Prediction of Final Construction Cost and Duration by Forecasting the Slopes of Cost and Time for Each Stage

공사 진행단계별 기울기 추정을 통한 최종 공사비 및 공기 예측

  • 진의재 (연세대학교 공과대학 토목공학과) ;
  • 곽수남 (연세대학교 공과대학 토목공학과) ;
  • 김두연 (연세대학교 공과대학 토목공학과) ;
  • 김형관 (연세대학교 공과대학 사회환경시스템공학부) ;
  • 한승헌 (연세대학교 공과대학 사회환경시스템공학부)
  • Published : 2006.11.11

Abstract

Cost and duration is important factors which directly affect profit therefore must be forecasted correctly to accomplish success of projects. So construction company uses EVMS(Earned Value Management System) to forecast final cost and duration. But previous forecasting model has low accuracy because of its linear forecasting method and can't reflect characteristic of company and project and changes as each progress. This paper presents cost and duration forecasting model using the slope prediction of cost and duration as each progress to reflect the various characteristics of construction industry. EVMS data of 23 road construction projects was used to make up regression analysis equation of slope forecasting model.

비용과 공기는 수익과 직접적인 상관관계를 갖는 중요한 요소로 성공적인 프로젝트를 위해서는 이들에 대한 정확한 예측이 이루어져야 한다. 현재 최종 공사비와 공기 예측을 목적으로 EVMS(Earned Value Management System)가 범용적으로 활용되고 있지만, 기존에 제시된 공사비 및 공기 예측모텔은 선형적인 예측방식을 사용하기 때문에 예측결과가 부정확하고 시공업체의 성향, 프로젝트의 특성, 진도율에 따른 변화 등을 고려하지 못하는 한계가 있었다. 본 연구에서는 건설산업의 다양한 특성이 반영될 수 있도록 PB-S curve와 다중회귀분석을 이용한 진행단계별 공사비 및 공기의 기울기 예측모델을 제안하고 이를 동해 최종 공사비 및 공기를 예측하고자 한다. 이를 위하여 국내 건설업체로부터 23건의 도로공사 EVMS 자료를 활용하여 공사 진행단계별 기울기 예측을 위한 회귀분석방정식을 도출하고, 활용성을 검증하였다.

Keywords