Abstract

This study performs modelling and simulation of permanent magnetic synchronous generator wind turbine by using Matlab & Simulink. In simulation, change of wind velocity, change of load, and voltage decrease of infinite bus are performed. Through such simulation, different with wiring system that there is only existing load, this study can confirm problems and voltage changing characteristics, which can occur in distributed electric power that load and electric power is mixed and operated, especially, in interconnecting with wind power generation.

본 연구는 Matlab & Simulink에서 영구자석 동기형 풍력발전기(Permanent Magnetic Synchronous Generator Wind Turbine)모델링과 시뮬레이션을 수행한다. 모의실험으로는 풍속의 변동, 부하의 변동, 그리고 무한모선의 전압강하가 수행되었다. 이러한 모의실험을 통해 기존의 부하만이 존재하는 배전계통과는 달리 부하와 전원이 혼재되어 운용되는 분산전원 특히 풍력발전 계통연계시 발생할 수 있는 문제점과 전압변동 특성을 확인할 수 있었다.

Keywords

References

  1. G. Hehenberger, "MULTIBRID technology: 5[MW] wind energy converter for offshore applications", World Wind Energy Conf. Germany 2002
  2. ENERCON GmbH, "Wind Turbine E-112. Available: http://www.enercon.de/en/_home.htm", Jan. 2006
  3. T. Senjyu, N. Sueyoshi, R. Kuninaka, K. Uezato, H. Fujita, and T. Funabashi, "Study on terminal voltage and power factor control of induction generator for wind power generation system", in Proc. Int. Conf. Power SystemTech., vol. 1, pp. 753–758, Nov. 2004,
  4. R. Pena, J. C. Clare, and G. M. Asher, "Doubly fed induction generator using back-to-back PWM converters and its application to variable speed wind-energygeneration", IEEE Elect. Power Appl, vol. 143, no. 3, pp. 231–241, Aug. 1996 https://doi.org/10.1049/ip-epa:19960288
  5. P. C. Krause, O. Wasynczuk, and S. D. Sudhoff, "Analysis of electric machinery and drive systems", John Wiley & Sons Inc, Jan, 2002
  6. T. Ackermann, "Wind Power In Power Systems", John Wiley & Sons Inc, 2002
  7. R. Doherty, E. Denny, and M. O’Malley, "System operation with a significant wind power penetration", in Proc. IEEE Power Engineering Summer Meeting, vol. 1, pp. 1002–1007, Jun. 2004 https://doi.org/10.1109/PES.2004.1372988
  8. T. Senjyu, T. Kinjo, H. Fujita, and Aichi, "Analysis of terminal voltage and output power control of wind turbine generator by series and parallel compensationusing SMES", in Proc. IEEE 35th Annu. Power Electronics Specialists Conf, vol. 6, pp. 4278–4284, Jun. 2004 https://doi.org/10.1109/PESC.2004.1354757
  9. I. Erlich and U. Bachmann, "Grid code requirements concerning connection and operation of wind turbines in Germany", in Proc. IEEE Power Engineering Soc. General Meeting, pp. 2230–2234, Jun. 2005,
  10. P. Kundur, "Power System Stability and Control", McGraw-Hill, 1994
  11. R. Doherty, E. Denny, and M. O’Malley, "System operation with a significant wind power penetration", in Proc. IEEE Power Engineering Summer Meeting, vol. 1, pp. 1002–1007, Jun. 2004 https://doi.org/10.1109/PES.2004.1372988
  12. N. Dizdarevic, M. Majstrovic, and S. Zutobradic, "Power quality in a distribution network after wind power plant connection", in Proc. IEEE Power Systems Conf. Expo., vol. 2, pp. 913–918, Oct. 2004

Cited by

  1. A Study on the Gain Scheduling Speed Controller of Permanent Magnet Synchronous Generators for MW-Class Direct-Driven Wind Turbine Systems vol.25, pp.8, 2011, https://doi.org/10.5207/JIEIE.2011.25.8.048