Bearing Capacity of Cast-in-situ Concrete Piles Socketed in Completely Weathered Gneiss

풍화암에 근입된 현장타설말뚝의 지지거동 분석

  • 전경수 (한국도로공사 도로연구소) ;
  • 김정환 (삼성건설 기술연구소) ;
  • 김명모 (서울대학교 공과대학 토목공학과)
  • Published : 1999.12.01

Abstract

In completely weathered granite gneiss,8 of 40cm cast-in-situ concrete piles are constructed, and static pile load tests are executed on the piles to study the bearing behavior of rock-socketed piles. Subsurface explorations are carried out on the test site in three phases, in which 14 borehole investigations as well as the seismic investigation are performed. Rock socketd depths of the piles in the weathered rocks are varied as 3m, 6m and 9m to separate the shaft resistance from the end bearing resistance, and for a couple of piles, styrofoam of 10cm thickness is installed under the pile point to eliminate the effect of the end resistance. Strain gages are instrumented on re-bars to pick-up the transferred loads along the pile length. From the results of the pile load tests, the allowable shaft resistance and the allowable end bearing values of weathered rocks are proposed as $8.6t/m^2\;and\; 84t/m^2$, respectively. The empirical equation relating the elastic modulus of rock mass with the uniaxial compressive strength of the rock specimen is also proposed for the weathered rocks.

화강편마암으로 된 풍화암이 기반암인 암반에 소켓된 말뚝의 지지 거동을 알기 위하여 직경 40cm인 현장타설말뚝 8개를 시공하고 말뚝 재하 시험을 실시하였다. 지반 조사는 예비조사, 본조사, 그리고 시험후 조사 등 3차례에 걸쳐서 이루어 졌으며, 이 때 BX와 NX 보링(12개소) 조사와 탄성파 탐사 등이 시행되었다. 암반 소켓 말뚝의 지지 거동을 주면부와 선단부로 분리하여 평가하기 위하여 암반 소켓 깊이를 3m, 6m 그리고 9m등으로 다양하게 하고, 선단부 지지력의 영향을 배제하기 위하여 말뚝 선단부에 스타이로폼(styrofoam)을 매설하기도 하였다. 그리고 말뚝 깊이에 따른 하중 전이 해석을 위하여 말뚝 철근에 변형률 게이지 등을 설치하고 재하 시험을 수행하였다. 상기의 재하 시험 결과로부터 국내 화강 편마암으로 된 풍화암에 소켓된 현장타설말뚝의 허용 주면지지력과 허용 선단지지력을 각각 $8.6t/m^2 \;와 \;84t/m^2$로 제안하였으며, 일축압축강도를 이용한 풍화암의 탄성계수 산정식을 제안하였다.

Keywords