A Simulation Model for the Application of Concurrent Engineering to Design Phase in Construction

건설공사 설계단계에서의 동시공학 적용을 위한 시뮬레이션 모델

  • Published : 2009.05.31

Abstract

Although several research efforts have been directed to fast-tracking to reduce the total delivery time, few researches have been studied on concurrent engineering in construction projects. The focus of fast-tracking is primarily on overlapping independent activity pairs. In comparison, the focus of concurrent engineering is on overlapping dependent activity pairs. Dependent activities are much harder to overlap successfully. This paper presents a simulation-based Concurrent Engineering methodology to optimize the overall duration of a set of design activities in a project by modelling key factors that determine the duration of individual activities and overlap between dependent activities. This methodology involves determining how much to overlap activities, how to decide which activities to overlap and the corresponding cost and time tradeoffs using a discrete event model solution. This simulation model, therefore, can be used as a reference on decision-making to define optimum point between time and cost.

동시공학 연구는 최근까지 국내에서 인식이 부족하여 잘 활용되지 못하였고 다만 패스트 트랙에 관한 연구가 활발히 진행되어 왔다. 그러나 본 연구는 기존의 패스트 트랙 방법에서 정량적인 분석과 논리적으로 증명 및 평가하는 연구가 미비하다고 판단하여, 상위 개념인 동시공학 방법을 분석하였다. 설계단계에서 정성적인 분석이 아닌 실제 예제를 통하여 정량적인 자료를 이용하여 각 공정별 중첩이 전체 프로젝트에 미치는 영향을 명확하게 보여주는 분석방법을 제시하였다. 시뮬레이션 기법을 이용한 정량적인 분석방법을 통하여 실제 분석 결과를 가지고 의사결정에 참고 자료로 활용이 가능하도록 하였다. 사례분석 결과 중첩 비율별 공기 비용 간의 관계를 알 수 있었고 중첩 비율별 값을 가지고 공기 비용간의 정량적인 분석을 통해 최적점을 제시함으로서 의사결정이 가능토록 하였다.

Keywords

References

  1. 김기홍 (1992). 신회계이론, 창문각
  2. 김정훈, 구교진, 현창택 (2003). '설계시공 일괄방식 프로세스 성공모델에 관한 연구', 한국건설관리학회 논문집, 제4권 제3호, 119-127
  3. 남규현, 송성진 (2000). "동시공학 경영혁신 이론과 사례에 관한 연구", 대한건축학회 논문집 16권 12호, 183-194
  4. 변은정 외 (2005). '리모델링 공사에서 Fast Track 적용방안', 대한건축학회 학술발표대회 논문집, 25권 1호, 321-324
  5. 백승호 (1997). "시뮬레이션을 이용한 통계적 코스트 모델의 유효성 검증방법", 대한건축학회 학술발표대회 논문집, 17권 2호, 1511-1517
  6. 이국환 (2001). 동시공학기술, 기전연구사
  7. 최도승, 이재섭 (2007). '동시공학을 통한 공기단축 의사 결정 모델', 한국건설관리학회논문집, 제8권 제6호, 197-206
  8. 한미파슨스 (2006). Construction Management Best Practice, 기문당
  9. Barrie, D. S. and Paulson, Jr., B. C. (1992). Professional Construction Management, McGraw-Hill, Inc., New York, NY
  10. Blackburn, J. D., editor (1991). Time-Based Competition: The Next Battleground in American Manufacturing, Business One Irwin, Homewood, IL
  11. Bogus, S. M., Molenaar, K. R., and Diekmann, J. E. (2006). 'Concurrent Engineering Approach to Reducing Design Delivery Time', ASCE Journal of Construction Engineering and Management, 131(11), 1179-1185 https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1179)
  12. Clark, K. B., and Fujimoto, T. (1991). Product Development Performance: Strategy, Organization, and Management in the World Auto Industry, Harvard Business School Press, Boston, MA
  13. Eldin, N. N. (1997). 'Concurrent Engineering: A Schedule Reduction Tool.' ASCE Journal of Construction Engineering and Management, 123(3), 354-362 https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(354)
  14. Krishnan, V., Eppinger, S. D., and Whitney, D. E. (1997). 'A Model-Based Framework to Overlap Product Development Activities.' Management Science, 43(4), 437-451 https://doi.org/10.1287/mnsc.43.4.437
  15. Lee, J. S., Molenaar, K. R., Bogus, S. M., and Diekmann, J. E. (2006). 'An Activity Overlapping Algorithm for Construction', Joint International Conference on Computing and Decision Making in Civil and Building Engineering, Montreal, Canada, 3827-3836
  16. Maheswari, J. U., Varghese, K., and Sridharan, T. (2006). 'Application of Dependency Structure Matrix for Activity Sequencing in Concurrent Engineering Projects', ASCE Journal of Construction Engineering and Management, 132(5), 482-490 https://doi.org/10.1061/(ASCE)0733-9364(2006)132:5(482)
  17. Prasad, B. (1996). Concurrent Engineering Fundamentals: Integrated Product and Process Organization, Prentice Hall, Upper Saddle River, NJ