An Analysis of the Duration of the Construction Document Phase of Large Public Building Projects Delivered by the Total Solution Service from 2009 to 2014

공공기관 발주 대형건축공사 실시설계 기간에 대한 분석 및 개선방안 -2009년부터 2014년까지 공공발주 맞춤형 서비스 프로젝트를 중심으로 -

  • Jung, Wooyoung (Department of Architectural Engineering, Yonsei University) ;
  • Lee, Taewon (Department of Architectural Engineering, Yonsei University) ;
  • Rhee, Pung-wook (Public Procurement Service in Korea) ;
  • Lee, Ghang (Department of Architectural Engineering, Yonsei University)
  • Received : 2015.03.20
  • Accepted : 2015.06.09
  • Published : 2015.07.31

Abstract

This paper analyzes the duration of the construction document (CD) phase of 42 large public building projects delivered by the total solution service of Public Procurement Services in Korea from 2009 to 2014. The quality of construction documents significantly affects the quality of construction and facility management. Thus, securing appropriate time for the CD phase during project planning is important for the quality of a project. Currently, the duration of the CD phase is planned based on the construction costs of a project following a notice of the Ministry of Land, Infrastructure and Transport. However, our analysis results showed that the correlation between the actual duration of the CD phase and construction costs is very weak. The actual CD phase takes 1.33-1.79 times longer than the planned duration. The practitioners who were interviewed, were already aware that the correlation between the duration of the CD phase and the construction costs is weak. They identified the complexity of the project, the extent of the design changes, project type, client characteristics, and others as more influential factors on the CD phase than the construction costs. To improve the quality of CDs, a new guideline for determining an adequate CD phase duration should be studied and developed.

실시설계도서의 품질은 시공, 그리고 운영 및 관리단계에도 큰 영향을 미친다. 그리고 적절한 실시설계기간의 확보는 실시설계도서의 품질을 위해 중요한 요소이다. 따라서 이 연구는 2009년부터 2014년까지 조달청 맞춤형 서비스를 통해 발주된 총 42개의 건설프로젝트의 실시설계단계의 기간을 분석하였다. 분석에 의하면, 실제 실시설계기간은 계획 실시설계기간보다 1.33배에서 1.79배가 소요되었다. 계획 실시설계기간은 건설교통부 제2000-235호에서 고시하고 있는 방식대로 공사금액에 의해 산정하고 있었지만, 실제 실시설계기간은 공사금액과 아주 낮은 상관관계를 보였다. 이 결과를 토대로 실무자들과 인터뷰를 진행하였고, 공사금액이 실시설계기간과 낮은 상관관계를 보인 것은 이들에게 아주 잘 알려진 사실이었다. 그들은 공사의 복잡도, 설계변경의 정도, 그리고 발주처의 성향에 따라서 실시설계기간이 크게 좌우된다는 점을 언급하였다. 따라서, 실시설계도서의 품질을 향상시키기 위해서는 다양한 요소들을 실시설계기간 산정에 적용하여 적절한 기간을 산정해야하며, 고품질의 실시설계도서는 건설산업에 긍정적 효과를 불러일으킬 것으로 보인다.

Keywords

References

  1. Kim, H. I. (1998). "The causes of design change and improvement countermeasure for public construction", The National Assembly of the Republic of Korea, pp. 23-27.
  2. Kim, J. H. (2008). "The Constitution Plan of Design Error Management System in Construction Projects.", Journal of the Regional Association of Architectural Institute of Korea, 10(3), pp. 231-239.
  3. Lee, B. K., Jung, T. H., Park, H. J., and Koo, K. J. (2010). "Checklists for Construction Drawings of Office Buildings based on Working Drawing Analysis", Korean journal of Construction Engineering and Management, KICEM, 11(4), pp. 3-11. https://doi.org/10.6106/KJCEM.2010.11.4.3
  4. Lee, J. S. (2006). "Impacts of Pre-construction Design Quality on Construction Durations and Costs.", Journal of the Architectural Institute of Korea Structure & Construction, Architectural Institute of Korea, 22(5), pp. 219-226.
  5. Lee, J. Y., Kim, D. H., and Seo, Y. S. (2005). "A Study on the Factor of Change Order in the public construction Project.", Architectural Institute of Korea, 25, pp. 523-526.
  6. Lee, M. J., Park, B. J., and Im, K. S. (2008). "A Study on the Estimation of Change Orders Impact for the Public Construction", Journal of the Korean Society of Civil Engineers D, Korean Society of Civil Engineers, 28(3D), pp. 363-369.
  7. Lee, N. J., Son, M. J., Kim, J. H., Ji, S. M., and Hyun, C. T. (2011). "Development of Construction Documents Checklists for Preventing Error of Design Process in Public Construction Projects", Journal of the Architectural Institute of Korea Structure & Construction, Architectural Institute of Korea, 27(2), pp. 149-158.
  8. Love, P., Edwards, D., Smith, J., and Walker, D. (2009). "Divergence or Congruence? A Path Model of Rework for Building and Civil Engineering Projects", Journal of Performance of Constructed Facilities, 23(6), pp. 480-488. https://doi.org/10.1061/(ASCE)CF.1943-5509.0000054
  9. Ministry of Construction and Transportation (1999). Efficiency and Comprehensive plan for public construction projects, Korea.
  10. Ministry of Land, Infrastructure and Transport (2014). Manual for Deliberation and Evaluation of Technology Proposals on Design Development and Construction Documents, 2014-02, Sejong, Korea.
  11. Ministry of Land, Transport and Maritime Affairs (2010). Manual for Design Deliberation and Evaluation of Turn-key and Alternative Bids, 2010-03, Sejong, Korea.
  12. Ministry of Land, Transport and Maritime Affairs (2012). Registered Architects' Workscope and Estimation Guideline for Public Projects, 2012-08, Sejong, Korea.
  13. Presidential Decree Act No. 22637 (2011). Act on Contracts to Which the state is a Party, Enforcement decree Article 102(Choice for determination of successful bidder for construction document & technology proposal and etc.).
  14. Presidential Decree Act No. 22660 (2011). Act on Contracts to Which the state is a Party, Enforcement decree Article 85-2 (Choice for determination of qualified persons or successful bidder for construction document).
  15. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 85 (Tending procedures for designbuild and etc.).
  16. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 87 (Determination of successful bidder for design-build).
  17. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 103 (Tending procedures for construction document & technology proposal).
  18. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 104 (Determination of successful bidder for construction document & technology proposal).
  19. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 105 (Tending procedures for design development & technology proposal).
  20. Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 106 (Determination of successful bidder for design development & technology proposal).
  21. Public Procurement Service (2007). "Construction Delivery Handbook", Public Procurement Service, 2007-12, Daejeon, Korea.
  22. Shin, K. C., Park, H. K., Lee, Y. H., Kwak, J. H. (2011). "Development of the Design Management Guidelines to Enhance the Capability of Public Clients", Korean journal of Construction Engineering and Management, KICEM, 12(2), pp. 143-151. https://doi.org/10.6106/KJCEM.2011.12.2.143

Cited by

  1. Bim Strategy Plan through Domestic Construction Companies BIM Project Case Analysis - focused on the BIM USE of the project from 2009 to 2015 - vol.6, pp.2, 2016, https://doi.org/10.13161/kibim.2016.6.2.001