An Analysis of the Duration of the Construction Document Phase of Large Public Building Projects Delivered by the Total Solution Service from 2009 to 2014 (공공기관 발주 대형건축공사 실시설계 기간에 대한 분석 및 개선방안 -2009년부터 2014년까지 공공발주 맞춤형 서비스 프로젝트를 중심으로 -)

  • Jung, Wooyoung;Lee, Taewon;Rhee, Pung-wook;Lee, Ghang
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.4
    • /
    • pp.89-97
    • /
    • 2015
  • This paper analyzes the duration of the construction document (CD) phase of 42 large public building projects delivered by the total solution service of Public Procurement Services in Korea from 2009 to 2014. The quality of construction documents significantly affects the quality of construction and facility management. Thus, securing appropriate time for the CD phase during project planning is important for the quality of a project. Currently, the duration of the CD phase is planned based on the construction costs of a project following a notice of the Ministry of Land, Infrastructure and Transport. However, our analysis results showed that the correlation between the actual duration of the CD phase and construction costs is very weak. The actual CD phase takes 1.33-1.79 times longer than the planned duration. The practitioners who were interviewed, were already aware that the correlation between the duration of the CD phase and the construction costs is weak. They identified the complexity of the project, the extent of the design changes, project type, client characteristics, and others as more influential factors on the CD phase than the construction costs. To improve the quality of CDs, a new guideline for determining an adequate CD phase duration should be studied and developed.

Bim Strategy Plan through Domestic Construction Companies BIM Project Case Analysis - focused on the BIM USE of the project from 2009 to 2015 - (국내 건설회사 BIM 프로젝트의 사례 분석을 통한 BIM전략 수립 방안 - 2009년부터 2015년까지 프로젝트의 BIM Use를 중심으로 -)

  • Jo, Yong-Hyun;Lee, Joo-Sung;Ham, Nam-Hyuk;Kim, Jae-Jun
    • Journal of KIBIM
    • /
    • v.6 no.2
    • /
    • pp.1-11
    • /
    • 2016
  • In South Korea, there have been attempts to enhance BIM work practices in various aspects. Public Procurement Service(PPS) has recently published 'basic guidelines to improve BIM work practices in construction and facility management'. It defines roles and responsibilities of project members in their application of BIM. It also developed a set of modelling standards and guidelines for effective model creation, management and communication among BIM users. Moreover, numerous construction companies have tried to cultivate BIM specialized manpower throughout entire construction phases. However, there are still challenges faced by firms during BIM adoption. Therefore, this study aims to provide practical counsel for construction companies to help them create optimized facilities and deliver high performance by analyzing BIM-based domestic construction projects in Korea from 2009 and 2015. The study will investigate types of client, project, BIM application range, and application technology.

Development of the Design Management Guidelines to Enhance the Capability of Public Clients (공공 발주자 역량 향상을 위한 설계관리 지침서 및 절차서 개발)

  • Shin, Kyoo-Chul;Park, Hyung-Keun;Lee, Young-Ho;Kwak, Jun-Hwan
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.2
    • /
    • pp.143-151
    • /
    • 2011
  • The process of design management by public client has not performed effectively due to lack of the formal guidelines and procedures in domestic public projects. The purpose of this research is to develop the guidelines and procedures of design management for public clients. The research methodology is to analyze current status of design management process in domestic and overseas cases and to develop the guidelines based on the administrative stages of design process along the project. The guidelines of design management developed by the design stages of pre-contract, contract, and post-contract stages to classify administrative procedures. The outcome of this research is able to be utilized by the public clients and design firms to standardize the process of design management and minimize potential risk during the process of the project.

