Evaluation of DBR system in a serial production line

직렬 생산라인에 대한 DBR 방식의 평가

  • Published : 2002.05.01

Abstract

An alternative to traditional production planning and control systems such as MRP and JIT is the drum-buffer-rope (DBR). Using the DBR system, companies can achieve a large reduction of work-in-process (WIP) and finished-goods inventories (FGI). significant improvement in scheduling performance, and substantial earnings increase. The purpose of this paper is to analyze the effect of the DBR system in a serial production line. Using Markov process, we modeled a DBR system with three stages. For the model developed we analyze the system characteristics and then present an optimization model for system design. The system performance is also analyzed through sensitivity analysis.