A Study On the Predicting Method of the EAC according to the Performance Index of Construction Projects

건설공사 수행에 따른 최종공사비 예측방법에 관한 연구

  • Published : 2002.12.01

Abstract

The EVMS(Earned Value Management System) comes from C/SCSC which was first released by the United States Department of Defense in December 1967, and preyed very powerful and efficient project management tool from a lot of practices. Although it is an excellent tool, we can not be succeed appling foreign system due to the differences of construction culture and law between the Korean and US construction industries. EAC(Estimate at Completion) is one of the most important functions in the EVMS. The purpose of this study is to propose the improved EAC method according to the performance indices better than old that and to prove from examples. In advance, the improved EAC method is to estimate more exactly costs and to promote efficiency in construction projects.

Keywords

References

  1. David S. Christensen, Estimating the cost of a defense contract with performance indices, Air Force Institute of Technology, 2002. 3
  2. David C. Bachman, A new definition with example, Acquisiton Review Quarterly, Fall 2001
  3. Eleanor Haupt, Basic Earned Value Management for Program Manegers, ASC/FMCE
  4. 김선규.김재준, EVMS 최종공사비 예측 모델 최적성과지수에 대한 고찰, 한국건설관리학회, 2000. 9
  5. 백승호 외 3인 EVMS를 활용한 공정-공사비 통합관리 프로세스 모델, 한국건설관리학회, 2000. 6
  6. 배동혁.조창연, 삼성건설 EVMS 사례, 한국건설관리학회, 2000. 6
  7. 임형철 외 3 인, 비용-일정 통합관리를 통한 건축공사 구축, 대림기술정보, 2002 봄호

Cited by

  1. Developing a Bayesian Network Model for Real-time Project Risk Management vol.24, pp.2, 2011, https://doi.org/10.7232/IEIF.2011.24.2.119