Abstract
Although several research efforts have been directed to fast-tracking to reduce the total delivery time, few researches have been studied on concurrent engineering in construction projects. The focus of fast-tracking is primarily on overlapping independent activity pairs. In comparison, the focus of concurrent engineering is on overlapping dependent activity pairs. Dependent activities are much harder to overlap successfully. This paper presents a simulation-based Concurrent Engineering methodology to optimize the overall duration of a set of design activities in a project by modelling key factors that determine the duration of individual activities and overlap between dependent activities. This methodology involves determining how much to overlap activities, how to decide which activities to overlap and the corresponding cost and time tradeoffs using a discrete event model solution. This simulation model, therefore, can be used as a reference on decision-making to define optimum point between time and cost.
동시공학 연구는 최근까지 국내에서 인식이 부족하여 잘 활용되지 못하였고 다만 패스트 트랙에 관한 연구가 활발히 진행되어 왔다. 그러나 본 연구는 기존의 패스트 트랙 방법에서 정량적인 분석과 논리적으로 증명 및 평가하는 연구가 미비하다고 판단하여, 상위 개념인 동시공학 방법을 분석하였다. 설계단계에서 정성적인 분석이 아닌 실제 예제를 통하여 정량적인 자료를 이용하여 각 공정별 중첩이 전체 프로젝트에 미치는 영향을 명확하게 보여주는 분석방법을 제시하였다. 시뮬레이션 기법을 이용한 정량적인 분석방법을 통하여 실제 분석 결과를 가지고 의사결정에 참고 자료로 활용이 가능하도록 하였다. 사례분석 결과 중첩 비율별 공기 비용 간의 관계를 알 수 있었고 중첩 비율별 값을 가지고 공기 비용간의 정량적인 분석을 통해 최적점을 제시함으로서 의사결정이 가능토록 하였다.