• Title/Summary/Keyword: shield tunnels

Search Result 84, Processing Time 0.021 seconds

Calculation and field measurement of earth pressure in shield tunnels under the action of composite foundation

  • Chi Zhang;Shi-ju Ma;Yuan-cheng Guo;Ming-yu Li;Babak Safaei
    • Geomechanics and Engineering
    • /
    • v.34 no.1
    • /
    • pp.17-27
    • /
    • 2023
  • Taking a subway shield tunnel in a certain section of Zhengzhou Metro Line 5 as an example, the field tests of shield cutting cement-soil monopile composite foundation were carried out. The load and internal force of the tunnel lining under the action of composite foundation were tested on-site and the distribution characteristics and variation laws of earth pressure around the tunnel under the load holding state of the composite foundation were analyzed. Five different load combinations (i.e., overburden load theory + q0, Terzaghi's theory + q0, Bierbaumer's theory + q0, Xie's theory + q0, and the proposed method (the combination of compound weight method and Terzaghi's theory) + q0) were used to calculate the internal force of the tunnel structure and the obtained results were compared with the measured internal force results. The action mode of earth pressure on the tunnel lining structure was evaluated. Research results show that the earth pressure obtained by the calculation method proposed in this paper was more consistent with the measured value and the deviation between the two was within 5%. The distribution of the calculated internal force of the tunnel structure was more in line with the distribution law of field test data and the deviation between the calculated and measured values was small. This effectively verified the rationality and applicability of the proposed calculation method. Research results provided references for the design and evaluation of shield tunnels under the action of composite foundations.

A Study on Standard Construction Process Management System for Prediction of Proper Construction Period of Subsea Tunnel (해저터널 적정 공사기간 예측을 위한 표준공정관리 체계 연구)

  • Bae, Keunwoo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.18 no.4
    • /
    • pp.36-47
    • /
    • 2017
  • As a typical domestic subsea tunnel construction the Gadeok subsea tunnel applying the method of immersed tunnel has been completed and the Boryeong-Taean subsea tunnel is under construction using NATM. The high-speed railway subsea tunnels between the Honam and Jeju are under consideration, and the feasibility of constructing subsea tunnels with Japan and China is also under consideration. However, it is difficult to provide the process plan information for the construction work such as the analysis of the feasibility of the subsea tunnel and the prediction of the proper construction period because there is no case of domestic construction for it applying the shield TBM method. Due to economic and other reasons, government organizations are reluctant to apply the shield TBM, and there is lack of data on the construction process management field using the shield TBM method. Therefore, a standard construction process management system for the subsea tunnel is needed to analyze the feasibility of the subsea tunnel and to predict the proper construction period. By presenting the standard construction process management system of subsea tunnels such as WBS, Network Diagram, and construction period calculation model, I hope to contribute technically and economically to future subsea tunnel projects.

Development of optimal cross-section design methods for bored utility tunnels: case study of overseas typical cross-sections and design criteria (터널식 공동구 최적단면 설계기술 개발: 해외 표준단면 사례 및 설계기준 분석)

  • Park, Kwang-Joon;Yun, Kyoung-Yeol
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.20 no.6
    • /
    • pp.1073-1090
    • /
    • 2018
  • Since the domestic utility tunnels were built mainly in the development project of the new city, they are all in the form of cut-and-cover box tunnel. But, in the case of overseas construction of utility tunnels for existing urban areas, the bored tunnel types are mainly adopted. It is reasonable to install bored tunnels in a downtown area because it is difficult to block the roads or install bypass roads due to heavy traffic and civil complaints. In order to activate the utility tunnels in bored type, it is necessary to secure optimized cross-sectional design technology considering the optimal supplying capacity and mutual influencing factors (Thermal Interference, electrolytic corrosion, efficiency of the maintenance, etc.) of utilities (power cables, telecommunication cables, water pipes, etc.). The optimal cross-section design method for bored utility tunnels is ultimately to derive the optimal arrangement technique for the utilities. In order to develop the design methods, firstly, the cases of tunnel cross-section (Shield TBM, Conventional Tunneling) in overseas shall be investigated to analyze the characteristics of the installation of utilities in the section and installation of auxiliary facilities, It is necessary to sort out and analyze the criteria related to the inner cross-section design (arrangement) presented in the standards and guidelines.

