measurement model was consistent with the collected data. The results of the critical CFA tests are shown in Figure 2.
Based on the above tests, this latest structure included factors that were eligible for further analysis in terms of reliability, convergence, and differentiation. The results obtained served as the basis for the following conclusions on the factors: (i) Factors have not only a high likelihood but also a significant consequence for equipment management. The risk score was equal to the product of the multiplication of means; and (ii) The order of a risk factor group’s consequences for equipment management is calculated using the factor loading-based mean of the group. The summarized results are shown in Table 9:
Table 9: Summary of results
Regarding likelihood (L), the results showed that the five most frequent factors belonged to group 2 (Managementrelated risk) and group 6 (Site condition-related and external risks), including (R2.1), (R2.3), (R2.9), (R6.1) and (R2.5). Regarding the consequence (C), the results showed that five risk factors having the most tremendous consequences for equipment management to which construction companies need to pay attention were (R2.1), (R1.1), (R2.9), (R2.7) and (R4.3), which were included in group 1 (Site organizationrelated risks) and group 2 (Management-related risks). In general, the results showed that the five most important risk factors in equipment management, to which construction companies should pay attention, were (R2.1), (R2.9), (R1.1), (R2.7) and (R2.3), and the factor group with the most significant consequence for equipment management as well as others was group 2 “Management-related risks.” The five risks factors discussed in further detail below to facilitate the recommendations of relevant solutions.
a) “Insufficient budget for equipment purchase or hire” (R2.1) is the most significant risk in the equipment management of construction companies (12.349). Indeed, unsound corporate finances, in reality, is a frequent problem. Failure of project-involved plans is inevitable if the financial situation is not sound. It adversely affects not only the execution plans of a project but also equipment purchases or hiring plans. This is particularly true in the construction sector, especially for high-value equipment such as tower cranes and hoists. Moreover, unsound finance, accompanied by inadequate quality equipment from suppliers, results in serious financial loss. It often takes much time to repair or change poor quality equipment, which disturbs equipment management in construction projects. In short, to cope with the financial risks as well as to diminish the initial financial burden on companies and to reduce operating costs of equipment, construction companies can (i) buy used equipment at a lower price but with advanced functionality or technology; (ii) hire or rent equipment out of the regular use to avoid obsolescence; or (iii) purchase new or used equipment in light of the onhand budget. In particular, the option of “hiring or renting equipment” has some advantages: (i) low initial investment; (ii) good upgradability to remove outdated equipment; and (iii) less concern about damage or loss of value.
Figure 1: Results of factor analysis to confirm standardized CFA
b) “Inadequate control of equipment in use” (R2.9) was the second most important factor. Construction projects require diverse types and large quantities of equipment. Therefore, it is difficult to effectively manage without tight control. On the other hand, managers or engineers at construction sites tend to pay more attention to the quality and progress of projects rather than the quality and operation of equipment. Besides, to ensure the proper control following the given procedure, some companies require that all activities from the projects be approved by them, which is another obstacle to meeting demand at the sites. To strengthen the control over equipment, construction companies should use a conventional block diagram model or apply new algorithms such as artificial intelligence and genetic algorithms to optimize the operating time and location of equipment (Haidar, Naoum, Howes, & Tah, 1999; Long, Tran, & Nguyen, 2019; Ramakrishnan, Shabbir, Kassim, Nguyen, & Mavaluru, 2020).
c) The out-of-schedule usage period of equipment” (R1.1) was the third most important factor. It meant that the management for out-of-schedule implementation faced many difficulties because an essential feature of construction equipment is turnover, which can fail and affect the progress of any project if the given plans cannot be met. Undoubtedly, a construction company should establish the progress of any of its projects under CPM and find its critical path (Lambert & Cooper, 2000). Then, focusing on solving one or more job sequences throughout the project that are important and critical is necessary.
d) “Vague and intermittent exchange of project information and plans between sites and companies” (R2.7) is also an important factor that has a significant impact on the equipment management of companies. The demand for equipment in a project must be approved by a relevant construction company (which, at its discretion, selects the new purchase, rent, or transfer of equipment). Therefore, the vague and intermittent communication between projects or sites and companies will affect the progress and form of equipment supply. This has a significant influence on equipment management in construction projects as well as in the companies. To cope with this risk, construction companies should: (i) take advantage of the management information system software to make the communication simple, fast, and professional; (ii) make precise and accurate reports and status reports on equipment on a daily or weekly basis; and (iii) adjust the implementation schedule of the projects in case of any unexpected failures of equipment.
e) “Insufficient knowledge about equipment in use” (R2.3) is of equal importance. Currently, there are a number of types of equipment, and the technology of the equipment is so advanced and sophisticated that companies have not used it before (Lee & Xuan, 2019; Li et al., 2020). As a result, inadequate knowledge about the equipment in use becomes a major hurdle. To get rid of this problem, the companies should work in coordination with equipment sellers to organize training sessions under the instruction of the companies’ equipment management department or experienced equipment management experts. Additionally, due to the distinctive features of Vietnam as a country, (Unfavorable equipment transportation time due to regulations on traffic timeframe) (R6.1) is also quite important. The reason is that the majority of respondents work at projects in Ho Chi Minh City, the largest city of Vietnam, where traffic jams frequently and inevitably occur. Therefore, equipment transportation in the prescribed traffic hours or on prescribed traffic routes can have a significant impact on how long it takes to get to the site, which sometimes takes even a whole day for the prescribed transportation.
