The Study on the System to Estimate the Cost by Using Regression in the Early Stage of the Project

공사 초기단계에서의 회귀분석을 이용한 최종공사비(EAC) 추정 방법

  • Published : 2006.11.11

Abstract

The EAC(Estimate at Completion) among existing methods, which estimate cost and time effectively, help managers anticipate changeable several results at the point of $15{\sim}30%$ in the project progress. However, this method may cause such some problems as not to consider the periodically changing circumstances caused by construction risks or uncertainties which can affect the cost and time in the project, and to regard collected and accumulated data only as a single value when predicting the results on the progress. Accordingly, it is very difficult to accept the even small range of variability based on the anticipation of EAC. Consequently, the study focuses on the possibility methodology to anticipate time and cost accurately on the way to utilize EVMS(Earned Value Management System), and also suggest the way to perform the right estimation of EAC as considering various risks and uncertainties in construction projects.

건설 사업은 다양한 불확실성 및 리스크 요인으로 인하여 사업 수행 과정이 초기 계획대로 수행되고 있는지에 대한 반복적인 성과측정 및 후속 관리 조치가 필요하다. 이러한 성과 측정의 가장 대표적인 기준이 공정, 공사비, 품질이며 특히, 공정과 공사비의 경우 정량적인 평가가 가능하고 통합관리를 통해 효율성을 높일 수 있는 주요 관리 대상이 된다. 이를 위해 EVM(Earned Value Management)기법을 운영하도록 제도화 하였으며 EVM을 활용함으로써 사업 진도율 $15{\sim}30%$ 시점에서 사업의 EAC(Estimate at Completion)와 공정결과를 예측할 수 있다. 본 연구에서는 기존 EAC 추정의 문제점을 제시하고 회귀분석을 이용하여 적정 EAC 변동 범위를 예측한다. 따라서 공동주택 건설사업에서의 공사 수행 중 공정과 공사비의 문제점을 사전에 파악하여 변동 범위의 결과 값을 통해 의사결정자들이 효율적인 의사결정을 할 수 있도록 정보를 제공한 수 있을 것으로 판단된다.

Keywords