Development of Start·Stop Control System at Water Turbine Generator for Tidal Power Plant

조력발전소를 위한 수차발전기의 기동·정지 제어시스템 개발

  • Received : 2014.03.18
  • Accepted : 2014.04.22
  • Published : 2014.06.30

Abstract

Recently, tidal power generation has gained much attention. South Korea's tidal power generation systems were imported from abroad by turnkey type and have being operated. Therefore, for efficient operation and technological independence of a tidal power system, development of core technology is required. This paper deals with the start stop control system of water turbine generator in the tidal power plant, as one of our development project results. Using the SCADA system, the status and operations of water turbine generator in the tidal power plant, as well as simulation for calculation of maximum power were carried out. A small model type of start stop control device was also developed. In addition, the control system in Sihwa tidal power plant was modeled, and the results obtained by the dynamic simulation were given in graphics by 2D simulator.

Keywords

References

  1. Min-Hwan Oh, Chul-Won Park, Byong-Og Cho, Yoon-Sang Kim et al., "Development & demonstration of start.stop control system at turbine-generator", Ministry of Knowledge Economy Technology Innovation Program, 1st year report, pp. 1-197, 2012. 10.
  2. Min-Hwan Oh, Jae-Hoon Kim, Kwang-Chul Shin, "Introduction of Joint control system for the Shiwa Tidal Power Plant Construction", KIEE summer conference, Vol. D, pp. 2222-2223, 2008.
  3. Kyu-Ho Kim et al., "Status and technology of tidal power", Proceedings of the KIEE, Vol. 55, No. 8, pp. 32-37, 2006. 8.
  4. Min-Hwan Oh, "Optimum operating plan of tidal power", Small Hydro/Marine Energy International Joint Seminar, pp. 505-508, 2007.
  5. D.H. Kang et al.,"The design for automatic operation of Tidal power generation equipment", KIEE summer conference, pp. 2579-2581, 2005.
  6. Hyun-Han Kim, kwang-Ho Kim, Jong-Chan Jeong, Sung-Ho Park, Yeon-Ho Ok, Hyung-Chol Choi, "Tidal Power Station Excitation System for a Considering Wave Characteristic", KIEE summer conference, pp. 251-252, 2008. 7.
  7. Hyun-Han Kim, June-Kyou Kim, Yeon-Ho Ok, Jin-Geuk Nam, Hung-Chol Choi, Gwang-Yong Han, Kwang-Ho Kim, "The analysis of Governor Operation Characteristics of Tidal Power Station Considering Sea Condition", KIEE summer conference, pp. 1227-1228, 2010. 7.
  8. Jin-Geuk Nam, "Study on the Optimal Operating Model to Maximize the Electric Power Generation of the SIHWA Tidal Power Plant", Korea University of Technology and Education, Master's Thesis, pp. 1-52, 2009.
  9. Min-Hwan Oh, Hual-Soo Kim, Jae-Hoon Kim, Guy-Seok Song, "The Development of Model to Calculate Maximum Power for Tidal Power Plant Operation", The Korean Society for New and Renewable Energy 2006 spring conference, pp. 505-508, 2006.
  10. Kyu-Ho Kim, Kyung-Bin Song, Seok-Kee Kwon, Tae-Hoon Kim, "Generator Forecast for Intergrating Shihw Tidal Power into Power Systems", KIEE power system spring conference, pp. 375-377, 2006.
  11. Kyu-Ho Kim, Kyung-Bin Song, Sang-Bong Rhee, "Assessment of LMP on Energy Function", KIEE summer conference, pp. 64-65, 2010.
  12. Park Chul-Won, Ban Woo-Hyeon, Ahn Sang-Ji, Kim Yoon-Sang, "Review of generator control system for tidal power plant", KIEE power system spring conference, pp. 269-271, 2012. 5.
  13. Chul-Won Park, Woo-Hyun Ban, Yoon-Sang Kim, Min-Hwan Oh, Byung-Ok Cho, Sang-Ji Ahn, "Development of Water Turbine Generator System Modeling and Virtual Simulator for Tidal Power Plant", KIEE summer conference, pp. 910-911, 2012. 7.
  14. Sang-Ji Ahn,Yu-Hyeon Ban, Chul-Won Park, "Dynamic Characteristic Analysis of Water-Turbine Generator Control System of Sihwa Tidal Power Plant", KIEE Vol. 61P, No. 4, pp. 180-185, 2012. https://doi.org/10.5370/KIEEP.2012.61.4.180
  15. Jeon Jinhong, Cho Changhee, Kim Seulki, Ahn Jongbo, "Development of a Wind Turbine Simulator based on RTDS and MG set", KIEE summer conference, pp. 515-516, 2006. 7.
  16. Yu-Hyeon Ban, Byong-Og Cho, Minhwan Oh, Chulwon Park, "Development of Start-Stop Control System at Water Turbine-Generator in Tidal Power Plant", International Symposium on Green Energy Policy Innovation, Vol. 1, No. 1, Jan. 2013.
  17. PTS(Power Technologies Solution), "PSSE V33 EDUCATION", Siemens, pp. 32-37, 2011.