Analysis of Major Management Factors Affecting Crew Productivity in Road Bridge Construction Site Using IPA

IPA를 이용한 도로교량 골조공사의 작업조 생산성 관리요인의 중요도 및 실행도 분석

  • Huh, Young-Ki (Department of Architectural Engineering, Pusan National University) ;
  • Lee, Sang-Ho (Department of Architectural Engineering, Pusan National University)
  • Received : 2018.12.17
  • Accepted : 2018.12.28
  • Published : 2019.05.31

Abstract

Crew productivity in the construction industry is an important indicator of soundness and efficiency of work process, since all works in a site are conducted as groups of people. A survey was conducted in order to reveal importance and performance of major management factors affecting crew productivity in road bridge construction site using IPA. As a result of the analysis, it was found that 'Construction equipment' and 'Human resource related' factors among five major-categories are most important but with low performance. Furthermore, from another analysis with 27 factors of sub-categories, it is revealed that factors needed sustained attention are four, namely 'Just-in-time machinery delivery', 'Formation of a crew members', 'Skill of workers', and 'Site control and management', whereas those needed much more improvement are five, such as 'Machinery performance', 'Clearity of Design', 'Clearity of shop drawing', 'Timing of work instruction and approval', and 'Clearity of work instruction'. Findings from this study will enable road agencies as well as road construction experts to enhance crew productivity in a site.

건설현장의 생산성은 견실성 및 생산활동의 효율성 평가을 위한 매우 중요한 지표이며, 건설 현장작업은 모두 작업조를 중심으로 수행됨으로 작업조의 생산성 관리는 특히 중요하다. 문헌연구 및 전문가 인터뷰를 통해 도출된 27개의 관리요인들로 설문조사를 실시하였으며 32부를 회수하여 분석하였다. 대분류항목의 실행도 및 중요도를 분석한 결과, '장비'와 '건설인력' 항목이 도로교량 공사의 작업조 생산성에 매우 중요한 것으로 나타났으며, 실행도는 중요도에 비해 비교적 미비한 것으로 밝혀졌다. 또한 소분류 항목 27개를 분석한 결과, 지속적인 관심을 가져야 하는 항목으로는 '적기의 장비조달', '효율적 작업조 구성', '작업자의 숙련도', '현장통제 및 감독능력'이 중요도에 비해 실행도가 낮음으로 보다 더 향상시킬 필요가 있는 관리 요인들로는 '장비 가동성능', '설계도서의 정확성', '시공상세도의 정확성', '작업지시 및 승인 시기', '작업지시의 정확성' 등인 것으로 밝혀졌다. 본 연구의 결과는 앞으로 도로공사의 구조체 공사에서 작업조 생산성 향상을 위해 유용하게 사용될 수 있을 것으로 사료된다.

