A study on hydraulic back analysis for an urban tunnel site and stability analysis based on hydro-mechanical coupling analysis (도심지 터널 용출수 발생구간에서의 수리 역해석 및 수리-역학 연계해석을 통한 안정성 해석 연구)

  • Park, Inn-Joon;Song, Myung-Gyu;Shin, Uyu-Soung;Park, Yong-Su
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.10 no.4
    • /
    • pp.397-404
    • /
    • 2008
  • Excessive amount of groundwater flowed into tunnel, while constructing Incheon international airport railway. Tunnel passes under subway line no. 2 with only 1.76 m below. To protect the existing structure, TRcM excavation method was applied. As station and construction shaft are already constructed, which are located back and forth of TRcM section, 86.4 ton per day of groundwater inflow is against expectation. To identify mechanism of excessive water inflow, hydraulic back analyses were performed. Then, hydro-mechanical coupled analysis were also performed with the hydrogeologic parameters identified, whose results are investigated for checking the stability of adjacent structures to the tunnel under construction. And a number of mechanical analyses were also performed to check the hydro-mechanical coupling effect. The result from the mechanical analysis shows that subsidence and tunnel ceiling displacement will be 0.85 mm and 1.32 mm. The result of hydro-mechanical couple analysis shows that subsidence and maximum tunnel ceiling displacement will be 1.2 mm and 1.72 mm. Additional displacements caused by groundwater draw down were identified, however, displacement is minute.

  • PDF

The study on interval calculation of cross passage in undersea tunnel by quantitative risk assesment method (해저철도터널(목포-제주간) 화재시 정량적 위험도 평가기법에 의한 피난연결통로 적정간격산정에 관한 연구)

  • Yoo, Ji-Oh;Kim, Jin-Su;Rie, Dong-Ho;Shin, Hyun-Jun
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.3
    • /
    • pp.249-256
    • /
    • 2015
  • Quantitative Mokpo-Jeju undersea tunnel is currently on the basis plan for reviewing validation. As for the cross section shape for express boat of 105 km line, sing track two tube is being reviewed as the Euro tunnel equipped with service tunnel. Also, 10 carriage trains have been planned to operate 76 times for one way a day. So, in this study, quantitative risk assessment method is settled, which is intended to review the optimal space between evacuation connection hall of tunnel by quantitative risk analysis method. In addition to this, optimal evacuation connection hall space is calculated by the types of cross section, which are Type 3 (double track single tube), Type 1 (sing track two tube), and Type 2 (separating double track on tube with partition). As a result, cross section of Type 2 is most efficient for securing evacuation safety, and the evacuation connection space is required for 350 m in Type 1, 400 m in Type 2, and 1,500 m in Type3 to satisfy current domestic social risk assessment standard.

A study on evacuation characteristic by cross-sectional areas and smoke control velocity at railway tunnel fire (철도터널 화재시 단면적별 제연풍속에 따른 대피특성 연구)

  • Yoo, Ji-Oh;Kim, Jin-Su;Rie, Dong-Ho;Kim, Jong-Won
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.17 no.3
    • /
    • pp.215-226
    • /
    • 2015
  • In this study, with variables the cross section area ($97m^2$, $58m^2$, $38m^2$) and the wind velocity(0.5, 1.0, 1.5, 2.0, 2.5, 3.0, 3.5 m/s), the time of getting off train dependent on the way of itself and the width of the evacuation route was analyzed, and also fire and evacuation characteristics is reviewed by cross section area of each wind velocity. As the result, if cross section become smaller, the density of harmful gases in the tunnel increased more than the ratio of decreasing cross section area. In the case of small cross sectional area, the surrounding environment from initial fire is indicated to exceed the limit criteria suggested in performance based design. In the analysis of effective evacuation time for evacuation characteristics, the effective evacuation time was the shortest in the case of evaluating effective evacuation time by the visibility. Also, there was significant difference between the effective evacuation time on the basis of performance based evaluation and the effective evacuation time obtained by analyzing FED (Fractional effective dose), one of the analysis method obtaining the point that deaths occur, against harmful gases.

