A Study on the Decay Effect of Ground Vibration based on the Number of PLHBM Holes in Gneiss Area

편마암지역에서 선대구경 수평보링 공수적용에 따른 지반진동 감쇠효과 연구

  • Received : 2016.04.27
  • Accepted : 2016.05.27
  • Published : 2016.06.30

Abstract

In this study, the field tests were performed on V-cut, PLHBM 1 hole, PLHBM 2 hole in gneiss area in order to compare the effects of the vibration decay of a tunnel cut-hole according to the number of PLHBM holes with scaled distance. Based on the prediction equation of blasting vibration from the result of the tests, the decay rate of vibration were confirmed 21.8~61.1% using PLHBM 1 hole, 35.7~79.3% using PLHBM 2 hole for scaled distance within $10{\sim}100m/kg^{1/2}$ on the basis of V-cut PPV. As the scaled distance was increased, the effect of vibration decay was decreased. The effect of vibration decay of cut-hole for intial PLHBM 1~2 hole was significantly high.

본 논문에서는 PLHBM의 환산 거리별 공수에 따른 터널 심발공의 진동감쇠효과를 비교하기 위해 편마암지역에서 V-cut, PLHBM 1공, PLHBM 2공에 대한 현장실험을 수행하였다. 시험결과 얻어진 발파진동추정식을 근거로 하였을 때 진동 감쇠율은 V-cut의 PPV를 기준으로 환산거리 $10{\sim}100m/kg^{1/2}$의 범위에서 PLHBM 1공 적용 시 21.8~61.1%, 2공 적용시 35.7~79.3%로 나타났다. 진동감쇠효과는 환산거리가 증가할수록 작아지는 경향을 보였으며, PLHBM 1~2공은 심발공의 진동감쇠효과가 높은 것으로 나타났다.

Keywords

References

  1. 건설교통부, 2006, 도로공사 노천발파 설계.시공 지침, pp. 100.
  2. 김우철 외, 1988, 현대통계학, 영지문화사, 서울, pp. 237.
  3. 김재극, 1992, 산업화약과 발파공학, 서울대학교 출판부, 서울, pp. 373.
  4. 김창섭, 백상현, 백종현, 원아람, 유정렬, 최형빈, 한동훈, 2012, 선대구경 공법을 적용한 터널의 진동.소음저감 사례, 대한화약발파공학회 추계학술발표회 논문집, 서울, pp. 104-117.
  5. 백종현, 김창섭, 백상현, 원아람, 한동훈, 2012, 선대구경 수평보링 발파공법(PLHBM)의 설계 연구, 화약.발파(대한화약발파공학회지), 제30권, 제2호, pp. 66-76.
  6. 이정인, 신일재, 조혁기 2000, 선대구경 수평 보링공을 이용한 터널발파공법에 관한 연구, 서울대학교 공학연구소, pp. 1-44.
  7. 우준명, 2003, 터널 심발발파시 대구경 무장약공의 효과에 관한 연구, 석사학위 논문, 서울산업대학교, 서울.
  8. 양형식 역, 1992, 발파진동학, 구미서관, 서울, pp. 20.
  9. 한국철도시설공단, 2014, 지반조사보고서, pp. 1.