Application of CCPM to Construction Project

건설프로젝트에 CCPM의 적용

  • 김영 (부경대학교 대학원 건설관리공학과) ;
  • 이영대 (부경대학교 토목공학과) ;
  • 김옥수 (㈜성포건설) ;
  • 김성환 (㈜유신코퍼레이션) ;
  • 박혁 (울산광역시 중구청 건설도시국장)
  • Published : 2003.09.01

Abstract

The Theory of Constraints (TOC) is an approach and a philosophy that is used to develop specific management techniques. It was first popularized by the novel, The Coal, that applied the principles to operations management. Since 1997 it has found application in two areas within project management The first application is scheduling of a sing1e project to reduce project duration and simplify project control. there is a further application to allocate resources that are shared by concurrent project. It is the objective of this paper to explore the fundamentals of critical chain and to pursue an application of critical chain method to construction project by a case study.

제약이론은 특정한 관리기술을 개발하는데 사용되는 접근방법이며, 철학이다. 운영관리상에 적용되었던 소설 "The Goal"에 의해서 처음으로 널리 보급되었다. 1997이후로 프로젝트관리의 두 가지 영역에서 적용되어 왔으며, 그 첫 번째 적용은 단일프로젝트에 대한 공기단축과 프로젝트 통제관리의 간소화를 위한 공정관리분야이며, 두 번째 적용은 동시에 수행되는 여러 프로젝트에 의해서 공유되는 자원의 효과적 관리이다. 이 논문은 프로젝트 관리에 적용된 제약이론인 애로사슬(Critical chain)의 원리에 대해서 연구하고, 국내의 건설프로젝트에 적용하는 것을 목적으로 한다.

Keywords

References

  1. KT. Yeo, Integrating supply chain andcritical chain concepts in engineer-procure-construct (EPC) projects, International Journal of ProjectManage -ment, 2002
  2. Mohamed S, Options for applying BPR in Australian construction industry, futernational Journal of Project Management, 1996
  3. De la Garza JM, Value of concurrent engineering for N/E/Gi Industry, Journal of Managementin Engineering, 1994
  4. H Steyn, Project management application ofthe theoty of constmints beyond critical chain schedul -ing, Intemational Journal of Project Management, 2002
  5. Eliyahu M.Goldratt, The Goal. North River Press, 1984
  6. Lawrence P. Leach, Critical Chain Project Management, Artech House,2000
  7. Ing. NE Schieman, CCPM&Project Success an exploratory study, Maastricht University, 2002
  8. Chiu-Chi Wei, Resource-constrained project management using enhanced theory of constraint, International Journal of Project Management, 2002
  9. SEE Elmaghraby, Note on the psper 'Resource-constrained project management using enhanced theory of constraint' by Wei et al, International Journal of Project Management, 2003
  10. Ari-Pekka Hameri, Improving effiency: time critical intetfacing of project tasks, International Journal of Project Management, 2002
  11. H Steyn, Project management application of the theory of constrnints beyond critical chain schedul-ing, International Journal of Project Management, 2002
  12. Zinovy D.Radovilsky, Aquantitative apptroach toestimate the size of the time buffer in the theory of constrnints, International Journal of Production Bxnomics, 2003
  13. GrahamK Rand, Critical chain: the theoty ofconstraints applied to project management, International Journal of Project Management, 2000
  14. Herman Steyn, An investigation into the fundamentals of critical chain project scheduling, International Journal of Project Management, 2000
  15. Willy Herroelen, On the merits and pitfalls of critical chain scheduling, International Journal of Project Management, 2001