Effects of evacuation delay time and fire growth curve on quantitative risk for railway tunnel fire (철도터널 화재 시 피난개시시간지연 및 화재성장곡선이 정량적 위험도에 미치는 영향)

  • Ryu, Ji-Oh;Kim, Hyo-Gyu;Lee, Hoo-Young
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.20 no.5
    • /
    • pp.809-822
    • /
    • 2018
  • A quantitative risk assessment has been introduced to quantitatively evaluate fire risk as a means of performance based fire protection design in the design of railway tunnel disaster prevention facilities. However, there are insufficient studies to examine the effect of various risk factors on the risk. Therefore, in this study, the risk assessment was conducted on the model tunnel in order to examine the effects of the evacuation start time delay and the fire growth curve on the quantitative risk assessment. As a result of the analysis of the scenario, the fatalities occurred mainly when escapes in the same direction as the direction of the fire smoke movement. In addition, after the FED exceeded 0.3, the maximum fatalities occurred within 10 minutes. In the range of relatively low risk, distance between cross passages, evacuation delay time and fire growth curve were found to affect the risk, but they were found to have little effect on the condition that the risk reached the limit. Especially, in this study, it was evaluated that the evacuation delay time reduction, fire intensity and duration reduction effect were not observed when the distance between cross passages was more than 1500 m.

Reliability analysis of surface settlement during shield TBM tunneling (쉴드 TBM 터널 굴착시 지표침하에 관한 신뢰성해석)

  • Han, Myeong-Sik;Cho, Kuk-Hwan
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.18 no.3
    • /
    • pp.305-318
    • /
    • 2016
  • This study is to evaluate the uncertainty of the soil parameters associated with the Gap parameter during shield TBM tunnel excavation of ${\bigcirc}{\bigcirc}$ International Airport Terminal 2 connecting railway construction basic design. And This study is to evaluate the adequacy of the shield TBM design by performing a reliability analysis of the Surface settlement. In addition, By analyzing the reliability indices of the design constants and Sensitivity probability of failure to be used in designing an integer parameter Gap, and By evaluating the design constants of a great influence on the surface subsidence, it was to provide a basis for carrying out an optimum design.

Comparison of high speed rail tunnels in Korea with those on other high speed railways worldwide (국내와 외국고속철도 터널의 설계 및 시공사례 비교)

  • ;Kim, Byeong Ho;Choe, Jeong Hwan
    • Magazine of korean Tunnelling and Underground Space Association
    • /
    • v.3 no.2
    • /
    • pp.32-44
    • /
    • 2001
  • Most of the major aspects of the high speed rail tunnels in Korea, including such items as the tunnel geometry, excavation methods, primary support, final lining, drainage and waterproofing, are similar to the practices followed in other countries. The tunnels in Korea provide the largest net internal area $(107\;m^2)$ as compared to the other counties addressed in this paper. The effective adaptation and modification of international practices and designs, combined with the integration of domestic practices, has resulted in the successful construction of these large tunnels. The experience gained from the completed work to date on the high speed line in Korea, combined with international technology input, will help to ensure future tunnels are constructed in an efficient manner with adequate design measures implemented for the long-term operational life of the tunnels. As has occurred in these other countries, further improvements and modifications to the Korea high-speed railway tunnels will occur as experience is gained and new technology develops.

  • PDF

Comparison of measured values and numerical analysis values for estimating smart tunnel based groundwater levels around vertical shaft excavation (수직구 굴착시 스마트 터널기반 지하수위 현장계측과 수치해석 비교 연구)

  • Donghyuk Lee;Sangho Jung
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.26 no.2
    • /
    • pp.153-167
    • /
    • 2024
  • Recently the ground settlement has been increasing in urban area according to development. And, this may attribute a groundwater level drawdown. This study presents an analysis of groundwater level drawdown for circular vertical shaft excavation of 「◯◯◯◯ double track railway build transfer operate project」. And, in-situ monitoring data and numerical analysis were compared. So, if we examine the groundwater level drawdown in design, ground conditions should be applied so that the site situation can be reflected. And, groundwater level should be considered a seasonal measurement in order to apply the appropriate groundwater level. It was confirmed a similar predicted value to groundwater level drawdown of in-situ monitoring data.