Risk Mitigation Methodology of the General Conditions of Contract (공사계약일반조건의 위험요인 감소방안)

  • Yoon, Chul-Sung;Kwon, Soon-O;Kim, Seon-Gyoo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.5 s.27
    • /
    • pp.177-185
    • /
    • 2005
  • Construction uncertainties are frequently exposed to the claims. In most cases, an interpretation of the claims is based on the construction contract. Therefore, the key points of contract negotiation are how to fairly distribute the contract risks to the client and contractor. For these, a FIDIC that is considered as an international standard contract form would be a good reference to decide reasonable contract risk distribution. In order to find out any unreasonable and unfair contract clauses at the general conditions of contract applying generally to public construction project in Korea, this study surveys, analyses and evaluates the general conditions of contract based on a FIDIC, and then proposes a risk mitigation methodology to response those clauses' risk factors reasonably.

A Review of Large-Scale Hydropower Project in Public Sector of Pakistan

  • Umair, Muhammad;Choudhary, Muhammad Abbas;Jahanzaib, Mirza
    • Journal of Construction Engineering and Project Management
    • /
    • v.4 no.4
    • /
    • pp.47-59
    • /
    • 2014
  • Client organization inadequate project planning before awarding the contract and insufficient monitoring and control system among the parties involved create severe problems. Ultimately, large-scale projects go beyond the expected cost and time control limits. This paper discusses the major issues involved with a large-scale Hydropower Project in Pakistan Public Sector environment. The latest approved Baseline Plan of project was reviewed and analyzed using Variance Analysis and Trend Analysis techniques in Primavera project management software to assess the efforts made of the parties involved. It was found that Project is 202% Cost overrun and 25% time delays from original contract award. After analysis of baseline plan and quantification of various variance issues in impacted activities, the questionnaire survey was conducted to identify the impact of causative factors. There were almost 17 most significant causative factors identified among 60 identified factors and responsibilities are assigned accordingly. At the end recommendations are made for strategic decisions as lessons learned during project evaluation.

An Empirical Study on the Possibility of Duplicated Sanctions in Bid-rigging on Construction Projects (건설공사 입찰담합의 중복제재 가능성에 관한 실증연구)

  • Shin, Young-Su;Cho, jin-Ho;Kim, Byung-Soo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.24 no.2
    • /
    • pp.50-58
    • /
    • 2023
  • Bid-rigging is a common issue in public construction projects, and appropriate sanctions are required from the relevant authorities. This study analyzes the need for an optimal enforcement model to prevent bid-rigging by considering both civil and criminal aspects. Recently, there have been overlapping sanctions under the Fair Trade Act, such as fines imposed by the Fair Trade Commission and civil lawsuits filed by the client for damages. The purpose of this study is to evaluate the effectiveness of penalty surcharges and compensation systems for preventing bid-rigging, and to consider the possibility of overlapping sanctions in public construction projects. It was found that overlapping sanctions under the Fair Trade Act can be helpful in improving the system. However, in cases where the state is the plaintiff for damages in a lawsuit, it is necessary to consider the penalty surcharge and sentence, reduce the penalty surcharge for joint acts, refund the surcharge after a final judgment, and consider the damage compensation system when imposing a surcharge. This study contributes to the development of an efficient enforcement model to suppress bid-rigging in public construction projects by analyzing the improvement effects of sanctions and compensation.

An Improved Privacy Preserving Construction for Data Integrity Verification in Cloud Storage

  • Xia, Yingjie;Xia, Fubiao;Liu, Xuejiao;Sun, Xin;Liu, Yuncai;Ge, Yi
    • KSII Transactions on Internet and Information Systems (TIIS)
    • /
    • v.8 no.10
    • /
    • pp.3607-3623
    • /
    • 2014
  • The increasing demand in promoting cloud computing in either business or other areas requires more security of a cloud storage system. Traditional cloud storage systems fail to protect data integrity information (DII), when the interactive messages between the client and the data storage server are sniffed. To protect DII and support public verifiability, we propose a data integrity verification scheme by deploying a designated confirmer signature DCS as a building block. The DCS scheme strikes the balance between public verifiable signatures and zero-knowledge proofs which can address disputes between the cloud storage server and any user, whoever acting as a malicious player during the two-round verification. In addition, our verification scheme remains blockless and stateless, which is important in conducting a secure and efficient cryptosystem. We perform security analysis and performance evaluation on our scheme, and compared with the existing schemes, the results show that our scheme is more secure and efficient.