5. Conclusions
The performance of a project is dependent on the method and procedure of resource management, especially equipment management. Each construction company, regardless of whether it is large, medium, or small-sized, sets up its equipment management procedure. However, these equipment management procedures often are not interconnected or are not an optimal solution, so it is impossible to take the maximum advantage of the features of a particular piece of equipment, and this has a direct influence on the profitability of the project, especially in the case of high-rise building projects. With the construction companies’ desire to respond to risks and difficulties in equipment management and minimize their damages, this study has found 32 most influential factors that reduce the effectiveness of equipment management in Ho Chi Minh City, Vietnam. It also has proposed solutions to the most significant risks. These influential factors fell into six main groups: i) site organization-related risks; (ii) managementrelated risks; (iii) owner-related risks; (iv) supplier-related risks; (v) legal risks; and (vi) site condition and related external risks. In particular, group 2 (management-related factors) contributed to the most significant problems for equipment management as well as others.
Also, the study results illustrated five risk factors that have a significant influence on and a high likelihood in equipment management: (i) insufficient budget for equipment purchase or hire; (ii) inadequate control of equipment in use; (iii) use of equipment out-of-schedule; (iv) vague exchanges of project information and plans between sites and companies; and (v) insufficient knowledge about the equipment being used. The author offers the following recommendations based on the results of this study: (i) expand the study scope, sampling scale, and the number of samples to obtain more accurate results; (ii) study and propose an equipment management process that is most appropriate under the conditions in Vietnam; (iii) require that persuasions and proofs are obtained so that the proposed solutions are effective for equipment management; (iv) Based on the findings of the influence factors on equipment management, require that there needs to be an emphasis on equipment plan management, equipment control, and the knowledge about equipment in use; and (v) Further, carry out studies on equipment management in combination with the progress of companies’ in-process projects. This would make the most of the equipment turnover and give the highest benefit to company owners.
References
- Alaghbari, W., Razali, A. Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206. https://doi.org/10.1108/09699980710731308
- Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-357. https://doi.org/10.1016/j.ijproman.2005.11.010
- Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), 55-63. https://doi.org/10.1016/S0263-7863(96)00039-7
- Gurmu, A. T., & Aibinu, A. A. (2017). Construction Equipment Management Practices for Improving Labor Productivity in Multistory Building Construction Projects. Journal of Construction Engineering and Management, 143(10). https://doi.org/10.1061/(ASCE)CO.1943-7862.0001384
- Haidar, A., Naoum, S., Howes, R., & Tah, J. (1999). Genetic algorithms application and testing for equipment selection. Journal of Construction Engineering and Management, 125(1), 32-38. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:1(32)
- Lambert, D. M., & Cooper, M. C. (2000). Issues in supply chain management. Industrial Marketing Management, 29(1), 65-83. https://doi.org/10.1016/S0019-8501(99)00113-3
- Lee, J. W., & Xuan, Y. (2019). Effects of technology and innovation management and total factor productivity on the economic growth of China. Journal of Asian Finance, Economics and Business, 6(2), 63-73. https://doi.org/10.13106/jafeb.2019.vol6.no2.63
- Li, J., Li, H., Umer, W., Wang, H., Xing, X., Zhao, S., & Hou, J. (2020). Identification and classification of construction equipment operators' mental fatigue using wearable eyetracking technology. Automation in Construction, 109. https://doi.org/10.1016/j.autcon.2019.103000
- Long, L. D., Tran, D. H., & Nguyen, P. T. (2019). Hybrid multiple objective evolutionary algorithms for optimising multi-mode time, cost and risk trade-off problem. International Journal of Computer Applications in Technology, 60(3), 203-214. https://doi.org/10.1504/IJCAT.2019.100299
- Luong, D. L., Tran, D. H., & Nguyen, P. T. (2018). Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. International Journal of Construction Management. https://doi.org/10.1080/15623599.2018.1526630
- Naskoudakis, I., & Petroutsatou, K. (2016). A Thematic Review of Main Researches on Construction Equipment over the Recent Years. Paper presented at the Procedia Engineering.
