Development of Top-Down Connection System to Solve the Problem of Construction Tolerances in Installing Prefabricated Beams to Pre-founded Columns
시공오차가 있는 선기초기둥에 공장제작보의 설치가 용이한 탑다운공사용 접합기술개발
- Published : 2011.05.20
Abstract
Almost prefounded columns for top-down construction certainly have construction tolerances in plan and plumbness. Therefore, it is very difficult to connect prefabricated beams to prefounded columns at each floor level after excavation by usual top-down connection method and this usual connection method leads to long construction time, increasing cost and decreasing quality. This paper presents a new method for connecting prefabricated beam to prefounded column with GROUT-JACKET CONNECTION SYSTEM consisting of sleeve, bearing-shear bands and grout. Details and illustrations of the connections and applications by GROUT-JACKET CONNECTION SYSTEM for the top-down construction are also included in this paper.
Keywords
- Top-Down Construction;
- Prefounded Column;
- Construction Tolerance;
- Prefabricated Beam;
- Grout-Jacket Connection System
- 탑다운 공사;
- 선기초 기둥;
- 시공오차;
- 공장제작 보;
- 그라우트-재킷 접합시스템;