A Study on the Development of Rescheduling Procedure for Shipbuilding Master Production Schedule

조선 기준일정계획을 위한 재계획 절차의 개발

  • 박주철 (울산대학교 산업공학과) ;
  • 황하룡 (현대중공업(주) 조선사업기획부)
  • Received : 19980900
  • Published : 1998.11.30

Abstract

In this paper, a rescheduling procedure is developed for shipbuilding master production schedule. Shipyard initially develops backward production schedules for the entire shipbuilding process, and then refines the schedule by stage. The rescheduling procedure of this paper tries to resolve the schedule discrepancies between the outdoor backward schedule and the refined indoor schedule. Through the proposed rescheduling procedure, outdoor schedule can be successfully adjusted using buffer days and duration reduction. An Object-oriented program is also developed to automate the procedure. We can observe the improvement on productivity and quality of rescheduling works from the application of the developed procedure.

Keywords