- Nguyen, H. M., & Bui, N. H. (2020a). Energy consumption - Economic growth nexus in vietnam: An ARDL approach with a structural break. Journal of Asian Finance, Economics and Business, 7(1), 101-110. https://doi.org/10.13106/jafeb.2020.vol7.no1.101
- Nguyen, H. M., & Bui, N. H. (2020b). Revisiting the relationship between energy consumption and economic growth nexus in Vietnam: new evidence by asymmetric ARDL cointegration. Applied Economics Letters, 1-7. doi:10.1080/13504851.2020.1789543
- Nguyen, H. M., Dang, L. A. T., & Ngo, T. T. (2019). The effect of local foods on tourists' recommendations and revisit intentions: The case in Ho Chi Minh City, Vietnam. Journal of Asian Finance, Economics and Business, 6(3), 215-223. https://doi.org/10.13106/jafeb.2019.vol6.no3.215
- Nguyen, P. T., & Nguyen, C. P. (2020). Risk Management in Engineering and Construction: A Case Study in Design-Build Projects in Vietnam. Engineering, Technology & Applied Science Research, 10(1), 5237-5241. https://doi.org/10.48084/etasr.3286
- Nguyen, P. T., & Nguyen, Q. L. H. T. T. (2020). Critical Factors Affecting Construction Price Index: An Integrated Fuzzy Logic and Analytical Hierarchy Process. Journal of Asian Finance, Economics and Business, 7(8), 197-204. https://doi.org/10.13106/jafeb.2020.vol7.no8.197
- Nugraha, A., & Putranto, L. (2019). The effect of heavy equipment management on the performance of the construction project and the construction company. Paper presented at the IOP Conference Series. Materials Science and Engineering.
- Petroutsatou, K., & Giannoulis, P. (2020). Analysis of construction machinery market: the case of Greece. International Journal of Construction Management. https://doi.org/10.1080/15623599.2020.1741491
- Pham, H. C., Dao, N. N., Cho, S., Nguyen, P. T., & Pham-Hang, A. T. (2019). Construction Hazard Investigation Leveraging Object Anatomization on an Augmented Photoreality Platform. Applied Sciences, 9(21), 4477. https://doi.org/10.3390/app9214477
- Prasertrungruang, T., & Hadikusumo, B. (2009). Study of factors influencing the efficient management and downtime consequences of highway construction equipment in Thailand. Journal of Construction Engineering and Management, 135(1), 2-11. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:1(2)
- Prasertrungruang, T., & Hadikusumo, B. H. W. (2007). Heavy equipment management practices and problems in Thai highway contractors. Engineering, Construction and Architectural Management, 14(3), 228-241. https://doi.org/10.1108/09699980710744881
- Ramakrishnan, J., Shabbir, M. S., Kassim, N. M., Nguyen, P. T., & Mavaluru, D. (2020). A comprehensive and systematic review of the network virtualization techniques in the IoT. International Journal of Communication Systems, 33(7), 01-19. https://doi.org/10.1002/dac.4331
- Ramanathan, C., Narayanan, S., & Idrus, A. B. (2012). Construction delays causing risks on time and cost-a critical review. Construction Economics and Building, 12(1), 37-57. https://doi.org/10.5130/AJCEB.v12i1.2330
- Randunupura, S. N., & Hadiwattege, C. (2013). Plant and equipment management to minimize delays in road construction projects. Socio-Economic Sustainability in Construction, 14-15. https://www.irbnet.de/daten/iconda/CIB_DC26728.pdf
- Samee, K., & Pongpeng, J. (2016). Structural equation model for construction equipment management affecting project and corporate performance. KSCE Journal of Civil Engineering, 20(5), 1642-1656. https://doi.org/10.1007/s12205-015-0717-1
- Schaufelberger, J. E., & Migliaccio, G. C. (2019). Construction equipment management. London, UK: Routledge.
- Sy, D. T., Likhitruangsilp, V., Onishi, M., & Nguyen, P. T. (2017). Different perceptions of concern factors for strategic investment of the private sector in public-private partnership transportation projects. ASEAN Engineering Journal, 7(2), 66-86. https://doi.org/10.11113/aej.v7.15493
- Sy, D. T., Likhitruangsilp, V., Onishi, M., & Nguyen, P. T. (2017). Impacts of risk factors on the performance of public-private partnership transportation projects in Vietnam. ASEAN Engineering Journal, 7(2), 30-52. https://doi.org/10.11113/aej.v7.15520
- Tatari, O., & Skibniewski, M. (2006). Integrated agent-based construction equipment management: Conceptual design. Journal of Civil Engineering and Management, 12(3), 231-236. https://doi.org/10.3846/13923730.2006.9636397
- Vu, T. Q., Pham, C. P., Nguyen, T. A., Nguyen, P. T., Phan, P. T. & Nguyen, Q. L. H. T. T. (2020). Factors Influencing Cost Overruns in Construction Projects of International Contractors in Vietnam. Journal of Asian Finance, Economics and Business, 7(9), 389-400. https://doi.org/10.13106/jafeb.2020.vol7.no9.389
- Yeo, K. T., & Ning, J. (2006). Managing uncertainty in major equipment procurement in engineering projects. European Journal of Operational Research, 171(1), 123-134. https://doi.org/10.1016/j.ejor.2004.06.036
Cited by
- Exploring Critical Risk Factors of Office Building Projects vol.8, pp.2, 2020, https://doi.org/10.13106/jafeb.2021.vol8.no2.0309
- Critical Factors of Subcontractor Evaluation and Selection: A Case Study in Vietnam vol.8, pp.3, 2021, https://doi.org/10.13106/jafeb.2021.vol8.no3.0297