• 제목/요약/키워드: cast-in-place bored pile

검색결과 3건 처리시간 0.022초

Field test of the long-term settlement for the post-grouted pile in the deep-thick soft soil

  • Zou, Jin-Feng;Yang, Tao;Deng, Dong-ping
    • Geomechanics and Engineering
    • /
    • 제19권2호
    • /
    • pp.115-126
    • /
    • 2019
  • The long-term settlement characteristics for the cast-in-place bored pile in the deep-thick soft soil are investigated by post-grouting field tests. Six cast-in-place bored engineering piles and three cast-in-place bored test piles are installed to study the long-term settlement characteristics. Three post-grouting methods (i.e., post-tip-grouting, post-side-grouting, and tip and side post-grouting) are designed and carried out by field tests. Results of the local test show that decreased settlements for the post-side-grouted pile, the post-tip-grouted pile and the tip and side post-grouted pile are 22.2%~25.8%, 30.10%~35.98% and 32.40%~35.50%, respectively, compared with non-grouted piles. The side friction resistance for non-grouted piles, post-side-grouted pile, post-tip-grouted pile and the tip and side post-grouted pile undertakes 89.6~91.3%, 94.6%, 92.4%~93.0%, 95.7% of the total loading, respectively. At last, the parameters back analysis method and numerical calculation are adopted to predict the long-term settlement characteristics of the cast-in-place bored pile in the deep-thick soft soil. Determined Bulk modulus (K) and a creep parameter (Ks) are used for the back analysis of the long-term settlement of the post-grouted pile. The settlement difference between the back analysis and the measurement data is about 1.11%-7.41%. Long-term settlement of the post-grouted piles are predicted by the back analysis method, and the predicted results show that the settlement of the post-grouted pile are less than 6 mm and will be stable in 30 days.

Shaft resistance of bored cast-in-place concrete piles in oil sand - Case study

  • Barr, L.;Wong, R.C.K.
    • Geomechanics and Engineering
    • /
    • 제5권2호
    • /
    • pp.119-142
    • /
    • 2013
  • Pile load tests using Osterberg cells (O-cell) were conducted on cast-in-place concrete piles founded in oil sand fill and in situ oil sand at an industrial plant site in Fort McMurray, Alberta, Canada. Interpreted pile test results show that very high pile shaft resistance (with the Bjerrum-Burland or Beta coefficient of 2.5-4.5) against oil sand could be mobilized at small relative displacements of 2-3% of shaft diameter. Finite element simulations based on linear elastic and elasto-plastic models for oil sand materials were used to analyze the pile load test measurements. Two constitutive models yield comparable top-down load versus pile head displacement curves, but very different behaviour in mobilization of pile shaft and end bearing resistances. The elasto-plastic model produces more consistent matching in both pile shaft and end bearing resistances whereas the linear elastic under- and over-predicts the shaft and end bearing resistances, respectively. The mobilization of high shaft resistance in oil sand under pile load is attributed to the very dense and interlocked structure of oil sand which results in high matrix stiffness, high friction angle, and high shear dilation.

베트남 밤콩 사장교의 설계 (Design of Vam Cong Cable Stayed Bridge in Vietnam)

  • 이용진;강정운;배상운;윤연석;노병철
    • 한국건설순환자원학회논문집
    • /
    • 제1권2호
    • /
    • pp.120-127
    • /
    • 2013
  • 밤콩 사장교는 메콩강 삼각주 지역 연결 사업의 일환으로 메콩강 하류의 꾸롱 삼각주에 위치하고 있으며, 중앙경간 450m의 사장교로 설계되었다. 왕복 4차선으로 구성된 강합성 보강형과 멀티 스트랜드 방식의 케이블을 적용하였으며, 개선된 H형 주탑과 현장타설 콘크리트 말뚝 기초로 구성되어 있다. 주탑, 프리캐스트 콘크리트 바닥판 그리고 현장타설 콘크리트 말뚝에는 고강도 콘크리트를 적용하여 구조적 안정성을 확보하였다. 본 고에서는 밤콩 사장교의 설계에 적용된 설계기준 및 주요 설계 특징을 설명하고자 한다.