Applicability Analysis of Empirical Methods for the Calculation of TBM Advance Rate (국내 TBM굴진속도 산정을 위한 경험적 방법들의 적용성 분석)

  • 조만섭;우동찬;김경곤;이진무
    • Tunnel and Underground Space
    • /
    • v.13 no.4
    • /
    • pp.260-269
    • /
    • 2003
  • In order to introduce to engineers the suitable calculation techniques of TBM advance rate (ad.) and ultimately promote to understand the designing process, this study was carried out. We analyzed the 17 bored data of TBM which applied to the roadway and water supply tunnels in Korea. From this analysis, it was able to how that the average utilization is 30.83% md the correlation equation of Ad and TBM´s diameter (D) is Ad(m/month) = 506.05ㆍ $e^{-0.1162}$$\times$D than the correlation coefficient ($R^2$) is 0.76. In the object of the W tunnel of Seoul-Busan highspeed railway, the Ad of TBM 5.0mø was analyzed by the variety of empirical models and upper correlation equation. Average Ad of the empirical models was calculated to be larger than one of the upper equations. But considering only the results of 3.0~5.0mø TBM in the 17 bored data, the average Ad by the models belongs to the similar range of bored data. Therefore, when the reliability and representative of parameters are decreased, a reliability test should be carried out through the comparison a variety of empirical models with the upper correlation equation.

Rock Mass Rating for Korean Tunnels Using Artificial Neural Network (인공신경망을 이용한 한국형 터널 암반분류)

  • 양형식;김재철
    • Tunnel and Underground Space
    • /
    • v.9 no.3
    • /
    • pp.214-220
    • /
    • 1999
  • In this study, the validity of items of RMR system is evaluated and the applicability of this system to the data measured in Korean sites if discussed. Database was constructed from 139 sites, which are composed of subways, railway tunnels and road tunnels. These sites are located nationwide. Analysis shows that original classification of Bieniawski is valid although it was derived empirically. But it has considerable rating difference (error) in the result of Korean application. Thus new classification systems of KRMRI and KRMR2 are suggested, which are deduced from the Korean database. The former includes adjusted ratings and the latter adopts two more items. These are deduced by artificial neural network because it is difficult to select \`characteristic value'to estimate rock quality.

  • PDF

The geophysical survey and rock classification suitable for the design of a tunnel in urban area passing underneath the Gyeongbu Line(Railload) (경부선 직하부를 나란히 통과하는 도심지 터널에 있어서 지표물리탐사 및 암반등급 평가 사례 연구)

  • Lee Kun;Kim Eun-Duk;Sha Sang-Ho;Cha Young-Ho;Kim Tae-Young;Jung Doo-Suk;Hwang Nak-Yeon
    • Proceedings of the KSR Conference
    • /
    • 2005.05a
    • /
    • pp.673-679
    • /
    • 2005
  • Urban conditions such as underground facilities and ambient noises due to cultural activity restrict the application of conventional geophysical techniques in general. We used the linear array microtremor technique which uses these noises as strong energy source. The result parameter of the survey is shear wave velocity profile which had been applied as an fundamental information for the determination of the rock support type in tunnel design. This study was the first case in Korea which utilized a surface geophysical technique yielding successful result in urban area especially under the existing rail ways. The quantitative relation between the shear wave velocity from this method and the rock mass rating(RMR) determined from the inspection of the cores recovered from the same boreholes showed high statistical relationship. These correlations were then used to relate the shear-wave velocity to RMR along the entire profile.

  • PDF