Keywords

GGRHC4_2019_v20n3_39_f0001.png 이미지

Fig. 1. Research methodology

GGRHC4_2019_v20n3_39_f0002.png 이미지

Fig. 2. IPA Result of main category factors

GGRHC4_2019_v20n3_39_f0003.png 이미지

Fig. 3. IPA result of main contractors

GGRHC4_2019_v20n3_39_f0004.png 이미지

Fig. 4. IPA result of sub-contractors

GGRHC4_2019_v20n3_39_f0005.png 이미지

Fig. 5. IPA results of the sub-category factors

Table 1. Major mgmt. factors for time management of RC works

GGRHC4_2019_v20n3_39_t0001.png 이미지

Table 2. Factors decreasing construction productivity in housing project

GGRHC4_2019_v20n3_39_t0002.png 이미지

Table 3. Factors decreasing construction productivity in building project

GGRHC4_2019_v20n3_39_t0003.png 이미지

Table 4. Management factors of crew-productivity

GGRHC4_2019_v20n3_39_t0004.png 이미지

Table 5. General information of the survey respondents

GGRHC4_2019_v20n3_39_t0005.png 이미지

Table 6. IPA results of sub-category factors

GGRHC4_2019_v20n3_39_t0007.png 이미지

References

  1. Ahn, S.H., and Yu, J.H. (2009). "Management of work efficiency and work condition in construction site." Journal of Excellent Graduation Thesis of the Architectural Institute of Korea, AIK, 5, pp. 381-384.
  2. Baek, K.G., Kang, S.H., Baek H.G., and Seo J.W. (2009). "A Study on the factors of haul routes planning for earthmoving." Journal of Conference Korea Institute of Construction Engineering and Management, KICEM. pp. 899-903.
  3. H. Randolph Thomas (1991). "Labor productivity and work sampling: the bottom line." Journal of Construction Engineering and Management, ASCE, 117(3), pp. 423-444. https://doi.org/10.1061/(ASCE)0733-9364(1991)117:3(423)
  4. Kim, B.S., and Kwon, S.H. (2009). "The conceptual cost estimate model on preliminary design phase for RC rahmen bridge." Korean Journal of Construction Engineering and Management, KICEM, 10(2), pp. 111-120.
  5. Kim, J.W., Kim, Y.S., Kim, Y.S., and Kim, S.B. (2008). "WBS development for acquisition and analysis of public housing productivity data." Korean Journal of Construction Engineering and Management, KICEM, 9(5), pp. 86-94.
  6. Lee, D.W., Cho, H.J., Lee, K.J., and Kim, N.S. (2011). "Productivity analysis on the standard quantity-per-unit costing method and work crew combination method : focused on non-vibration mass excavation method." Journal of Korean Society of Civil Engineers, KSCE, 31(3), pp. 457-468.
  7. Lee, K.J., and Kim, Y.S. (2010). "An importance analysis for the major schedule management factors classified by construction participants in high-rise building reinforced concrete work." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 26(12), pp. 185-192.
  8. Kim, J.Y., Choi, J.H., and Lee, S.H. (2011). "Factors affecting the losses of domestic construction productivity and strategies for avoiding them." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 27(2), pp. 113-124.
  9. Lee, S.B., and Pyo, Y.M. (2007). "A study on the analysis of factors decreasing construction labor-productivity using AHP method." Journal of the Architectural Institute of Korea Structure & Construction, AIKRA, 9(1), pp. 179-187.
  10. Lee, S.H. (2004). "The measurement and analysis techniques of total project productivity on transportation projects." Journal of Conference Korea Institute of Construction Engineering and Management, KICEM. pp. 95-100.
  11. Lee, S.H., and Hong, S.H. (2005). "An evaluation method for the impact of disruptive events on road construction projects using total project productivity." Journal of Korean Society of Civil Engineers, KSCE, 25(5), pp. 747-756.
  12. O'Connor, James T., and Huh, Y.K. (2005). "Crew production rates for contract time estimation: bent footing, column, and cap of highway bridges." Journal of Construction Engineering and Management, ASCE, 131(9), pp. 1013-1020. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:9(1013)
  13. O'Connor, James T., and Huh, Y.K. (2006). "Crew production rates for contract time estimation: beam, erection, deck, and rail of highway bridges." Journal of Construction Engineering and Management, ASCE, 132(4), pp. 408-415. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:4(408)
  14. Ohn, S.W., Woo, S.K., and Kim, O.K. (2007). "An application of simulation method to planning of road pavement operation." Korean Journal of Construction Engineering and Management, KICEM, 8(1), pp. 124-131.
  15. Park, S. M., Park, T. E., and Kim, H. K. (2013). "Checklist for the application of concurrent engineering in bridge construction." Korean Journal of Construction Engineering and Management, KICEM, 14(1), pp. 3-11. https://doi.org/10.6106/KJCEM.2013.14.1.003
  16. Seo, J.H., and Park, H.K. (2011). "A study on the development of standard of estimate of representative construction type of road project." Journal of Conference Korea Institute of Construction Engineering and Management. KICEM. pp. 97-98.
  17. Son, C.B., and Lee, D.C. (2002). "An analysis on the factors decreasing productivity of building construction." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 18(12), pp. 125-132.
  18. Yoo, D.Y., Park, H.K., and Lim, H.M. (2013). "A study on the development of work-crew based daily-productivity for representative B.O.Q item in river conservation project." Journal of the Korean Society of Civil Engineers, KSCE, 33(6), pp. 2519-2528. https://doi.org/10.12652/Ksce.2013.33.6.2519
  19. Yoon, B.S., Yu, J.H., and Kim, C.D. (2010). "An analysis on the influence of work management type on work condition." Korean Journal of Construction Engineering and Management, KICEM, 11(5), pp. 76-84.