Recent Topics on Tunnel Engineering in Japan

  • Toshihisa Adachi
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2002.10a
    • /
    • pp.29-50
    • /
    • 2002
  • Based on the investigation results on the damages of some underground structures due to the severe Kobe Earthquake it concludes that the aseismicity of underground is far superior to that of aboveground structures. Therefore, at first, necessity to reconstruct strong cities especially by good use of underground space will be discussed. Then two non-circular shield-tunneling projects in Japan are discussed. The first is construction of the world's first shield driven double track subway tunnel of rectangular shape for the Kyoto Municipal Subway. This paper presents a report on the overall planning, the tests that were performed in the process of planning, and the results of driving. The second is the design of the Hirakata Tunnel, with three traffic lanes and shoulders on one side, which will be constructed as one of the tunnels for The New Meishin (Nagoya-Kobe) Expressways. This paper presents the feasibility study of the shield tunneling method, using the same design criteria as the non-circular, horseshoe section of mountain tunnel, to the equivalent section of the Hirakata Tunnel.

  • PDF

Simplified nonlinear simulation for composite segmental lining of rectangular shield tunnels

  • Zhao, Huiling;Liu, Xian;Yuan, Yong
    • Structural Engineering and Mechanics
    • /
    • v.81 no.4
    • /
    • pp.513-522
    • /
    • 2022
  • Steel-concrete composite segments replacing the conventional reinforced concrete segments can provide the rectangular shield tunnel superiorities on bearing capacity, ductility and economy. A simplified model with high-efficiency on computation is proposed for investigating the nonlinear response of the rectangular tunnel lining composed of composite segments. The simulation model is developed by an assembly of nonlinear fiber beam elements and spring elements to express the transfer mechanism of forces through components of composite segments, and radial joints. The simulation is conducted with the considerations of material nonlinearity and geometric nonlinearity associated with the whole loading process. The validity of the model is evaluated through comparison of the proposed nonlinear simulation with results obtained from the full-scale test of the segmental tunnel lining. Furthermore, a parameter study is conducted by means of the simplified model. The results show that the stiffness of the radial joint at haunch of the ling and the thickness of inner steel plate of segments have remarkable influence on the behaviour of the lining.

Pipeline deformation caused by double curved shield tunnel in soil-rock composite stratum

  • Ning Jiao;Xing Wan;Jianwen Ding;Sai Zhang;Jinyu Liu
    • Geomechanics and Engineering
    • /
    • v.36 no.2
    • /
    • pp.131-143
    • /
    • 2024
  • Shield tunneling construction commonly crosses underground pipelines in urban areas, resulting in soil loss and followed deformation of grounds and pipelines nearby, which may threaten the safe operation of shield tunneling. This paper investigated the pipeline deformation caused by double curved shield tunnels in soil-rock composite stratum in Nanjing, China. The stratum settlement equation was modified to consider the double shield tunneling. Moreover, a three dimensional finite element model was established to explore the effects of hard-layer ratio, tunnel curvature radius, pipeline buried depth and other influencing factors. The results indicate the subsequent shield tunnel would cause secondary disturbance to the soil around the preceding tunnel, resulting in increased pipeline and ground surface settlement above the preceding tunnel. The settlement and stress of the pipeline increased gradually as buried depth of the pipeline increased or the hard-layer ratio (the ratio of hard-rock layer thickness to shield tunnel diameter within the range of the tunnel face) decreased. The modified settlement calculation equation was consistent with the measured data, which can be applied to the settlement calculation of ground surface and pipeline settlement. The modified coefficients a and b ranged from 0.45 to 0.95 and 0.90 to 1.25, respectively. Moreover, the hard-layer ratio had the most significant influence on the pipeline settlement, but the tunnel curvature radius and the included angle between pipeline and tunnel axis played a dominant role in the scope of the pipeline settlement deformation.

