원자력 발전소 RCB 외벽 거푸집 1단 타설 높이별 시공성 분석

Analysis of Construction RCB Exterior Wall Formwork Placing High on Nuclear Power Plant

  • 송효민 (경기대학교 건축공학과) ;
  • 신윤석 (경기대학교 플랜트건축공학과)
  • 발행 : 2014.11.14

초록

It is very important to reduce the construction duration of the Reactor Containment Building (RCB) when considering the more than 50 months on average from concrete placement to completion. The purpose of this study attempts to evaluate the single-stage workability of the system given a change in the height of the setting of RCB exterior wall formwork to be used in nuclear power plant construction. As a result of this study, it is possible height of 3.5m~4m uses formwork when analyzing the construction period and material costs an increase in formwork by concrete lateral pressure, to ensure the workability of the RCB exterior wall formwork. Through this study, I want to provide as basic data for the improvement of workability and RCB shortening the construction period.