A Study Of the Construction Management Applied to BAT Korea Factory Construction Project in Korea (BAT Korea Factory 건설 프로젝트의 CM 적용사례 연구 - Cost Management 사례를 중심으로 -)

  • Kim Duk-Kon;Kwon O-Kyung;Kim Jong-Hoon
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.48-57
    • /
    • 2003
  • BAT Korea's Factory is the one of the major projects that clearly confirms and demonstrates that Construction Management (CM), provided by a Korean CM Company to the foreign clients, enables them to successfully complete projects; with savings in time and reduction in cost, which it is $15\%$ lower than the cost of the overseas construction. Also, throughout the thorough schedule management, it was possible to commence with manufacturing one month after the completion date. The Key Success Factors was generated by the excellent construction management skills, and more importantly by the confidence gained by the client in giving a CM company full authority for the construction management of the project. This study has focus on elements of construction management applied to this project throughout the concept of 'One Stop Shop', including cost managements, contract management and value engineering etc. We hope that this study will provide useful data to enable public clients to take advantages of construction management, in a similar way to. the private clients, who have already implemented CM actively.

  • PDF

A Study on the Process of Estimating the Amount of Materials for Client's Decision-Making Support in Space Programming Stage of Pre-design BIM -focusing on Building Interior Finishing- (건축 기획 BIM의 공간 프로그래밍 단계에서 발주자 의사결정지원을 위한 물량예측 방법론에 관한 연구 -건축마감을 중심으로-)

  • Jun, Yeong-Jin;Kim, Ju-Hyung;Kim, Jae-Jun
    • Journal of The Korean Digital Architecture Interior Association
    • /
    • v.10 no.3
    • /
    • pp.19-28
    • /
    • 2010
  • The construction projects are recently having changes in their magnitude and complexity. Therefore, the amount of information created and managed by participants over project phases is enormous and this may cause difficulties in consistent and integrated data management. Because of the change in construction projects, there is a need to apply more logical and systematic ways to deal integrated data management. For the solution to this, BIM(Building Information Modeling), a new paradigm for integrated management of the information over project life-cycle, has been seriously considered. Also, the Korean Public Procurement Service announced that project over 50 billion Korean Won should introduce BIM into procurement starting from 2012. However, the studies and development have lack on studies of applying BIM and managing the data made using BIM in pre-design and maintenance stage. In pre-design stage, the concept of schematic design model is made to support for making major decisions concerning the size, shape and cost of the project. To decide the cost for the building in this stage by making use of BIM, estimating the amount of building materials used for constructing should be preceded. In this study, the pre-design BIM is explained to gain a better understanding of its process, since this paper focused on space programming stage. Finally, the paper suggests the concept process of estimating the amount of materials in building interior finishing from selecting the type for the elements of each space made to support the client for making decisions in space programming stage based on pre-design BIM.

Estimation Method of the Competitive Bid-price in Bid-rigging of Public Construction (기댓값 분석에 따른 공공공사 입찰담합의 가상경쟁가격 산정방법)

  • Jeong, Kichang;Kim, Wooram;Kim, Namjoon;Lee, Jaeseob
    • Korean Journal of Construction Engineering and Management
    • /
    • v.19 no.3
    • /
    • pp.52-60
    • /
    • 2018
  • Korea's public construction projects are under construction through bidding, however, due to the nature of the bidding, collusion between participants can occur. The collusion of bids accordingly damages the client. So, it is necessary to calculate the appropriate fictitious competition price to compensate for this. In this regard, econometrics methods are generally used, but there are limitations and issues arising from the nature of construction, especially design-build bid. Therefore, this study proposes a method to estimate reasonable competitive bid-price in design-build bid. It derives the lowest bid-price from the design submitted by the proponent and estimates the competitive bid-price by examining the factors according to the penetration rate according to the technical level of the tester, the skill level of the competitor, and the type of tester. Based on the method proposed in this study, a reasonable price can be derived that reflects the characteristics of the design and construction bidding bidder selection method and also it can be used as a reference material in the actual bidding process as well as calculating the damage due to the answer.