Face Stability Assessment of Slurry-shield Tunnels - Concentrating on Slurry Clogging Effect - (슬러리 쉴드 터널의 막장 안정성 평가 - 슬러리의 폐색효과를 중심으로 -)

  • Lee, In-Mo;Lee, Sam;Cho, Kook-Hwan
    • Journal of the Korean Geotechnical Society
    • /
    • v.20 no.6
    • /
    • pp.95-107
    • /
    • 2004
  • In this paper, the rheological characteristics of slurry used fur slurry-shield tunnels were studied with emphasis on penetration characteristics. The slurry penetration was modeled by soil-filter clogging theory. The coefficient of particle deposition was suggested as an indicator of sin clogging during tunnel construction and calculated through model tests. The measured slurry weight, clogged in the base soil, was compared with the value obtained from clogging theory. Based on the testing results, a stability analysis of a tunnel face was performed to pinpoint the most influential factor affecting stability of slurry-shield tunnels. It was found that the stability of tunnel face is dependent on the ratio of infiltration velocity to the coefficient of particle deposition, and the penetration distance of slurry increases with the ratio of infiltration velocity to the coefficient of particle deposition. Since the stability of tunnel face decreases with the slurry penetration distance, it was necessary to add some additives in order to reduce the slurry penetration distance. It was found that the ground condition needs additives when the soil has the effective particle diameter$(D_{10})$ larger than 0.75mm. It was also found that the tunnel face stability due to slurry penetration is significantly affected by the tunnel advance rate.

A Physical Model Test on the Behavior of Shield-tunnel Lining According to Drainage Conditions in Weathered Granite Soil (화강풍화토 지반에서 배수조건에 따른 쉴드터널 라이닝의 거동연구를 위한 모형실험)

  • Choi, Gou-Moon;Yune, Chan-Young;Ma, Sang-Joon
    • Journal of the Korean Geotechnical Society
    • /
    • v.31 no.6
    • /
    • pp.71-82
    • /
    • 2015
  • Recently, due to the expansion of urban infrastructure for the citizen convenience, the shield tunnel construction has increased considering the civil complaints minimization and construction stability. Most shield tunnels are designed based on the assumption of the undrained condition that underground water does not inflow, but they are operated in the field as drained tunnels with drainage facility to drain underground water. Therefore, the drained condition needs to be considered in the shield tunnel design. It is also necessary to consider the weathered granite soil that is widely distributed throughout the country and consequently is encountered in most of construction sites. In this paper, the model test which can control total stress and pore water pressure and simulate the underground tunnel located in the weathered granite soil below ground water level is conducted. Total stress, pore water pressure and an inflow water into an inner pipe were measured using the testing device. Test results showed that the total stress in a drained condition was lower than in an undrained condition because pore water pressure decreased in a drained condition and an inflow water into an inner pipe was proportional to the loading stress in a drained condition. As a result, if a drained condition is considered in the shield tunnel design, the more economical design can be expected because of the stress reduction of the lining.

Dynamic responses of shield tunnel structures with and without secondary lining upon impact by a derailed train

  • Yan, Qixiang;Li, Binjia;Deng, Zhixin;Li, Bin
    • Structural Engineering and Mechanics
    • /
    • v.65 no.6
    • /
    • pp.741-750
    • /
    • 2018
  • The aim of this study was to investigate the mechanical responses of a high-speed railway shield tunnel subjected to impact by a derailed train, with emphasis on the protective effect of the secondary lining. To do so, the extended finite element method was used to develop two numerical models of a shield tunnel including joints and joint bolts, one with a cast-in-situ concrete secondary lining and one without such a lining. The dynamic responses of these models upon impact were analyzed, with particular focus on the distribution and propagation of cracks in the lining structures and the mechanical responses of the joint bolts. The numerical results showed that placing a secondary lining significantly constricted the development of cracking in the segmental lining upon the impact load caused by a derailed train, reduced the internal forces on the joint bolts, and enhanced the safety of the segmental lining structure. The outcomes of this study can provide a numerical reference for optimizing the design of shield tunnels under accidental impact loading conditions.